HomeMy WebLinkAbout09 1871LarpenteurPUD - TimetableTHE FIELDS 1871 Larpenteur Avenue PRELIMINARY SCHEDULE Pre-construction 45 -60 Days Site Development 45 -60 Days Footing -Foundation 20 -30 Days Building Structure 30 -40 Days Exterior
Finishes 35 45 Days Interior Finish 50 -60 Days Landscaping 15 -20 Days Estimated time frame 160 -180 days. ???????