Laserfiche WebLink
CHANGE ORDER #1 <br />(Attachment) <br />This contract is amended as follows: <br />WHEREAS: It was determined by the Engineer that the existing pipe locations should be <br />potholed for verification of pipe alignments and angles prior to the construction of <br />the precast manhole structures, and <br />WHEREAS: The Engineer determined that bends in the existing 48" RCP sanitary sewer line <br />would require the use of minor bends in the 12" slipline pipe, and. <br />WHEREAS: The Engineer determined that is would be more cost effective to have the <br />Contractor complete the work as part of the project, and <br />WHEREAS: The Engineer directed the Contractor to complete the work on a time and <br />material basis. <br />NOW, THEREFORE, IT IS HEREBY MUTUALLY AGREED AND UNDERSTOOD THAT: <br />1. The Contractor shall complete the above described changes and additions to the project. <br />2. Payment for the work was reviewed and approved by the Engineer. <br />3. The Contractor will not make claim of any kind or character for any other costs or <br />expenses that he may have incurred or that he may hereafter incur in performing the <br />work or furnishing the materials of this agreement. <br />3 <br />