CHANGE ORDER #1 <br />(Attachment) <br />This contract is amended as follows: <br />WHEREAS: It was determined that an existing sanitary and water stub to a property would <br />need to be adjusted to allow installation of the new storm sewer system on <br />Spruce Street; and <br />WHEREAS: There was more poor material that had to be removed from Spruce Street then <br />was represented by the boring taken for the project; and <br />WHEREAS: An existing tree from within the Pinetree development was overhanging an <br />adjacent building and required special means for removal; and <br />WHEREAS: Several of the piles within the Pinetree development contained rubble and <br />construction debris requiring separation and disposal. <br />WHEREAS: The Engineer determined that it would be more cost effective to complete these <br />work items while both project areas were disturbed and the Contractor was <br />already on site, and <br />WHEREAS: The Engineer directed the Contractor to complete the work as part of this project. <br />NOW, THEREFORE, IT IS HEREBY MUTUALLY AGREED AND UNDERSTOOD THAT: <br />1. The Contractor shall complete the above described changes and additions to the project. <br />2. Payment for the work was reviewed and approved by the Engineer. <br />3. The Contractor will not make claim of any kind or character for any other costs or <br />expenses that he may have incurred or that he may hereafter incur in performing the <br />work or furnishing the materials of this agreement. <br />GENERAL CONDITIONS 00700 - 2 <br />6 <br />