<br />AGENDA ITEM 6B
<br />STAFF ORIGINATOR: David Ahrens, Public Works Director/City Engineer
<br />DATE: April 5, 1996
<br />TOPIC: Resolution No. 96 - 02, Award Construction Contract Marshan Lake
<br />Condominium Street and Utility Improvements
<br />INTRODUCTION:
<br />Sealed bids were received and opened on Thursday, January 18, 1996, for the
<br />construction of streets and utilities for the Marshan Lake Condominiums. City
<br />Council action is required to award a construction contract to the lowest
<br />responsible bidder.
<br />BACKGROUND:
<br />The City Council ordered the improvement for the Marshan Lake Condominium
<br />Street and Utility Improvements at the December 18, 1996, Council Meeting. On
<br />Thursday, January 18, 1996, thirteen sealed bids were received and opefled with
<br />the following results:
<br />Company Bid Amount Alternate Total, Bid
<br />C. W. Houle, Inc. $540,153.40 $24,215.00 $564,368.40
<br />S.J. Louis Construction $575,238.00 $18,039.00 $593,277.00
<br />Kadlec Excavating $573,522.90 $29,435.00 $602,957.90
<br />Bonine Excavating $593,157.45 $24,430.85 $617,588.30
<br />Forest Lake Contracting $594,387.50 $29,175.00 $623,562.50
<br />Northdale Construction $594,926.36 $28,832.18 $623,758.54
<br />Rehbein Excavating $593,406.00 $35,608.50 $629,014.50
<br />S. M. Hentges $630,402.00 $18,450.00 $648,852.00
<br />Ryan Contracting $617,256.75 $36,805.00 $654,061.75
<br />Arcon Excavating $633,334.69 $31,670.15 $665,004.84
<br />Richard Knutson $640,058.66 $31,957.70 $672,016.36
<br />Brown & Cris $648,090.40 $34,547.50 $682,637.90
<br />Kober Excavating $677,465.82 $29,879.99 $707,345.81
<br />Engineer's estimate $626,662.00 $22,235.00 $648,897.00
<br />A bid alternate was included in the bid form to extend sanitary sewer to
<br />properties south of Aqua Lane. The property owners have indicated to staff that
<br />they do not want this sewer extension.
<br />
|