GRANDVIEW
<br />STORM WATER POLLUTION
<br />PREVENTION
<br />[ S WPPPI
<br />PLAN
<br />City of Lino Lakes, Minnesota
<br />GENERAL EROSION AND SEDIMENT CONTROL
<br />INSPECTIONS AND MAINTENANCE
<br />1. The Permtttee(s) (either the owner or operator) must routinely inspect the
<br />construction site once every seven (7) days during Dative construction and within
<br />24 hours after a rainfall event greater than 0.5 Inches in 24 hours
<br />2. At inspections and maintenance conducted during construction must be recorded in
<br />writing and these records must be retained with the SWPPP In ocoordonce with
<br />RECORD DETENTION. Records of each Inspection and mdntenonce activity shag
<br />Include aha8 include
<br />a. Date and fine Inspections
<br />b. Noma of persm(s) conducting inspection;
<br />c Findings of Inspection, Including recommendations for corrective action;
<br />d. Corrective actions taken (Including dotes, times. and party compietng
<br />maintenance activities);
<br />e. Date and amount of rainfall events greater than 1/2 inch (0.5 inches)
<br />in 24 had; and
<br />L Documentation of changes mode to the SIYPPP.
<br />3 When ports of the constructon efts how undergone final etabnizatbn, but work
<br />remains on other parts of the site, inspections of the stob0osd aim may be
<br />reduced to once per month. When work has been suspended due to froze, ground
<br />conditions, the required Inspections and maintenance must take place as soon ors
<br />runoff occurs at the efts or prier to resuming construction. whichever comes first.
<br />4. M erosion prevention and sediment control BLIP. most be inspected to ensure
<br />integrity and effectiveness. M nonfunctional BAPS must be repaired, replaced, or
<br />supplemented with functional BMPs The Permltee(s) must investigate and comply
<br />with the following inspection and maintenance requirements
<br />e M silt fences must be repaired replaced, or supplemented when they become
<br />nonfanetiond (develop tears, detach from posts. post become dislodged from
<br />ground, etc) or the sediment noshes 1/3 of the height of the fence. These
<br />repairs must be mode .ithn 24 hours of discovery, or as man 0s the field
<br />conditions agma proem
<br />b. Temporary and pennmsnt sedimentation ponds must be droned and the sediment
<br />removed when the depth of the sediment collected In the basin reaches 1/2 the
<br />storage volume. Drainage and removal must be completed widen 72 hours of
<br />discovery or as soon m field conditions allow access.
<br />e Surface waters, Including drainage ditches and conveyance systems, must be
<br />repeated for evidence of sediment being deposited by erosion. The PennItete(s)
<br />must remove all deltas and sediment deposited in sumom waters. Indud,g
<br />drainage ways catch brine, and other draooge systems. and restedglze the areas
<br />when sediment removal reautts in exposed .W. The removal and stabilization must
<br />take place within sewn (7) days of discovery unless precluded by legal, regulatory,
<br />or physical constraint. The Permitee Mae use all reasonable efforts to
<br />obtain access If precluded, removal and stabilization must tats place within sever
<br />.11 moot, regional states andrfedwl authorities and�recea,g any responsible applicable permits,
<br />prier to conducting any work
<br />d Construction site vehicle eat locations must be Inspected far evidence o8 -she -
<br />sediment tracking onto paved surfaces Tracked Indolent must be removed eon
<br />an off-site paved enlaces, within 24 hours of discovery, or R applicable, within a
<br />shorter time
<br />s The Permittee(s) are responsible for operation and maintenance of temporary
<br />and permanent water quality management RMPS as well as dl erosion prevention
<br />ond sediment control BMPS for the duration of the conshuctkan work at the site
<br />The Penntttee(e) an respectable until another Pennttee has assumed contra over
<br />areas of the site that hove not been finally stabilized or the site has undergone
<br />fad stab6sation, and a Notice of Termination has been submitted to the MPCA
<br />(see TERMINATION C COVERAGE).
<br />f. if sediment escapes is construction sits off-site accumulations must be removed
<br />In o manner and at a frequency sufficient to minimize off-site impact. (e.g.,
<br />fugitive sediment in streets could be washed Into •norm sewers by the next rain
<br />and /or pose a safety hazard to users of public farads).
<br />5. M 'filtration areas must be inspected to ensure that no sediment from ongoing
<br />construction activities is reaching the infiltration area and these areas are
<br />protected from compaction due to construction equipment driving Dross the
<br />Infiltration area
<br />POLLUTION PREVENTION MANAGEMENT MEASURES
<br />The Pormltee(s) Mae implement the following pollution prevention management
<br />measures an the site
<br />I. Solid Waste Collected sediment, asphalt and concrete millings, Booting debris,
<br />paper, plastic, fabric, construction and demolition deb. and other wastes oust be
<br />deposed of properly and must comply with MPCA disposal requirements
<br />2. Hazardous Materials OE, gasoline, point and any hazardous substances moat be
<br />property stared, including •eeandary containment to prevent spies leaks or other
<br />discharge Restricted access to storag. areas must be provided to prevent
<br />vandalism. Storage and disposal of hmordo o waste nest be in compliance with
<br />MPG* regulations.
<br />3 External washing of trues and other construction vehicle must be limited to 0
<br />defined area of the site Runoff must be contained and waste property deposed
<br />of. No ongne degreasing is allowed on site
<br />DE-WATERING AND BASIN DRAINING
<br />1. Dewotertng or basin draining (e.g., pumped discharges. trench/ditch cuts for
<br />drainage) related to the conatructl= actl*ty that may have turbid or sediment
<br />laden discharge water must be discharged to a temporary or permanent
<br />sedimentation book, on the project site whenever possible. If the water carrot be
<br />discharged to sedimentation bas, prior to entering the surtoa water, it must
<br />treated with the appropriate BMP, such that the discharge dos not dwasely
<br />affect the receiving water or downstream landowners. The Pem tttee(s) rust
<br />ensure that discharge points ore adequately protected from erosion and sixr.
<br />T. discharge must be dispersed over noturd rock riprap, sand bogs plastic
<br />sheeting or other °scented energy dsngotion measure.. Adequate sedimentation
<br />control measures are required for discharge water that contains ausponded solids
<br />2. M water from dewaterng or basin draining activities must be discharged in a
<br />manner that does not sous nuisance conditions. erosion in receiving channels or
<br />on ...lope properties r inundation in wetland. causing slgnifko t adverse
<br />Impact to the wetland
<br />AMENDMENTS TO SWPPP
<br />The Permittee(s) must amend the SWPPP as necessary to include odditiond
<br />requirements, such m additional or modified BMPs, designed to correct problems
<br />ktenUfied or address situations whenever.
<br />1. There a a change in design, construction, operation, maintenance, weather r
<br />season conditions that has a significant effect on the discharge of pollutants to
<br />surface waters or underground water;
<br />2. Inspections or investigations by site operators, toad, state or federal officials
<br />indicate the SWPPP is not effective in eliminating or significantly minimizing the
<br />discharge of pollutants to surfer* water or rmdrgro red waters or that the
<br />discharges are causing water quality standard ezceodances, or
<br />3. The SWPPP Is not achieving the general objectives of controlling pollutants r storm
<br />water discharges associated with construction activity; or tie SWPPP is not
<br />consistent with the terns and condition of the permit
<br />4. At any fkne after permit coverage a effective, the MPCA may determine that the
<br />project's stem water Recharges• may cause, hove reasonable potential to cause, or
<br />contrbute to no- attainment of any applicable water quality standard - N MPCA
<br />makes such a determnotion, the MPCA .81 notify the Permittee(a) a writing. in
<br />response, the Permttes(s) must dewlap a supplemental BMP cotton pion or
<br />appropriate 511PPP amendment. describing SWPPP modifications to address the
<br />Identified 0000000 and =bait information requested by the MPCA, which may
<br />naiad. an individual permit application. If MPCA's ,mitten notification requires a
<br />response, theme to respond within the specified tfinefrrne constitutes a permit
<br />violation.
<br />FINAL STABILIZATION
<br />The Permltee(s) must ensure find stabilization of the site The Pemdtee(s) most
<br />submit o Notkoe of Termination within 30 days after fad stabilization le complete.
<br />or another owner/operator (Permlttee) has assumed control over di areas of the
<br />site that have not undergone final stabilization. Find stabilization can be achieved
<br />in one of the following ways
<br />1. M soil disturbing at the site hove been completed and ail soils most be stabilized
<br />by a onlorrn perennial vegetative cover with o density of 70 percent over the
<br />entire previous surface ores, or other equivalent means necessary to prevent cog
<br />fakers under ewive .eond/feons and:
<br />a M drainage ditches, constructed to drain water from the site after construction is
<br />complete, must be stabilized to preclude erosion;
<br />b. M tempo synthetic, and structural trod= prevention and sediment contra
<br />Best Management Plow (such as elt fence) mud be removed as poi of the site
<br />final stabilization; and
<br />c The Pennitee(s) must dem out all sediment from =san d
<br />y0es a from
<br />Maim sedimentation aim that ore to be used as permanent water quality
<br />management basins Sedknent must be stabilized to prevent It from being wasted
<br />bock Into the basin, conveyance and drainage ways discharging off-site or to
<br />surface waters The dean out of permanent basins must be sufficient to return
<br />the basin to design capacity.
<br />2. For residential construction only,- find stabilization nos been achieved when
<br />temporary erosion protection and down gradient perimeter - control for individual lots
<br />has been completed and the residence hos been transferred to the homeowner.
<br />Additionally, the Permits. must distribute the MPCA 'homeowner fact sheet' to the
<br />homeowner to inform the homeowner of the need for, and benefit. of, find
<br />stobltratlon.
<br />RECORD DETENTION
<br />The SWPPP, all changes to ft, and 'inspections and maintenance records must be
<br />kept at the site during construction by the Permtee who has operational control
<br />of that potion of the sits The SWPPP. can be kept In either the field off of in
<br />an on -site vehicle.
<br />M
<br />owner(s) must keep is SYPPP, along with the fo0owng additional records, on
<br />flee for three (3) years offer submitted of the NOT os outlined in TERMINATION OF
<br />COVERAGE This does not ,elude any records after eubmlttd of the NOT.
<br />1. My other permits required for the project
<br />2. Records of all Inspection and maintenono conducted during construction
<br />3. M permanent operation ond maintenance ogreements that have been implrnoted,
<br />including d right of .oji contracts, covenants and other binding requirements
<br />regarding perpshud maintenance, and
<br />4. M required calculations far design of the temporary and permanent storm water
<br />management systems
<br />TERMINATION OF COVERAGE
<br />1.
<br />Permittee(s) wathbg to terminate coverage under this permit must submit a Notice
<br />of Termination (NOT) to the MPG Compliance with the permit is required ono
<br />NOT is submitted The Permittee(e) authorization to discharge under the permit
<br />terminates at midnight of the -day the NOT is signed_
<br />2. All Pentnttee(s) must submit a NOT within thirty (30) days after one or more of
<br />the following conditions have been met
<br />e F,d Stabilization hos been addend on all portions of the sate for which the
<br />Permit, ls responeble (indudmg the removal of all tempo erosion control
<br />measures such as sot fence, and it applicable returning agricultural land to its pre
<br />construction agricultural osek -
<br />b. Another owner/operator (Permitee) has roomed control according to Part IL8.5 of
<br />SPCA Penn9 No. NN 8100001 over an areas of the site that have not been (Wally
<br />stabilized or
<br />e Far rshde ntil construction only, temporary erosion protection and down gradient
<br />perimeter control for Individual lots has been competed and the residence hos
<br />been transferred to the homeowner. Additionally, the Permits must distribute the
<br />MPCA's 'homeowner faetaheel' to the homeowner to inform the homeowner of the
<br />need for, and bene0ts.of, 1,d stobotzotlon.
<br />SITE SPECIRC EROSION AND SEDIMENT CONTROL
<br />BTiE ONION
<br />A) PROJECT NAME: GRANDVIEW
<br />B)- PRDJECT LOCATION: Between tte dead ends of Stagecoach True behind Gefhsemany Church.
<br />CJ PROJECT DESCRIPiIOtF
<br />Ws project MB coneat of the construction of oeven single -foray homes and a public:
<br />Most had surface run -off Is routed to a pre - treatment basin, Midi Is to be lined to
<br />present water infiltration. Th0 basin wB overflow to bin-filtration basin which has on
<br />underdron and a controlled outlet
<br />Soil disturbing activities will include: installation of o rock construction entrence
<br />Installation of set fence where surface run-off leaves site vibe grading, to include the
<br />Import of material and export of unsuitable sole wotennan, sanitary sewer, and storm
<br />sew installation; building .00100tion including foundation nrmrat1oa parking lot and
<br />roodwoy construction; and preparation for turf restoration.
<br />E) PERCENTAGE HARD SI_MFAC0 2'Z
<br />F) SITE ARFA$
<br />0) TOTAL 01511/1985 AREA' 4.35 ACRES
<br />H)
<br />111 1 • Jr. e!. m r • . .. nn • w•: 11• •. .. _ J: 0.
<br />• Prior to any grading opratone, the contractor shoo Install a rock construction
<br />entrance and perimeter slit fence as shown on plan. (Contact City and /or County
<br />to Inspect erosion control measures prier to grading operations, If necessary.)
<br />Additional set fence may be necessary R local conditions require
<br />• Provide W m (or approved equal) to 00 acting storm viewer inlets that wog receive
<br />run-off during site construction. Provide Met protector for ail proposed storme Inlets within 24 hours of structure natdation. Met protection to remain
<br />sewer
<br />, place until site has Men .tablaed.
<br />• Remove topsoil from sib and pace in temporary ...pie l000tnn (as determined
<br />by Owner). Seed etoo plc with temporary Bead ma and nwd. with weed-free straw
<br />If stsclp1n is to remain k, place for more than three (3) days
<br />• Perform site grading on an aeo-by -area bola to minimize uncompleted areas As
<br />each area is completed o0 exposed sole must have temporary erosion control
<br />protection or permanent cover according to the following tare table
<br />TYPE OF SLOPE
<br />Steeper than ::1
<br />7 days
<br />10:1 to 31
<br />14 days
<br />Flatter than 10.1
<br />21 days
<br />(• Marinas., Usna an area acrt
<br />remain cow whwn the wino Is
<br />not acU,eey balm; corked)
<br />Al sod seed mulch and fertilizer shoe conform with the following MnDOT
<br />specifications as modified below.
<br />ITEM
<br />BEFORE
<br />CONSTRUCTOR
<br />AFTER
<br />CONSIRBC110N
<br />TOTAL SITE AREA
<br />3.29 ACRES
<br />TOTAL ESTIMATED IMPERVIOUS
<br />0 ACRES
<br />0.89 ACRES
<br />TOTAL ESTIMATED PEfMOUS
<br />3.29 ACRES
<br />240 ACRES
<br />0) TOTAL 01511/1985 AREA' 4.35 ACRES
<br />H)
<br />111 1 • Jr. e!. m r • . .. nn • w•: 11• •. .. _ J: 0.
<br />• Prior to any grading opratone, the contractor shoo Install a rock construction
<br />entrance and perimeter slit fence as shown on plan. (Contact City and /or County
<br />to Inspect erosion control measures prier to grading operations, If necessary.)
<br />Additional set fence may be necessary R local conditions require
<br />• Provide W m (or approved equal) to 00 acting storm viewer inlets that wog receive
<br />run-off during site construction. Provide Met protector for ail proposed storme Inlets within 24 hours of structure natdation. Met protection to remain
<br />sewer
<br />, place until site has Men .tablaed.
<br />• Remove topsoil from sib and pace in temporary ...pie l000tnn (as determined
<br />by Owner). Seed etoo plc with temporary Bead ma and nwd. with weed-free straw
<br />If stsclp1n is to remain k, place for more than three (3) days
<br />• Perform site grading on an aeo-by -area bola to minimize uncompleted areas As
<br />each area is completed o0 exposed sole must have temporary erosion control
<br />protection or permanent cover according to the following tare table
<br />TYPE OF SLOPE
<br />Steeper than ::1
<br />7 days
<br />10:1 to 31
<br />14 days
<br />Flatter than 10.1
<br />21 days
<br />(• Marinas., Usna an area acrt
<br />remain cow whwn the wino Is
<br />not acU,eey balm; corked)
<br />Al sod seed mulch and fertilizer shoe conform with the following MnDOT
<br />specifications as modified below.
<br />ITEM
<br />MoDOT SPECI 1CAT10N/NOTES
<br />Sod
<br />3878
<br />Seed
<br />3878
<br />For pending areas (above NWL)
<br />MnDOT Mature 350 (at 84 bs /acre)
<br />• For turf eatablishme*t
<br />MnDOT Mature 280 (100 bs /aloe)
<br />MnDOT tincture 270 (120 but /Doe)
<br />Temporary Fall cover
<br />Spring/summer
<br />1 -2 yeas cow
<br />2- 5 tears rover
<br />141001 Mature 1008 (10D bs /ice)
<br />MnDOT Mature 110 (at 10D m. /Dore)
<br />MnDOT Mature 150 (at 40 Ibs /acre) -
<br />MnDOT Mixture 190 (at 80 Ibs /acr•)
<br />•• For bio- fltratlan basin
<br />MnDOT Mixture 328 (at B8 b. /awe)
<br />Muich
<br />3882 (Type 1 - Das Anchored)
<br />Fertilize -
<br />3881
<br />Wood Fiber Blanket 3885 (Category 2)
<br />w To reduce weed establishment mow 2 to 3 times (30 days apart)
<br />during the 1st war with the mower deck about 6' - 8' off the grand.
<br />Mow one time during the 2nd year before weeds set thole seeds Burn or
<br />mow once every 3-5 years following the Mid 2 yearn of maintenance to
<br />remove dead pi4M material and Mimed. new weed
<br />• Mow a minimum of once per 2 weeks
<br />the contractor shall pay special attention to nt .d)ocent property ems and make
<br />sure the erosion control practices apiece in those areas prevent migration of
<br />sediment onto odjoeent properties.
<br />If any dopes appear to be foiling, oddltiond Wt gents biomes and erosion control
<br />blanket Mali be added m needed
<br />The contractor shag mortar and repair an at fence (including the removal of
<br />�accumulated sediment) until vegetation k established and the site a stabilized. (See
<br />INSPECTIONS AND MAINTENANCE).
<br />• -Provide rip -rap at at pip outlets within 24 hours of pipe Installation.
<br />• Mato, s01 fence, ncludng the removed of accumulated aedbment, through
<br />completion of budding 00 0tructlon. Set fence to be removed only after mmpletlon
<br />of building construction and upon establishment of vegetation.
<br />• Fled grads swab areas upon stabilization of upstream rem.
<br />• 5d a9 disturbed drainage areas, adudmg sewer pond overflows around storm
<br />sew flared -end section, and off - street catch basins
<br />• install underground unities (water, sanitary sewer. storm sewer) In a mower that
<br />minimizes others. impacts to the stormwotr BMPs.
<br />• Provide temporary mulch over an pervious areas
<br />• Upon grading completion the contractor stag provide native topsoil, seed and mulch
<br />anchored with a straight set date with, 48 hours of final grading.
<br />• Excess son should be treated 111e other exposed .ol and stabilized with, 72 hours
<br />My son stockpiles to how sill fence placed around perimeter.
<br />• Adjacent streets sae but kept dean of construction materiels dirt, and other
<br />=desirable materials. When materials or debris how washed /flowed onto ad)ocent
<br />streets It is the Contractors responablity to sweep /scrape streets as necessary or
<br />as directed by the City.
<br />EROSION CONTROL fir-MIMES
<br />STRUCTURAL PRACTICES
<br />1. 509 Fence - wit be Installed prior to any grading actMtlee along the perimeter of
<br />those portions of the site wt. are downstream of etmm water rem -off.
<br />2. Storm Water Management - Storm water drainage will be provided by nub and
<br />gutter. storm sewer and catch basin. Run-off Is to be caroled and routed to
<br />pre - treatment and Mho- nitration begins
<br />3. Stone Sew Outlet Protection - such on rip -rap and geotextle Star fabric
<br />coal be installed at storm sewer outlets as a pennonent erosion control
<br />MOWN
<br />4. Rack Construction Entrance - shall be used at all locations where
<br />combustion vehicles leers MR. onto had surface roads
<br />S Storm Sewer inlet Protection - Moil be used at all CB. to prevent site
<br />sediment from waehing Into pending bosh.
<br />OTHER COORROL.6
<br />1. Construction Waste Materials - M waste materials generated as a resdt of site
<br />construction shag be collected -and removed =cording to all local and /or state
<br />waste management regulations by o licensed solid waste management company.
<br />The contractor wig snare that all site personnel are Instructed in these practices.
<br />2. Hazardous Wastes - Al hazardous waste materials shall be stored properly to
<br />prevent spills and vandalism. When necessary, hazordous wastes will be disposed
<br />of in the manner specified by lotol and /or state regulation or by the manufacturer.
<br />3. Sanitary Waste - M sanitary waste will be collected fern the portable ,alts by a
<br />local, =eased water management company, as required by local regulation.
<br />4. Offsite Vehicle Tracking - A .rack construction entrance has been provided to help
<br />reduce vehicle tracking of sediments The paved street adjacent to the site
<br />entrance shill be .rapt on an ors- needed basis. or as determined by the City.
<br />Dump trucks hauling loose materials (send, *set. .tc) "to and /or from th• site
<br />shag be covered with a tarpaulin.
<br />5. Vehicle Cteo,ng - No engine degreasing Is allowed on-site. External washing of
<br />vehicles to be confined to a defined area ('bons yard) on -sits The bone yard Is
<br />to be at least 50 feet from any.storm den Inlet and shag drain to a temporary
<br />pit of adequate volume to hold all liquid and waste concrete materials generated
<br />during washout operations Hardened concrete shag be broken up and disposed of
<br />as required by local regulations. If necessary, place sit fence around bone yard
<br />area to ensure no sediments enter any storm water basin or storm sewer Met
<br />lOP6CITM MD 'AMBIANCE PBDCEOURS3
<br />(Also aim Impactors old MWdeeence iedr YINERAL BROWN MD fIBtT CONTROL)
<br />The following are the inspection and maintenance practices that will be seed to
<br />maintain erosion and sediment controls
<br />• M control measures all be kopeeted at least once each weak and following any
<br />storm ewe of 0.5 Inches or greater.
<br />• M measures will be maintained In good working order, N a repair is necessary, t
<br />will be Initiated within 24 hour. or report
<br />• Built up sediment ell be removed from sat fence when it has reached one -third
<br />(1/3) the height of the fence.
<br />• 59t fence will be Inspected for depth of sediment, tears, to see If the fabric is
<br />securely attached to the fence pmts, and to see that the fence pasts are firmly
<br />In the ground
<br />• Tempo seeding and planing .91 be inspected for bare spots, - washouts, and
<br />healthy growth.
<br />• A maintenance report WI be mode after each Inspection
<br />M NPDES permit a required for construction. Permit is to
<br />name, on-site at al tine.
<br />The Owner and Contractor coq oversee and be responsible for
<br />bopkrnentatbn of SYRPP, and w10 be reopensble for erosion
<br />control measures orate until final stablbation has been
<br />achieved and a Notice of Termination (NOT) has been fated
<br />with the MPCA. The Contractor and Owner shall make
<br />available to the City end watershed a fist of contacts to be
<br />notified If repels and/or maintenance to site erosion control
<br />measures on required
<br />Contractor to provide designoted concrete truck washout area
<br />with appropriate elgnoge at booboo shown (r location
<br />approved by Engewsr). Washout area is to be a minimum of
<br />50' from storm areas, dddos. ponds or rainwater garden
<br />areas. Do not allos nn -off fron this ono by constructing o
<br />temporary pit or brined area large enough for liquid and mild
<br />mete After waste concrete is set break -up and dispose of
<br />Prop•nfp
<br />Contractor to provide phased traffic control (i accordance
<br />with the 'M,neeoto Monad of Untform Traffic Control
<br />Dedoen' as necessary whenever greeting, utility work, paving
<br />operations, and final tun restoration encroach within
<br />right- of-way or onto docent 'beets.
<br />M BMPs nest be mokso,ed with proper function until all site
<br />work has been eorpteted and site has undergone find
<br />stabilization.
<br />Contractor to provide toped] etoekpee at beatlon designated
<br />by owner. Stodepae location(s) to be surrounded by Mt
<br />fence. If etadkpbe is to be apiece longer Ulm 72 hours,
<br />provide seed and mdch.
<br />DRAWN BY:
<br />BNB.
<br />CHCim BY:
<br />C.C.S.
<br />DESIGN BY
<br />C.C.S.
<br />PROD. N0.
<br />07 -1131
<br />ORIGINAL DATE
<br />FEBRUARY 9, 2007
<br />REVISION DESCRIPTION
<br />S
<br />0
<br />a
<br />O
<br />Z
<br />ROYAL OAKS
<br />REALTY
<br />1000 COUNTY RD E,IIES
<br />SROREYIEw, MN 55128
<br />PHONE (851) 483 -5518
<br />5176 PLANNING
<br />d ENGINEERING
<br />PLOWE
<br />ENGINEERING, INC
<br />8778 LUE DRIVE
<br />SUITE 110
<br />LINO I.AA7R, MN 55014
<br />PHONE (851) 361 -825
<br />PIZ (851) 381 -8701
<br />C3
<br />
|