Laserfiche WebLink
ATTACHMENT "B" <br /> LARPENTEUR RECONSTRUCTION <br /> PROJECT DEVELOPMENT/IMPLEMENTATION PROCESS <br /> 1. Informational Meeting(s) Jul 1994 <br /> 2. Prepare and Submit Project Path Report to MnDOT /FHWA Jul /Aug 1994 <br /> 3. Submit Categorical Exclusion Sep 1994 <br /> 4. Public Hearing Oct 1994 <br /> 5. Prepare and Submit Study Report to MnDOT /FHWA Dec 1994 <br /> 6. Submit Right -Of -Way Plan to MnDOT /FHWA Dec 1994 <br /> 7. Right -Of -Way Certificate No. 1 Oct 1995 <br /> 8. Complete Final Plans and Specifications Oct 1995 <br /> 9. Municipalities Approve Final Plans and Specifications Nov 1995 <br /> 10. Submit Final Plans and Specifications to MnDOT /FHWA Dec 1995 <br /> 11. Advertise /Distribute Plans and Specifications for Bidding Feb 1996 <br />