CITY OF <br />LITTLE CANADA 2003 Street Reconstruction & Utility Improvements <br />Issue No. 2 -July 31, 2003 <br />Proposed Construction/Tenative Schedule <br />The Contractor anticipates beginning the installation of a steel casing pipe under the St. Paul Water <br />pipes on Monday August 4, 2003. The installation of the steel casing pipe will not affect access to <br />Sextant Avenue or Arkwright Street. However, the following day, Tuesday, August 5, 2003 the <br />Contractor will begin the sanitary sewer replacement, watermain, storm sewer, and street sub-grade <br />work on Sextant Avenue. This work will begin east of the cul-de-sac and progress to the west in <br />approximately 300-foot sections. All utility and street sub-grade work will be completed in an area <br />prior to moving to the next section to the west. Aline of barricades will be placed on Sextant Avenue <br />indicating the west end of the construction area. Access will be limited east of the barricade line as <br />described below in the "Access" section of the newsletter. <br />As with any construction work, the schedule and completion of the project will beC ~-~('~ <br />somewhat dependent on the weather. If we have any significant precipitation, the ~J~ <br />construction site may need to dry out prior to continuing work. We ask for your ~ .:,,, - } <br />patience with weather delays throughout this project. ~ '%'~~~/i <br />,, ,~,., <br />We urge you to use caution around the work site. Your assistance in reminding area children to stay <br />r clear of construction equipment is helpful in maintaining a safe environment. Your patience and <br />cooperation during this construction will be appreciated. Watch for future issues of this <br />newsletter for updates on the progress of the project. <br />Access <br />In order to minimize the time necessary for utility installation and inconvenience to residents, there will <br />be no access to driveways east of the barricade line on Sextant Avenue weekdays between <br />7:00 a.m. and 7:00 p.m. During this time residents will need to park in a temporary parking area near <br />the intersection of Arkwright Street and Sextant Avenue and walk to and from their homes. Access to <br />all driveways will normally be available between 7 p.m. and 7 a.m. during weekdays and on <br />weekends. Emergency vehicle access will be maintained at all times. <br />Temporary mailboxes will be place on Arkwright Street north of Sextant Avenue for mail delivery <br />during construction. Garbage and recycling should be placed at the end of driveways as normal. The <br />Contractor will be responsible for taking the containers outside the job site for pickup and bring them <br />back to each driveway. <br />New Water Service Locations <br />As part of the project, water services will be installed to the property lines of lots that currently do not <br />have water service. Residents will be given a lath with the words "Water Service" written on it. <br />Please place the lath in the approximate location, along your front lot line, that you would like your <br />water service to be installed. <br />uestions <br />Property owners with questions about the project should call Howard R. Green Company's <br />representatives -Lee Elfering, City Engineer, at (651) 644-4389, or Lyle Splittstoser, Project <br />Inspector, at {651) 341-3519, for construction related questions. Feel free to talk to either <br />of these individuals about issues or concerns you may haye about the project. <br />0 000 <br />0 00 <br />