<br />The city received competitive bids for the 2025 Street Improvements Project. The low bid from
<br />Minnesota Paving and Materials was 13% lower than the engineer’s estimate.
<br />
<br />The table below identifies the as-bid project costs, itemized by improvement type, with project
<br />contingency and indirect costs included.
<br />
<br />Location
<br />Feasibility
<br />Report
<br />Cost, CIP
<br />Amount
<br />As-bid
<br />Cost
<br />5%
<br />Contingency
<br />Indirect Costs
<br />Engineering,
<br />Geo,
<br />Appraisals
<br />As-Bid
<br />Estimated
<br />Total
<br />Project Cost
<br />Nadeau Road (2025-PW-41)
<br />Streets $79,805 $56,194 $2,810 $10,621 $69,624
<br />Sanitary & Water $1,760 $398 $20 $75 $493
<br />Storm Sewer $6,325 $4,964 $248 $938 $6,150
<br />Subtotal $87,890 $61,556 $3,078 $11,634 $76,267
<br />Maple Leaf Court (2025-PW-79)
<br />Streets $130,821 $84,443 $4,222 $15,960 $104,625
<br />Sanitary & Water $4,180 $3,732 $187 $705 $4,624
<br />Storm Sewer $4,620 $3,446 $172 $651 $4,270
<br />Subtotal $139,621 $91,622 $4,581 $17,317 $113,519
<br />Stoneridge Court (2025-PW-80)
<br />Streets $145,890 $124,546 $6,227 $23,539 $154,313
<br />Sanitary & Water $11,110 $6,207 $310 $1,173 $7,691
<br />Storm Sewer $61,287 $21,792 $1,090 $4,119 $27,000
<br />Subtotal $218,287 $152,545 $7,627 $28,831 $189,004
<br />Spruce Street
<br />Storm Sewer $0 $2,279 $114 $431 $2,824
<br />Spooner Lower Lot (2025-PARKS-11)
<br />Spooner Lower Lot Improvements $85,000 $71,651 $717 $13,026 $85,393
<br />Spooner Trail Repair (2025-PARKS-14)
<br />Trail Improvements $80,000 $50,504 $2,525 $9,545 $62,575
<br />Pioneer West Lot (2025-PARKS-14)
<br />Parking Lot Rehabilitation $135,000 $4,417 $221 $835 $5,473
<br />Pioneer Park (2025-PARKS-54)
<br />Vegetation Restoration $472,000 $358,457 $17,923 $67,748 $444,128
<br />Totals – Project $1,129,908 $796,545 $39,827 $150,547 $986,919
<br />
<br />SOURCE OF FUNDS:
<br />Street improvements will be funded through the City’s Infrastructure Capital Improvement Fund, and
<br />special assessments. Water and sewer improvements will be funded through the City’s Infrastructure
<br />Capital Improvement Fund. Storm sewer and drainage improvements will be funded through the City’s
<br />Stormwater Fund and Infrastructure Capital Improvement Fund. Trail improvements will be funded
<br />through the City’s Park Land Fund.
<br />
<br />STAFF RECOMMENDATIONS:
<br />• Staff recommends that the City Council approve a Motion to award 2025 Street Improvements
<br />to OMG Midwest Inc, Minnesota Paving & Materials in the amount of $796,544.75
|