Laserfiche WebLink
14. The cost split of the signal system at Otter Lake Rd will be based on the <br />future four -legs of which one leg will be the City's. The City shall pay to the County sixty -two <br />point five percent (62.5 %) of the cost of construction and installation of the whole traffic <br />actuated signal system at Otter Lake Rd. (including County supplied materials). The City's <br />. estimated share of the construction is $115,625.00. <br />15. The City shall pay to the County sixty -two point five percent (62.5 %) of <br />the cost of all construction necessary to upgrade the signal system to include the future fourth leg <br />at Otter Lake Road. The City shall pay one hundred percent (100 %) of all other costs to <br />construct the roadway portion of the future fourth leg. <br />16. The County shall pay one hundred percent of all interconnect costs. <br />17. The City shall pay one hundred percent (100 %) of Emergency Vehicle <br />Pre - emption (EVP) costs. The City's estimated share of the construction is $4,500.00. <br />18. The City shall pay their share of mobilization, computer equipment, field <br />office and mobile telephone as determined by Mn/DOT. The estimated City cost of these <br />items is $11,520.00. <br />19. The City shall pay their share of detour signing_ and traffic control as <br />determined by Mn/DOT. The estimated City cost of these items is $1,920.00. <br />21. The total estimated cost to the City for the project is summarized below: <br />1 Right of Way <br />2 Construction or Adjustment of Local Utilities <br />3 Grading, Base and Bituminous <br />4 Storm Sewer <br />5 Detention Basins (included in Storm Sewer) <br />6 Concrete Curb & Gutter <br />7 Decorative Medians <br />8 Median Plantings <br />9 Driveway Upgrades <br />10 Concrete Sidewalk <br />11 Trails <br />12 Street Lights <br />13 Traffic Signals <br />14EVP <br />15 Mobilization, Field Office <br />16 Traffic Control <br />Total Estimated Share of Construction Cost To <br />Estimated Federal Funds available to the City <br />Total Cost less Federal Funds <br />Credit for Standard Median replacement <br />Total Cost to City <br />- 5 3 - <br />$0.00 <br />$44,445.00 <br />$0.00 <br />$14,728.22 <br />$0.00 <br />$15,518.00 <br />$17,244.00 <br />$5,791.50 <br />$0.00 <br />$1,167.60 <br />$94,402.00 <br />$0.00 <br />$11 5,625.00 <br />$4.500.00 <br />$11,520.00 <br />$1,920.00 <br />The City $326,861.32 <br />$120,339.67 <br />$206,521.65 <br />(522,443.40) <br />$184,078.25 <br />