HomeMy WebLinkAboutCCRes_85-33RESOLUTION R-85-33
Member Chenoweth introduced the following
resolution and moved its adoption:
RESOLUTION ORDERING TATUM STREET IMPROVEMENTS
OF 1985 AND DIRECTING PREPARATION OF FINAL PLANS
AND SPECIFICATIONS
WHEREAS, after due Notice of Public Hearing on the
construction of storm sewer and street improvements for the
City of Falcon Heights, Minnesota, hearing on said improvements
was duly held and the Council heard all persons desiring to be
heard on the matter and fully considered the same;
NOW THEREFORE, BE IT RESOLVED by the City Council of the
City of Falcon Heights, Minnesota as follows:
1. It is advisable, expedient and necessary that said
improvements as described in the Notice of Hearing thereon be
constructed, and the same are hereby ordered made.
2. The improvements described in said Notice of Hearing
are hereby designated and shall be known as Tatum Street
Improvements of 1985.
3. The consulting engineers, Boonestroo, Rosene,
• Anderlick & Associates, are hereby directed to prepare final
plans and specifications for said improvements.
4. The City Council shall let the contract for all or
part of the work for said improvements or order all or part of
the work done by day labor or otherwise as authorized by
Minnesota Statutes, Section 429.041, Subdivision 2 within one
year of the date of this resolution ordering said improvements.
The motion for the adoption of the foregoing resolution
was duly seconded by member Ciernia and upon a
vote being taken thereon, the following voted in avor thereof:
Mayor Eggert, Councilmembers Hard, Ciernia and Chenoweth
and the following voted against the same: None.
~rThereupon said resolution was declared duly passed and
adopted.
Regular City Council Meeting of June 26, 1985
•
C
NOTICE OF PUBLIC HEARING ON IMPROVEMENTS
TO WHOM IT MAY CONCERN:
DATE AND TIME: NOTICE IS HEREBY GIVEN that at 8:00 p.m.
on June 12, 1985 at City Hall, 2077
West Larpenteur Avenue, Falcon Heights,
Minnesota a public hearing will be held
to consider improvements on Tatum Street.
IMPROVEMENTS: Such improvements shall include the
installation of storm sewer and street
reconstruction on Tatum Street.
r~
U
COST: The estimated cost to Falcon Heights of
the improvements is $493,320. The area
to be assessed includes the following
parcels as identified by the Ramsey County
Assessor:
AREA PROPOSED TO
BE ASSESSED: 16-29-23-24 parcels 0041 - 0070 and
0073 and 0074; 16-29-23-31 parcels
0027 - 0060.
• STATE OF MINNESOTA )
COUNTY OF RAMSEY ) gg
CITY OF FALCON HEIGHTS )
I, the undersigned, being the duly qualified and acting
Clerk-Administrator of the City of Falcon Heights, Minnesota,
DO HEREBY CERTIFY that I have compared the attached and fore-
going extract of minutes with the original thereof on file in
my office, and that the same is a full, true and complete
transcript of the minutes of a meeting of the City Council of
said City, duly called and held on the date therein indicated
insofar as such minutes relate to ordering and directing
• preparation of final plans and specifications for Tatum Street
Improvements of 1985 in said City.
WITNESS my hand and the seal of said City this 26th day
of _ June 1985.
ity Clerk- dministrator
(SEAL)
~1
L J
TATUM STREET IMPROVEMENTS
EXTRACT OF MINUTES OF MEETING OF THE
• CITY COUNCIL OF THE CITY OF
FALCON HEIGHTS, MINNESOTA
HELD: JUNE 26, 1985
Pursuant to due call and notice thereof, a regular meeting
of the City Council of the City of Falcon Heights, Minnesota, was duly
called and held at the City Hall in said City on the 26th day of June,
1985, at 7:00 P.M.
The following members were present:
Mayor Eggert, Ciernia, Hard and Chenoweth and the
following were absent: Baldwin
The meeting was held pursuant to resolution adopted April 24, 1985,
calling a public hearing on the proposed Tatum Street Improvements of 1985
in said City, as more particularly described in the Notice of a Public
Hearing ordered at said April 24, 1985 meeting, a copy of which is attached
hereto. The Clerk Administrator presented affidavits showing the due publication
and mailing of the Notices of Hearing and the Mayor announced that the Council
would hear all persons who cared to be heard for or against the improvements as
outlined in the Notice of Hearing. All persons present were afforded an opportunity
• to present their views and objections to the making of said improvements, and no
objections were presented, except as follows:
Name of Objector Property Objection
See Minutes of Public Hearing on June 12, 1985
t
MINUTES
REGULAR CITY COUNCIL MEETING/PUBLIC HEARINGS
JUNE. 12, 1985
PAGE 3
RESOLUTION R-85-24
' A RESOLUTION ORDERING THE CITY ENGINEER TO PREPARE A
FEASIBILITY STUDY AND PLANS AND SPECIFICATIONS FOR
THE LARPENTEUR AVENUE/COFFMAN STREET UTILITIES AND
STREET IMPROVEMENTS
Mayor Eggert moved, seconded by Councilmember Ciernia, that the 1985
sealcoating plans and specifications be approved, and that advertisement
for bids be authorized, bid opening to be schedule for 10:30 A.M.,
July 9, 1985. Motion carried unanimously.
At 8:00 P.M. Mayor Eggert opened the Public Hearing on the Proposed Tatum
Street Improvements and presented the Affidavits of Publication and Mailing.
He then explained that the matter has been discussed in the past and is
being considered again at this time as there are some tax .increment funds
available which could be used for the project, and those funds will only
be available for a defined period of time. Engineer Schunicht explained the
need for storm drainage and street reconstruction in the area, presented
information on the estimated cost, and emphasized the availability of tax
increment funds. Council questioned the amount of tax increment funds
indicated in the Engineer's report since the City's records indicate a
lesser amount.
Mark Ascerno, 1871 Tatum, asked if the tax increment funds are not used
for the project, but to pay off the bond issue, if the taxes would then
come back to the City. Mayor Eggert explained that tax increment financing
concept and that the approximately 12 percent of the taxes would come to the
City. Mr. Ascerno felt Tatum is not in bad shape, feared increase in traffic
and speed if the street is improved, questioned who instigated the storm sewer
project, felt that the Lindig lot owners might benefit at no cost to those
owners (and Lindig owners had already shown opposition to the storm sewer),
and felt this would not eliminate the drainage ditch on the east side of .
Tatum. Mr. Ascerno was opposed to the project and doubted that the
cost of the project would improve his property by the $2,800 he would be
assessed.
Jim Colton, 1760 Tatum, stated he was not fond of the idea due to traffic
and danger to children, but he did feel the time was coming when people
will be asking Council to improve the street. He also stated that the
availability of the tax increment funds gave him a different outlook on
the matter. He then asked if the drainage ditch would be removed to
which Engineer Schunicht replied that a Swale would still be necessary
but the depth of the area could be reduced. The storm sewer would be
constructed to handle a five year storm, which would be a definite benefit
to the area.
Roger Morris, 1920 Roselawn, indicated he opposed the project as it was
premature, unnecessary and unjustified. He commented on the number
of children in the area, problem of increased traffic, reduced property
values, the fact that the area is semi-rural and should stay that way.
He recommended that Council delay the improvement until the last possible
moment it could be used. He then inquired about his right to appeal.
Attorney Van de North replied he could take the City to court and attempt
RESOLUTION
R-85-24
PLANS AND
SPECS FOR
1985 SEAL-
COATING
APPROVED
PUBLIC
HEARING ON
PROPOSED
TATUM STREET
IMPROVEMENTS
MARK ASCERNO
1871 TATUM
JIM COLTON,
1760 TATUM
ROGER MORRIS
1920 ROSE-
LAWN
MINUTES
REGULAR CITY COUNCIL MEETING/PUBLIC HEARINGS
JUNE 12, 1985
PAGE 4
• to prove that Council is arbitrary and capricious, and stressed that
Council must consider broader interests of the community. He explained
that there are specific procedures to be followed in objecting to an
assessment. Engineer Schunicht explained that the cost of the project
could increase from the proposed $2,800 to as much as $6,000 if tax
increment funds are not utilized. He stated that the new street might
draw a little more traffic (10 to 15 cars) but traffic patterns are already
established. He felt that with the street being only 32 feet wide and with
many parked cars, that speed should not increase greatly, the speed
limit would remain the same and would be enforced.
Florian Lauer, 1736 Tatum, asked if all areas in the City have storm
sewers, if not, why not? He felt there was not a need for it. Engineer
Schunicht explained that most of Falcon Heights is sewered (exceptions are
Tatum, Lindig, Fairview, St. Mary's, the north end of Fry, and U of MN land).
He explained that the longevity of streets improves with storm sewer as the
salty snow runs off instead of standing on the street.
E. J. Kemmer, 1768 Tatum, asked how Council would like the neighbors run-
off water pouring onto their lots, that the drainage in the area is poor,
and commented on the lots on Lindig in the "no build" area.. Mr. Kemmer
stated he also would like to see the speed slowed down on Tatum and
suggested dips in the street. ,He stated he was in favor of the storm
sewer but would not like to see traffic speed up.
Myles Aikin, 1849 Tatum, inquired how wide the street would be and how
driveway grades would be affected. Engineer Schunicht replied the
street would be 32 feet wide and driveways would be restored to match
the street. Mr. Aiken also commented on speed and increase in traffic,
but felt ultimately something would have to be done with the street. He
was undecided as to whether or not he was for the project.
Mr. Aiken ased if it would be possible to put stop signs in the street
to slow traffic to which the Engineer replied that stop signs in the
middle of streets do not work well, people trust them and a strange
driver might not expect them and run the sign. Mayor Eggert commented
on the fact that the stop signs placed on Garden to slow traffic have
not been effective, more run the signs than stop.
John Labalestra, 1712 Tatum, asked if residential taxes would increase
due to the improvements to which Mayor Eggert replied in the negative.
Mr. Labalestra expressed conern over the possible increase in traffic,
and speed. He felt the street did not need immediate repair, perhaps
would in three or four years, and recommended the funds be invested
rather than using them for street repair at this time.
George Kilgriff, 1739 Tatum, was concerned that a street 36 feet wide
would be constructed with parking only on one side, or a 32 foot
street with no parking as was considered a few years ago. Mr. Schunicht
explained that at the time Tatum was a MN State Aid Street, and those
requirements were stipulated by State criteria. Mr. Kemmer also asked
the cost of grading and sealcoating the street with no curb and gutters,
and was informed it would be about $14.00 per foot. Mayor Eggert added
that it is the City's policy to add curb and gutter when streets are
reconstructed to increase the life of the street. Engineer Schunicht
FLORIAN
LAUER,
1736 TATUM
E . J . KEMMER
1768 TATUM
MYLES AIKIN,
1849 TATUM
JOHN
LABALESTRA,
1712 TATUM
GEORGE
KILGRIFF,
1739 TATUM
MINUTES
REGULAR CITY COUNCIL MEETING/PUBLIC HEARINGS
JUNE 12, 1985
PAGE 5
• indicated it would add approximately five years to the street.
Mayor Eggert then read into the record a letter from Harold C. Nilsen, HAROLD C.
1794 Tatum, indicating that he is strongly in favor of the project and NILSEN,
urged Council to go ahead, 1794 TATUM
John Janasek, 1808 Tatum, asked if it was possible to allow the Tatum JOHN JANASEK
residents to vote on the project rather than Council and Mayor Eggert 1808 TATUM
explained how improvement projects are instigated: (1) recommendation
by City Engineer, or (2) petition by homeowners. Mr. Janasek felt there
are many who are reluctant to give an opinion, but if they had a private
ballot could give an honest answer, Mr. Janasek wanted it to go through,
as the street is breaking up, but he felt it was due to poor patching.
Choonig-Schn Youn, 1742 Tatum, felt the street was not bad and he opposed CHOONIG-
the project as he was concerned for the safety and welfare of the SCHN
neighbors. He felt it would not improve the property and asked that YOUN, 1742
Council wait. TATUM
Donald Ledin, 1834 Tatum, asked if the double lots would be charged DONALD
double, and it was explained that the second area would be charged LEDIN,
only if the second phase (Lindig storm sewer) were implemented. Mr. 1834 TATUM
Ledin stated there is not much•flooding where he lives, and that
he is concerned for safety of small children. Mr. Ledin explained
that he was opposed to the project at the present time, just because
there are funds available should not be the primary reason.
Maxine Harkness, 1879 Tatum, stated she and her husband, Leonard, are MAXINE
in favor of the project, as they felt it was time something should be HARKNESS,
done for the neighbors who have suffered from water problems over the 1879 TATUM
years. She then asked if the storm sewer would correct the ponding of
water at Larpenteur and Tatum and Engineer Schunicht replied in the
affirmative.
Hans Schirrmeister, 1779 Tatum, asked if all homes on Tatum are connected HANS
to natural gas, to which the Engineer replied that if gas has not been SCHIRRMEISTE:
installed, it will be stubbed in when the street is under construction. 1779 TATUM
Mr. Schirrmeister commented on the fact that there have been drainage
problems for some time and he was in favor of the project.
Pam Hove, 1905 Tatum, informed that they had recently had natural gas PAVE HOVE,
installed and were told at that time that Northern States Power plans 1905 TATUM
to install new meters at all locations. Ms. Hove was undecided as to
the proposed Tatum project.
Meredith Hill, 1804 Tatum, stated she was ambivalent; however, did not MEREDITH
think her property justified a $2,800 investment, even though she agreed HILL, 1804
the street needs repair. She expressed concern for the safety of children TATUM
in the neighborhood.
Florian Lauer, 1736 Tatum, asked if in areas where there are no storm FLORIAN
sewers at present, if they will be installed if streets are improved, LAVER,
and Engineer Schunicht replied in the affirmative. 1736 TATUM
MINUTES
REGULAR CITY COUNCIL MEETING/PUBLIC HEARINGS
JUNE 12, 1985
PAGE 6
Mark Ascerno, 1871 Tatum, expressed concern that speed would increase MARK
and suggested making Tatum a dead end street (perhaps in the middle), ASCERNO,
and asked that Council delay implementation of the project until the 1871 TATUM
end of the tax increment period and invest the funds until that time.
Myles Aiken, 1849 Tatum, asked if the sewer would go down the side of MYLES
the street, to which Engineer Schunicht replied that the contractor will AIKEN,
determine the method. Mr. Aiken felt they owe the neighbors drainage 1849 TATUM
and would be in favor of the project.
Roger Morris, 1920 Roselawn, felt that with the rise in number of houses ROGER MORRIS
in the area, there is more traffic on Tatum, and there might be a 1920 ROSE-
dramatic increase if the street is improved. He also felt a double LAWN
dead end might be appropriate. Engineer Schunicht suggested the residents
petition if they felt a need for the dead end.
Florian Lauer, 1736 Tatum, stated it would help if Council would give
more information early in discussing project, such as explaining that
storm sewers are being added to all unsewered streets which are being
reconstructed.
There being no others wishing to be heard, Mayor Eggert closed the public
hearing at 9:19 P.M.
FLORIAN
LAUER,
1736 TATUM
PUBLIC HEART
CLOSED
Mayor Eggert suggested that persons who would like to be heard but are WRITTEN
uncomfortable about speaking be allowed to respond in writing within COMMENTS TO
the next 72 hours. After a short discussion, Mayor Eggert moved, seconded BE TAKEN
by Councilmember Hard, that written public comments be taken until UNTIL 6/14/8
4:30 P.M. on June 14, 1985. Motion carried unanimously.
Council then directed the Fiscal Consultant to review the tax increment
financing plan and program and determine the exact amount of funds
available, directed the City Attorney to obtain guidelines on investing
tax increment funds, and directed the City Engineer to determine if
the project could be completed by the end of October. The matter will
be placed on the June 26, 1985 agenda for discussion.
Councilmember Baldwin commented on the fact that with stop signs affects
air quality and creates noise, he felt policing is the important item.
He also stressed that any vote by the citizens would be advisory only.
Mayor Eggert commented on the discrepancy in the bottom line number on
funds in the tax increment account, and asked that an accounting be
provided Councilmembers. He also requested information on what other
bonding authority the City may have.
Engineer Karen Willis presented plans and specifications for the
Larpenteur/Coffman improvements and explained the same. Councilmember
Chenoweth moved, seconded by Mayor Eggert, that Resolution R-85-25
be adopted. Motion carried unanimously.
RESOLUTION R-85-25
A RESOLUTION ACCEPTING AND APPROVING THE FEASIBILITY
STUDY, AND PLANS AND SPECIFICATIONS, AND AUTHORIZING
ADVERTISEMENT FOR BIDS FOR THE LARPENTEUR/COFFMAN
IMPROVEMENTS
DEFERRED TO
/26/85
RESOLUTION
R-85-25