Laserfiche WebLink
ENGINEER'S ESTIMATE <br />PROJECT: WATERWORKS TRAIL CROSSING <br />OWNER: CITY OF LITTLE CANADA <br />ENGINEER: ELFERING AND ASSOCIATES <br />ITEM <br />•, <br />NO. <br />REF. <br />SCHEDULE 1.0 • WATERWORKS TRAIL CROSSING <br />1 2021.501 MOBILIZATION L3 1.00 <br />2 2101.501 CLEARING SF 2.275.00 <br />3 2101.502 CLEAR TREE 1.00 <br />4 2101.506 GRUBBING SF 2,275.00 <br />5 2101.507 GRUB TREE 1.00 <br />6 2104.501 REMOVE CONCRETE CURB AND GUTTER LF 20.00 <br />7 2104.501 REMOVE CHAIN LINK FENCE LF 50.00 <br />8 2104.505 REMOVEBITUMIPIOUS PAVEMENT SY 5,00 <br />9 2104.523 SALVAGE SIGN EACH 1.00 <br />10 2105.501 COMMON EXCAVATION (P) CY 395.00 <br />11 2105.521 GRANULAR BORROW (CV) CY 1,136.00 <br />12 2105.525 TOPSOIL BORROW CY 100.00 <br />13 2105.604 GEOTEXTILE FABRIC SY 800.00 <br />14 2211.501 AGGREGATE BASE CLASS 5 TON 510.00 <br />15 2350.501 TYPE M1/4 WEAR COURSE MIXTURE TON 90.00 <br />16 2411.604 MODULAR BLOCK RETAINING WALL SF 205.00 <br />17 2503.603 12" DUAL WALL HOPE PIPE SEWER LE 65.00 <br />18 2521.501 4" CONCRETE SIDEWALK SF 80.00 <br />19 2531.501 CONCRETE CURB & GUTTER SPECIAL LF 20,00 <br />20 2531.618 TRUNCATED DOMES 3F 12,00 <br />21 2557 603 INSTALL CHAIN LINK FENCE LE 450.00 <br />22 2557.603 INSTALL STEEL RAIL SAFETY FENCE LF 107.00 <br />23 2564.531 F & I SIGN PANEL, TYPE 0 SF 8.00 <br />24 2564.602 F & I SIGN POST EACH 2.00 <br />25 2564,602 INSTALL SALVAGED SIGN EACH 1.00 <br />28 2573.502 SILT FENCE, TYPE MACHINE SLICED LF 910.00 <br />27 2575.604 SEEDING (TYPE 270) SY 3,900.00 <br />28 2582.503 12" X 8' WHITE STRIPE - EPDXY EACH 2.00 <br />29 2582.503 RR CROSSING STRIPING - EPDXY EACH 2.00 <br />30 SPEC WORK BY MINNESOTA COMMERCIAL LS 1.00 <br />UNIT PRICE <br />(s) • <br />53,500,00 <br />50.50 <br />5120.00 <br />50.50 <br />535.00 <br />52.50 <br />510.00 <br />55.00 <br />$50.00 <br />520.00 <br />514.00 <br />530.00 <br />32.00 <br />318.00 <br />579.00 <br />525.00 <br />530.00 <br />315.00 <br />515.00 <br />533.00 <br />510.00 <br />570.00 <br />525.00 <br />575.00 <br />5100.00 <br />$2.00 <br />50.90 <br />5150.00 <br />5150.00 <br />56,086.92 <br />TOTAL; COST ;.. <br />53,500.00 <br />51,137.50 <br />5120,00 <br />51,137.50 <br />335.00 <br />350 00 <br />3500.00 <br />525.00 <br />850.00 <br />57,900.00 <br />515,904.00 <br />$3,000,00 <br />51.600.00 <br />59,180.00 <br />57,110.00 <br />$5,125.00 <br />51,950.00 <br />31 200.00 <br />3300.00 <br />5398.00 <br />34,500.00 <br />513,090.00 <br />5200.00 <br />5150.00 <br />3100.00 <br />31,820.00 <br />53,510,00 <br />5300.00 <br />5300.00 <br />56,086.92 <br />SCHEDULE 1.0 - WATERWORKS TRAIL CROSSING -- TOTAL $90,276.92 <br />SCHEDULE 2.0- TRAIL REPLACEMENTS <br />1 2021.501 MOBILIZATION LS 1.00 51,500,00 51,500.00 <br />2 2104,505 REMOVE BITUMINOUS PAVEMENT SY 350.00 55.00 31.750.00 <br />3 2105.501 COMMON EXCAVATION (P) CY 145.00 320.00 32,900.00 <br />4 2105.525 TOPSOIL BORROW CY 30.00 630.00 3900.00 <br />5 2105.604 GEOTEXTILE FABRIC SY 590.00 52.00 51,180.00 <br />6 2211.501 AGGREGATE BASE CLASS 5 TON 335.00 518.00 56,030.00 <br />7 2350.501 TYPE MV4 WEAR COURSE MIXTURE TON 60.00 579.00 54,740.00 <br />8 2503.511 12" DUCTILE IRON PIPE SEWER LF 20.00 535.00 5700.00 <br />9 2575.604 SEEDING (TYPE 270) SY 4,100.00 50.90 33,690.00 <br />SCHEDULE 2.0 - TRAIL REPLACEMENTS - TOTAL 523,390.00 <br />CONSTRUCTION TOTAL <br />30% ENGINEERING & ADMINISTRATION <br />$113,666.92 <br />534,100.08 <br />'I'Ol'AL PROJECT COST' 5147,767,00 <br />BNSF Railroad will also require one of their flagman be present when work is being completed within its right -ot -way. The cost of the flagman is estimated at <br />5800.00 per day and is not included in the total project cost number. <br />E119!1101 s Esi,r »te 061711 <br />3 <br />400-1A <br />