<br />Shenandoah Improvements Feasibility Report <br />City of Lino Lakes, MN <br />WSB Project No. 018901-000 Page 12 <br />Construction Cost - Option 2 <br />Description Units Contract Quantity Unit Price Total Price Comments <br />MOBILIZATION LS 1 $20,000 $20,000 ~10% of total budget, slightly lower b/c simpler <br />COMMON EXCAVATION C Y 14750 $17.50 $258,125 Essentially all cut and removal from site <br />RANDOM RIPRAP CL III C Y 10 $120.00 $1,200 For inlets <br />12" RCP L F 70 $90 $6,300 Based on OneOffice <br />12" RCP APRON EACH 2.00 $1,500 $3,000 Based on OneOffice <br />FLAP GATE/DUCKBILL VALVE EACH 2.00 $3,000 $6,000 Based on OneOffice, no duckbill estimate <br />STABILIZED CONSTRUCTION ENTRANCE EACH 1.00 $1,500 $1,500 Likely off Arrowhead Dr <br />SILT FENCE L F 1,060 $3.50 $3,710 <br />Need around grading + 40' to double up at <br />culvert outlet <br />EROSION CONTROL BLANKET S Y 3620 $3 $10,860 <br />Placed on all pond slopes (top contour area - <br />bottom contour area) <br />SEEDING ACRE 2.6 $2,000 $5,200 <br />Assume seeding occurs within full limits of <br />disturbance plus over access route <br />SEED MIX 25-151 LB 24 $10 $240 Seeding over access road, 120 lb/ac <br />SEED MIX 34-261 LB 80 $75 $6,000 Seeding wetland/pond areas, 31.5 lb/ac <br />1.5" CAL TREE - BALLED AND BURLAPPED TREE 30 $400 $12,000 Based on OneOffice <br />SHRUB - 5 GAL POT SHRB 100 $75 $7,500 Based on OneOffice <br />5 YEAR MONITORING/MAINTENANCE LS 1 $42,880 $42,880 <br />20% Contingency $68,327 <br />Total:$409,962 <br />7.1 Modeling Results <br />TSS Removal <br />(lb/yr) <br />TP Removal <br />(lb/yr) <br />Ditch 100 -yr HWL HWL Decrease (ft) <br />1,416 9.05 891.28 0.87 <br /> <br />The results above are based on the P8 and InfoSWMM modeling for this project. The <br />proposed wetland basins provided water quality improvements in accordance with <br />their footprint and volume, TSS and TP removals shown are increases over existing <br />modeled pollutant removals. The drop in ditch high water level is also a function of <br />basin volume. As such, Concept 2 shows the greate st benefits of all options due to <br />its largest basin footprint. <br />7.2 Construction E stimate <br />Again, the main driver of costs is excavation, even more so for this concept since <br />basin size is maximized . Concept 2 calls for nearly 15,000 cubic yards of <br />excavation, dr iving about 8 0 percent of the construction costs. As with Concept 1, <br />o ther major costs include the construction of associated storm sewer and vegetation <br />restoration across the site. The total estimated concept cost , including a 20 percent <br />cost contingency, is $410,000 . <br />Monitoring and maintenance of the site’s natural resources will be key to <br />establishing a diverse, native plant community. Site maintenance includes a <br />minimum of two site visits (spring and fall) for five years to conduct mowing and <br />herbicide spot treatments, and supplemental seeding during one of the <br />recommended five years. The cost of maintenance for five years as described is <br />$34,380. Monitoring the vegetation each year would provide the C ity with an <br />adaptive management approach to maintenan ce. The cost of monitoring one time per <br />year for five years is $8,500. <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br /> <br />