Laserfiche WebLink
IDTask ModeTask Name Duration Start Finish Predecessors % Complete1CSAH 14 at Sunset RAB686 daysFri 05/06/22Thu 03/21/240%2Receive Survey and DTM0 daysFri 05/06/22Fri 05/06/220%3Preliminary Design45 daysFri 05/06/22Sun 06/19/2220%430% Plans212 daysMon 06/20/22Tue 01/17/2330%530% Plans Review14 edaysTue 01/17/23Tue 01/31/2340%6PWC Item to negotiate JPA0 daysTue 01/31/23Tue 01/31/2350%760% Plans120 edaysTue 01/31/23Wed 05/31/2350%860% Plans Review21 edaysWed 05/31/23Wed 06/21/2370%9PM (If necessary)330 daysFri 05/06/22Fri 03/31/230%13Limits to R/W0 daysSat 03/18/23Sat 03/18/237SS+46 days0%14Preliminary Plat30 daysSun 03/19/23Mon 04/17/23130%15Appraisals60 daysFri 05/26/23Mon 07/24/2314FS+38 days0%16Review Appraisals15 daysTue 07/25/23Tue 08/08/23150%17Offer Letters19 daysWed 08/09/23Sun 08/27/23160%1830 Day good Faith Negotiations30 daysMon 08/28/23Tue 09/26/23170%19File for Condemnation0 daysTue 09/26/23Tue 09/26/23180%20Condemnation Hearing0 daysFri 11/10/23Fri 11/10/2319FS+45 days0%21Execute JPA0 daysMon 07/10/23Mon 07/10/236FS+160 days0%2295% Plans120 daysThu 06/22/23Thu 10/19/2380%2395% Plan Review30 daysFri 10/20/23Sat 11/18/23220%24100% Signed plans and Spec.60 daysSun 11/19/23Wed 01/17/24230%25Possession Date0 daysMon 12/25/23Mon 12/25/2319FS+90 days0%26Advertisement25 daysMon 02/05/24Thu 02/29/2425FS+15 days,24FS+18 days0%27Bid Opening0 daysThu 02/29/24Thu 02/29/24260%28Construction Can Begin0 daysThu 03/21/24Thu 03/21/2427FS+21 days0%05/0601/3103/1809/2611/1007/1012/2502/2903/21Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2202220232024TaskSplitMilestoneSummaryProject SummaryInactive TaskInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneDeadlineProgressManual ProgressPage 1Project: CSAH 14 / Sunset RAB Date: Tue 11/22/22STIP: TBD