Laserfiche WebLink
CHANGE ORDER NUMBER 1 <br />CITY OF LITTLE CANADA <br />1999 STREET RECONSTRUCTION PROJECT <br />Following our descriptions of the various change order items encountered in the 1999 Street <br />Reconstruction Project. <br />1. Install fiber optic cable along Viking Drive as per Mn /DOT. 4,000 linear feet at $10.50 per <br />linear foot. <br />Total lump sum addition for this item is $42,000. <br />2. Install a concrete arch pipe at the west end of East Brooks Street rather than the round pipe <br />in the original bid. The arch pipe was necessary for clearance for over the top of the pipe. <br />> Deduct Bid Item 16; 15" RC Pipe culvert, Class 5, 48 linear feet at $28.35 = <br />$1,360.80. <br />> Deduct Bid Item 17; 15" RC Pipe apron, 2 each at $617.50 for a total of $1,235. <br />> Add 15" RC Pipe, 48 linear feet at $66.75 per linear feet = $3,204. <br />> Add 15" arch RC pipe aprons, 2 each at $822.25 fora total of $1,644.50. <br />Total lump sum addition for this item is $2,252.70. <br />3. Service hook -up on Viking Drive at City's request, the Contractor dug for a potential water <br />service that was never found. <br />Total lump sum addition for this item is $200. <br />4. Construct drainage swale and line it with field stone rip -rap at the west end of Viking Drive. <br />This was a requirement of the Watershed District permit, which was received after the <br />project was bid. <br />Total lump sum addition for this item is $2,820. <br />5. Change the fence height along Viking Drive from 6 feet to 5 feet in height. <br />Total lump sum deduct for this item is $645. <br />6. Lower hydrant along Viking Drive <br />Total lump sum addition for this item is $650. <br />7. Remove 45 feet of 30 -inch CMP lined with 3 inches of concrete, which was discovered <br />along Viking Drive. <br />Total lump sum addition for this item is $2,170. <br />O: \PROJ \805140J \0071 \change order No. 1.nov99.doc <br />Page 179 <br />