Laserfiche WebLink
Municipal Consent Law <br />Minnesota Statues 161.162 to 161.167 <br />Process Diagram <br />Mn/DOT submits final layout and project report to city <br />Within 15 days of receiving final Layout, city schedules <br />public hearing <br />•hearing must be conducted within 60 days of receiving <br />final layout. <br />*city will provide at Least 30 day notice of public hearing <br />Within 90 days <br />of hearing ... <br />City approves Yes <br />final layout or <br />takes no action?, <br />Refer final layout to <br />an Appeal Board. <br />See Sections <br />161.164- 161 -167 <br />for more information <br />on the appeal <br />process. <br />No <br />yir No (i.e., city disapproves) <br />Mn/DOT <br />decides to <br />proceed ? <br />r Yes <br />City <br />requested <br />changes <br />made ? <br />• <br />Prepare final <br />construction plans <br />es <br />Changes in final v, No <br />construction plan <br />access, capacity, <br />• r /w? <br />Yes <br />1 <br />Resubmit changed <br />portion of layout to city <br />for approval <br />http: / /www. dot. state. mn. us /tecsu p /xyz /pl u /hpd p /book3 /2f /local/mu n i /process. pdf <br />January 23, 2003 <br />Send final construction <br />plan to city at least 45 <br />days before letting for <br />information <br />Let project <br />