<br />Prepared by: Bolton & Menk, Inc. Estimated Costs <br />Twin Lake Boulevard ǀ 0N1.125376 Page 9 <br /> <br />ESTIMATED COSTS <br />The estimated project cost to complete the improvements proposed herein are presented below. These <br />costs include estimated construction costs, a 15% factor for contingency, a 20% factor for engineering <br />and construction administration, and allowances for geotechnical investigations and other indirect costs, <br />and are split between the City of Little Canada and the City of Vadnais Heights. <br />These cost estimates are based upon public construction cost information. Since the consultant has no <br />control over the cost of labor, materials, competitive bidding process, weather conditions, and other <br />factors affecting the cost of construction, all cost estimates are opinions for general information of the <br />client and no warranty or guarantee as to the accuracy of construction cost estimates is made. It is <br />recommended that costs for project financing should be based upon actual, competitive bid prices with <br />reasonable contingencies. <br />Table 2: Estimated Cost Summary <br />Item Total Estimated <br />Cost* <br />City of Little Canada City of Vadnais <br />Heights <br />Streets $1,360,681 $667,033 $693,647 <br />Sanitary Sewer $28,290 $20,079 $8,211 <br />Water Main $66,654 $36,570 $30,084 <br />Storm Sewer $126,684 $63,342 $63,342 <br />Trail $801,991 $400,996 $400,996 <br />Total $2,384,300 $1,188,020 $1,196,280 <br />*See Appendix B for Detailed Cost Estimate <br />