ITEM SPEC.
<br />NO. REF.ITEM DESCRIPTION UNIT QTY.UNIT PRICE QTY.TOTAL PRICE QTY.TOTAL PRICE
<br />ORIGINAL CONTRACT THIS PERIOD TOTAL TO DATE
<br />36 2582.502 4" DOUBLE SOLID EPOXY LF 4,125.00 $0.54 0.00 $0.00 3909.00 $2,110.86
<br />37 2582.502 24" STOP LINE EPOXY LF 54.00 $6.96 0.00 $0.00 78.60 $547.06
<br />38 2582.503 CROSSWALK MARKING EPOXY SF 145.00 $4.39 0.00 $0.00 90.00 $395.10
<br />SCHEDULE 2.0 - COUNTRY DRIVE - TOTAL $0.00 $683,953.61
<br />SCHEDULE 3.0 - CENTERVILLE ROAD
<br />1 2021.501 MOBILIZATION LS 1.00 $99,795.00 0.00 $0.00 1.00 $99,795.00
<br />2 2101.501 CLEARING ACRE 0.44 $1,606.25 0.00 $0.00 0.82 $1,317.13
<br />3 2101.502 CLEARING TREE 36.00 $214.17 0.00 $0.00 45.00 $9,637.65
<br />4 2101.506 GRUBBING ACRE 0.44 $1,606.25 0.00 $0.00 0.48 $771.00
<br />5 2101.507 GRUBBING TREE 36.00 $107.08 0.00 $0.00 60.00 $6,424.80
<br />6 2104.501 REMOVE CONCRETE CURB LF 587.00 $7.33 0.00 $0.00 793.00 $5,812.69
<br />7 2104.501 REMOVE WATERMAIN LF 87.00 $22.49 0.00 $0.00 64.00 $1,439.36
<br />8 2104.501 REMOVE SEWER PIPE (STORM)LF 135.00 $19.28 0.00 $0.00 141.00 $2,718.48
<br />9 2104.501 REMOVE WATER SERVICE PIPE LF 60.00 $22.49 0.00 $0.00 119.00 $2,676.31
<br />10 2104.505 REMOVE CONCRETE PAVEMENT SY 88.00 $22.13 0.00 $0.00 221.80 $4,908.43
<br />11 2104.505 REMOVE BITUMINOUS PAVEMENT SY 17,186.00 $2.35 0.00 $0.00 17344.00 $40,758.40
<br />12 2104.509 REMOVE SIGN EACH 35.00 $26.77 0.00 $0.00 0.00 $0.00
<br />13 2104.509 REMOVE DRAINAGE STRUCTURE EACH 2.00 $803.13 0.00 $0.00 3.00 $2,409.39
<br />14 2104.509 REMOVE HYDRANT AND VALVE EACH 4.00 $1,873.97 0.00 $0.00 4.00 $7,495.88
<br />15 2104.511 SAW CUT CONCRETE (FULL DEPTH)LF 110.00 $6.14 0.00 $0.00 85.00 $521.90
<br />16 2104.513 SAW CUT BITUMINOUS (FULL DEPTH)LF 800.00 $2.25 0.00 $0.00 1327.00 $2,985.75
<br />17 2104.521 SALVAGE FENCE LF 1,350.00 $4.82 0.00 $0.00 1423.00 $6,858.86
<br />18 2104.523 SALVAGE MAILBOXES EACH 26.00 $37.48 0.00 $0.00 28.00 $1,049.44
<br />19 2105.501 COMMON EXCAVATION (P)CY 11,434.76 $17.00 0.00 $0.00 11174.00 $189,958.00
<br />20 2105.501 COMMON EXCAVATION (P) (DITCH GRADING)CY 731.86 $15.00 0.00 $0.00 731.86 $10,977.90
<br />21 2105.511 POND EXCAVATION (P)CY 3,375.20 $15.00 0.00 $0.00 3375.20 $50,628.00
<br />22 2112.604 SHOULDER PREPARATION (6")SY 1,100.00 $6.63 0.00 $0.00 1224.00 $8,115.12
<br />23 2131.502 CALCIUM CHLORIDE GAL 4,600.00 $0.50 0.00 $0.00 2000.00 $1,000.00
<br />24 2211.501 AGGREGATE BASE, CLASS 5 TON 12,525.00 $13.66 0.00 $0.00 14621.39 $199,728.19
<br />25 2211.501 AGGREGATE BASE, CLASS 5 (TRAIL AND SIDEWALK)TON 575.00 $19.00 0.00 $0.00 384.73 $7,309.87
<br />26 2215.501 FULL DEPTH RECLAMATION (7" FULL DEPTH & GRADING)SY 3,125.00 $2.49 0.00 $0.00 3125.00 $7,781.25
<br />27 2215.501 FULL DEPTH RECLAMATION (7" SFDR)SY 3,125.00 $2.75 0.00 $0.00 3125.00 $8,593.75
<br />28 2232.501 MILL BITUMINOUS SURFACE (2")SY 2,300.00 $3.48 0.00 $0.00 2050.00 $7,134.00
<br />29 2232.501 MILL BITUMINOUS SURFACE (PROFILE MILL 2")SY 2,200.00 $3.36 0.00 $0.00 1930.00 $6,484.80
<br />30 2331.609 BITUMINOUS MATERIAL FOR MIXTURE TON 40.00 $452.13 0.00 $0.00 50.82 $22,977.25
<br />31 2360.501 TYPE SP 12.5 WEARING COURSE MIX. SPWEB340E TON 265.00 $86.51 0.00 $0.00 306.40 $26,506.66
<br />32 2360.501 TYPE SP 12.5 WEARING COURSE MIX. SPWEB340C TON 6,550.00 $61.28 0.00 $0.00 6123.35 $375,238.89
<br />33 2360.501 TYPE SP 12.5 WEAR COURSE MIX. SPWEB340E (EDGERTON)TON 245.00 $82.28 0.00 $0.00 254.07 $20,904.88
<br />34 2360.501 TYPE SP 9.5 WEARING COURSE MIXTURE (TRAIL)TON 110.00 $68.96 0.00 $0.00 25.66 $1,769.51
<br />35 2360.501 TYPE 12.5 WEARING COURSE MIXTURE (DRIVEWAY)TON 264.00 $95.84 0.00 $0.00 480.88 $46,087.54
<br />36 2501.602 21" FES W/TRASHGUARD EACH 1.00 $2,527.18 0.00 $0.00 1.00 $2,527.18
<br />3 of 7
|