CITY OF LINO LAKES
<br /> RESOLUTION NO. 23-12
<br /> ACCEPTING BASE BID AND AWARDING A CONSTRUCTION CONTRACT
<br /> 2023 STREET REHABILITATION PROJECT
<br /> WHEREAS,pursuant to an advertisement for bids for the construction of the 2023 Street
<br /> Rehabilitation Project, bids were received,opened and tabulated according to law, and the following
<br /> bids were received complying with the advertisement; and
<br /> TOTAL TOTAL TOTAL
<br /> CONTRACTOR BASE BID ALTERNATE 1 BASE BID +
<br /> ALT 1
<br /> Bituminous Roadways, Inc. $902,813.70 $103,784.85 $1,006,598.55
<br /> North Valley, Inc. $909,686.68 $102,753.23 $1,012,439.91
<br /> Park Construction Co. $953,460.70 $102,494.85 $1,055,955.55
<br /> Northwest Asphalt $960,910.30 $110,035.45 $1,070,945.75
<br /> Valley Paving, Inc. $984,735.10 $108,741.90 $1,093,477.00
<br /> T.A. Schifsky& Sons, Inc $1,028,815.04 $109,678.25 $1,138,493.29
<br /> Meyer Contracting, Inc. $1,193,391.09 $104,488.69 $1,297,879.78
<br /> WHEREAS, it appears that Bituminous Roadways, Inc. is the lowest responsible bidder; and
<br /> WHEREAS,the City Council finds that it would be in the best interest of the city to proceed with
<br /> Base Bid and Alternate 1,
<br /> NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Lino Lakes:
<br /> 1. The Mayor and Clerk are hereby authorized and directed to enter into a contract with
<br /> Bituminous Roadways, Inc. in the amount of$1,006,598.55 by the name of the City of
<br /> Lino Lakes for the Base Bid and Alternate 1 construction of the 2023 Street Rehabilitation
<br /> Project according to the plans and specifications approved by the City Council and on file in
<br /> the office of the City Clerk.
<br /> 2. The City Clerk is hereby authorized and directed to return forthwith to all bidder the Bid
<br /> Bonds made with their bids,except that the deposits of the successful bidder and the next
<br /> two lowest bidders shall be retained until a contract has been signed.
<br />
|