JUN 03 '94 12 :58 PUBLIC WORKS GARAGE P_2 <br /> LARPBNTEUR AVENUE RECONSTRUCTION <br /> PROJECT D DEmonesumpungarAnos PROCESS <br /> TASK WEN <br /> 1. Informational Meeting(s) July, 1994 <br /> 2. Prepare and Submit Project Path Report to MnDOT /FHWA July /August, 1994 <br /> 3. Submit Categorical Exclusion September, 1994 <br /> 4. Public Hearing October, 1994 <br /> 5. Prepare and Submit Study Report to MnDOT /FHWA December, 1994 <br /> 6. Submit Right of Bay Plan to MnDOT /FHWA December, 1994 <br /> 7. Right of Way Certificate No. 1 October, 1995 <br /> 8. Complete Final Plans and Specifications October, 1995 <br /> 9. Municipalities Approve Final Plans and Specifications November, 1995 <br /> 10. Submit Final Plans and Specifications to HnDOT /FHWA December, 1995 <br /> 11. Advertise /distribute Plans and Specifications for bidding February, 1996 <br />