My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
03-25-2015 Additions
>
City Council Packets
>
2010-2019
>
2015
>
03-25-2015 Additions
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/26/2015 2:53:17 PM
Creation date
3/26/2015 2:53:05 PM
Metadata
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
7
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
At this time, Russ has indicated that he is very close to completing the construction plans for a <br />new building. As well, city staff has spoken with the general contractor for the project. The <br />contractor has indicated plans will be submitted to the City by April 15th. Russ plans are for <br />construction to begin after road restrictions are lifted (May roughly) and has been told it's about a <br />three month construction project. (City staff would also like to note that on November 12, 2014, <br />the Council approved the use of a temporary storage container on the property during this interim <br />time.) <br />City staff's recommendation is to approve an extension for application of the building <br />permit until April 15th. Additionally, that the storage pod is tied to the building permit <br />being issued and will be removed 30 days after the final inspection is completed. If the <br />building permit is not completed by the above deadline, the storage pod is required to be <br />removed from the site immediately. <br />
The URL can be used to link to this page
Your browser does not support the video tag.