Laserfiche WebLink
<br /> <br /> <br />Justification Report <br />Utility Connection Fees <br />City of Lino Lakes, MN <br />WSB Project No. 2988-26 Page 8 <br />4. FEE CALCULATIONS <br /> <br />4.1 2030 Unit Projections <br /> <br />The 2030 units are based on the average of the projected units based on land use and the <br />projected residential equivalents based on approximate future water use. <br /> <br />Currently within the City of Lino Lakes, there are approximately 6,828 developable acres <br />proposed to be developed by the year 2030 as identified in the City’s 2030 Comprehensive Plan. <br />Of that amount, 5,174 are residential acres; 1,090 are commercial or industrial acres; and 564 are <br />mixed-use acres. The total number of units projected is the assumed number of SAC units per <br />acre for each land use designation, multiplied by the remaining acres to be developed by 2030, <br />resulting in approximately 12,790 equivalent units developing by the year 2030. The assumed <br />density for each land use category is included in Appendix C. <br /> <br />The projected units based on water usage is a residential equivalent unit volume determined by <br />dividing average annual water usage by the number of gallons residential users demand on <br />average. The projected 2030 water usage was divided by the residential equivalent volume to <br />determine the additional residential equivalents by 2030, resulting in approximately 6,537 <br />additional residential equivalents developing by 2030. <br /> <br />The units used in this report were determined by the average of the two methodologies, resulting <br />in an assumed additional 9,663 units to connect to the City’s water and sewer system by 2030. <br />As development proceeds, this number should be tracked and updated to adjust fees every five <br />years, with adjustments made incrementally to address inflation. <br /> <br />4.2 Trunk Fee <br /> <br />Capital Improvement Plans (CIP) for both the sanitary sewer and water supply systems were <br />developed based on the City’s 2030 Comprehensive Plan. The CIPs were based on building the <br />trunk facilities to accommodate the 2030 estimated growth. <br /> <br />The trunk sanitary sewer CIP includes sanitary sewer pipe upgrades, new main installations, and <br />designated lift station improvements within the 2030 Urban Service Area. The trunk sanitary <br />sewer improvement projects and associated costs included in the trunk fee calculation are <br />detailed in Appendix B. The trunk water system CIP includes water main upgrades, new main <br />installations, and designated water supply wells and storage tanks within the 2030 Urban Service <br />Area. Additionally, it was assumed that the Trunk Fees would cover the cost of half of the water <br />treatment plant planned for construction. Because the 2030 Comprehensive Plan was written in <br />2009, those projects already constructed were removed, and five percent was added to the <br />estimated costs to address inflation. The trunk water system improvement projects and associated <br />costs included in the trunk fee calculation are detailed in Appendix B. <br /> <br />The total costs to construct the 2030 trunk sanitary sewer and 2030 trunk water systems are <br />estimated at $12,400,000 and $10,864,350, respectively. The total costs to construct the systems <br />were divided by the total number of 2030 units remaining to be developed to obtain a uniform <br />trunk fee per SAC unit. The calculated trunk sewer fee is $1,505 and the calculated trunk water <br />fee is $2,162.