April 2014 <br /> <br /> For all disturbed areas that sheet flow to MnDOT right-of-way and any disturbed <br />areas within MnDOT right-of-way, either Erosion Control Mat or Bonded Fiber <br />Matrix shall be used for temporary/permanent erosion control. <br /> <br /> Silt fence shall not be used for erosion control at the proposed project site <br />perimeter. Rather, continuous Wood Chip or compost Sediment Control Logs <br />shall be implemented. <br /> <br />Permit applicants are encouraged to contact MnDOT Metro Water Resource Engineering <br />with questions/concerns. Questions posed early in the permit application process help to <br />avoid project delays. This is particularly true for large project Drainage Permits with <br />significant complexity. <br />