City of Lino Lakes, Minnesota
<br />Management Report, Page 33
<br />1989 Construction
<br />This fund accounts for the various projects financed by the Temporary Improvement Bonds of
<br />1989. During 1992, the City allocated $250,070 of additional bond proceeds from the
<br />Improvement Bonds of 1992A to this fund. The fund balance of this fund was $224,640 at
<br />December 31, 1992. A summary of the financial activity of this fund from inception is as follows:
<br />Budget Actual Variance
<br />Financing Sources:
<br />Bond proceeds $4,120,767 $4,367,450 $246,683
<br />MSA construction 105,800 (105,800)
<br />Interest earnings 312,291 312,291
<br />Special assessments 758,312 758,312
<br />Other 1,200 1,200
<br />Total sources $4,226,567 5,439,253 $1,212,686
<br />Financing Uses:
<br />Construction costs:
<br />West Central Trunk $2,047,335 1,985,414 ($61,921)
<br />Woodridge Estates 819,933 851,967 32,034
<br />Sunrise Meadows 894,064 884,524 (9,540)
<br />Reshanau 3rd 206,925 252,047 45,122
<br />Reshanau 4th & 5th 258,310 397,543 139,233
<br />Transfers out:
<br />Area and unit charge 163,601 163,601
<br />Temp Bonds of 1989 580,643 580,643
<br />Dedicated parks 18,561 18,561
<br />Interim construction 48,400 48,400
<br />Surface water management 31,913 31,913
<br />Total uses $4,226,567 5,214,613 $988,046
<br />Fund Balance - December 31, 1992 $224,640
<br />The transfers to the Area and Unit Charge Fund and the Temporary Improvement Bonds of
<br />1989 were to transfer assessment collections to the appropriate funds. The transfer to the Interim
<br />Fund was for reimbursement of prior expenditures. The assessments for West Central Trunk,
<br />Woodridge Estates, and Sunrise Meadows were adopted in 1990. The assessments for Reshanau
<br />Third and Fourth Additions were adopted in 1991 and 1992, respectively. During 1992, the City
<br />recorded costs incurred on the Reshanau 5th Addition within this Fund. These costs were not
<br />originally budgeted at the time the bond was issued. We recommend the City determine a
<br />financing source for this project.
<br />
|