Contractor's Application for PaymentOwner's Project No.:Engineer's Project No.:Agency's Project No.:4 From09/01/23to 09/21/23A C D E F F1 F2 G H I J K LItem Quantity UnitsUnit Price($)Value of Bid Item(C X E)($)Quantity Previous EstimateValue Previous EstimateEstimated Quantity Incorporated in the WorkValue of Work Completed to Date(E X G)($)1 1.00 LS 43,600.00 43,600.00 1.00 43,600.00 1.00 43,600.00 43,600.00 100% - 2 51.00 EACH 220.00 11,220.00 51.00 11,220.00 51.00 11,220.00 11,220.00 100% - 3 14.00 EACH 95.28 1,333.92 14.00 1,333.92 14.00 1,333.92 1,333.92 100% - 4 14.00 EACH 40.12 561.68 - - - - - 561.68 5 430.00 LF 2.67 1,148.10 397.00 1,059.99 397.00 1,059.99 1,059.99 92% 88.11 6 470.00 LF 2.67 1,254.90 432.00 1,153.44 432.00 1,153.44 1,153.44 92% 101.46 7 80.00 LF 5.00 400.00 113.00 565.00 113.00 565.00 565.00 141% (165.00)8 240.00 SY 7.74 1,857.60 439.00 3,397.86 439.00 3,397.86 3,397.86 183% (1,540.26)9 70.00 SY 17.12 1,198.40 72.00 1,232.64 72.00 1,232.64 1,232.64 103% (34.24)10 30.00 SY 15.69 470.70 16.00 251.04 16.00 251.04 251.04 53% 219.66 11 10.00 SY 28.34 283.40 - - - - - 283.40 12 27.00 SY 15.69 423.63 43.00 674.67 43.00 674.67 674.67 159% (251.04)13 1,850.00 LF 3.27 6,049.50 2,616.00 8,554.32 2,616.00 8,554.32 8,554.32 141% (2,504.82)14 1,193.00 CY 22.22 26,508.46 1,849.00 41,084.78 1,849.00 41,084.78 41,084.78 155% (14,576.32)15 210.00 CY 30.35 6,373.50 - - - - - 6,373.50 16 344.00 CY 6.05 2,081.20 1,153.00 6,975.65 1,153.00 6,975.65 6,975.65 335% (4,894.45)17 1,655.00 CY 9.38 15,523.90 1,175.00 11,021.50 1,175.00 11,021.50 11,021.50 71% 4,502.40 18 330.00 CY 21.69 7,157.70 - - - - - 7,157.70 19 210.00 CY 30.71 6,449.10 - - - - - 6,449.10 20 752.00 CY 13.89 10,445.28 1,109.00 15,404.01 1,109.00 15,404.01 15,404.01 147% (4,958.73)21 16,800.00 SY 2.76 46,368.00 16,880.00 46,588.80 16,880.00 46,588.80 46,588.80 100% (220.80)22 7,100.00 LF 0.71 5,041.00 - - - - - 5,041.00 23 860.00 GAL 2.01 1,728.60 - - 125.00 251.25 251.25 15% 1,477.35 24 1,590.00 TON 98.00 155,820.00 3.60 352.80 3.60 352.80 352.80 155,467.20 25 70.00 TON 225.00 15,750.00 - - 79.00 17,775.00 17,775.00 113% (2,025.00)26 1,590.00 TON 95.00 151,050.00 - - 1,341.00 127,395.00 127,395.00 84% 23,655.00 27 7,100.00 LF 16.75 118,925.00 6,914.00 115,809.50 6,914.00 115,809.50 115,809.50 97% 3,115.50 28 2,100.00 LF 13.91 29,211.00 2,111.00 29,364.01 2,111.00 29,364.01 29,364.01 101% (153.01)29 195.00 SY 69.69 13,589.55 108.00 7,526.52 108.00 7,526.52 7,526.52 55% 6,063.03 30 45.00 SY 123.05 5,537.25 - - - - - 5,537.25 31 174.00 SY 196.93 34,265.82 - - - - - 34,265.82 32 10.00 SY 62.61 626.10 - - - - - 626.10 33 14.00 EACH 145.42 2,035.88 - - - - - 2,035.88 34 1.00 LS 2,808.15 2,808.15 0.75 2,106.11 0.75 2,106.11 2,106.11 75% 702.04 35 14.00 EACH 225.66 3,159.24 - - - - - 3,159.24 36 64.00 SF 58.17 3,722.88 - - - - - 3,722.88 37 1.00 LS 3,225.26 3,225.26 - - - - - 3,225.26 38 40.00 HR 1.00 40.00 - - - - - 40.00 39 22.00 EACH 149.93 3,298.46 27.00 4,048.11 27.00 4,048.11 4,048.11 123% (749.65)40 500.00 LF 3.17 1,585.00 1,562.00 4,951.54 1,562.00 4,951.54 4,951.54 312% (3,366.54)41 500.00 CY 38.57 19,285.00 - - - - - 19,285.00 42 3,280.00 SY 1.93 6,330.40 - - - - - 6,330.40 43 2,860.00 SY 1.93 5,519.80 - - - - - 5,519.80 44 280.00 SY 5.63 1,576.40 - - - - - 1,576.40 45 370.00 SY 8.70 3,219.00 - - - - - 3,219.00 46 160.00 MGAL 97.18 15,548.80 14.00 1,360.52 14.00 1,360.52 1,360.52 9% 14,188.28 47 4,270.00 LF 0.81 3,458.70 - - - - - 3,458.70 TRM CAT 1, SEED MIX 35-241, FERTILIZERWATER FOR TURF ESTABLISHMENT4" DOUBLE PAVEMENT MARKING - PAINTSEDIMENT CONTROL LOGS, TYPE COMPOSTCOMMON TOPSOIL BORROW (LV)HYDRAULIC MATRIX TYPE MULCH, SEED MIX 25-151, HYDRAULIC MATRIX TYPE MULCH, SEED MIX 35-241, EROSION CONTROL BLANKET CAT 3N, SEED MIX 34-261, INSTALL SIGN TYPE CSIGN TYPE CEROSION CONTROL SUPERVISORSKIDSTEER WITH OPERATORSTORM DRAIN INLET PROTECTIONCONCRETE VALLEY GUTTERPAVER DRIVEWAYGRAVEL DRIVEWAYINSTALL MAILBOX & SUPPORTTRAFFIC CONTROLTYPE SP 9.5 WEARING COURSE MIXTURE (2, E] DRIVEWAYTYPE SP 12.5 NON WEARING COURSE MIXTURE (3,C)CONCRETE CURB AND GUTTER DESIGN B618CONCRETE CURB AND GUTTER DESIGN - RIBBON6" CONCRETE DRIVEWAY PAVEMENTREMOVE BITUMINOUS DRIVEWAY PAVEMENTREMOVE CONCRETE DRIVEWAY PAVEMENTINSTALL SALVAGED EXCESS RECLAIM MATERIAL (AGGREGATE FULL DEPTH RECLAMATIONJOINT ADHESIVE (MASTIC)BITUMINOUS MATERIAL FOR TACK COATTYPE SP 9.5 WEARING COURSE MIXTURE (3, C]EXCAVATION - SUBGRADE CORRECTIONCOMMON EMBANKMENTSALVAGE RECLAIM FOR REUSEHAUL EXCESS RECLAIM MATERIAL OFFSITESTABILIZING AGGREGATE - SUBGRADE CORRECTIONEXCAVATION - COMMONProgress Estimate - Unit Price WorkCity of Little CanadaBolton & Menk, Inc.OMG Midwest, Inc. Minnesota Paving & MaterialsTwin Lake Boulevard ImprovementsOwner:0N1.12537623-04Engineer:Contractor:Project:Contract:09/21/23PART 1: STREETSBBASE BID% of Value of Item (J / F)(%)Balance to Finish (F - J)($)DescriptionWork CompletedMaterials Currently Stored (not in G)($)Work Completed and Materials Stored to Date (H + I)($)Contract InformationBid Item No.SALVAGE MAIL BOX & SUPPORTSALVAGE SIGNREMOVE GRAVEL DRIVEWAYREMOVE PAVER DRIVEWAYREMOVE CONCRETE PAVEMENT (VALLEY GUTTER)REMOVE BITUMINOUS CURBSAWING BITUMINOUS PAVEMENT (FULL DEPTH)SAWING BITUMINOUS DRIVEWAY PAVEMENT (FULL DEPTH)SAWING CONCRETE DRIVEWAY PAVEMENT (FULL DEPTH)Application Date:Application Period:Application No.:MOBILIZATIONGRUBBINGPrevious EstimateUnit PriceEJCDC C-620 Contractor's Application for Payment(c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.1 of 4DocuSign Envelope ID: 5DD39E2D-55DC-46B1-8BE6-8680F879E5CB
|