Laserfiche WebLink
Feasibility Study <br />Water Treatment Plant <br />City of Lino Lakes, MN <br />WSB Project No. 015822-000 Page 14 <br />The average and maximum day water demand projections from Table 4-2 are shown graphically <br />in Figure 4-1 below. The system firm capacity and total storage volume are also shown, including <br />approximate timing of system improvements. Tower No. 3 is currently under construction and will <br />be complete in 2021. Well Nos. 7 and 8 are projected to be needed prior to years 2023 and 2033, <br />respectively. The anticipated capacity of future wells was assumed to be 1,000 gpm on average. <br />Six additional wells, for a total of twelve wells, are projected to be needed to satisfy the City’s <br />ultimate water demands. <br />Figure 4-1. Projected Water Demand Trigger Chart