COMPENSATING CHANGE ORDER NO. 2
<br />2008 SURFACE WATER MANAGEMENT PROJECT
<br />CITY OF LINO LAKES, MINNESOTA
<br />TKDA PROJECT NO. 14043.003
<br />PERIOD ENDING: August 13, 2009
<br />CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
<br />. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
<br />PROJECT 1 - 496 LONESOME PINE
<br />1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00 $ - $ 400.00
<br />2
<br />BUILD CATCH BASIN OVER EXISTING 21" ST. SEWER TYPE 409 EA 1.0 1.0 $ 4,131.00 $ 4,131.00 $ - $ 4,131.00
<br />3 4" PERFORATED DRAINTILE WITH ROCK & FABRIC WRAP LF 120.0 125.0 $ 20.00 $ 2,500.00 $ 100.00 $ 2,400.00
<br />4 INSTALL YARD DRAIN BOX EA 1.0 1.0 $ 3,450.00 $ 3,450.00 $ $ 3,450.00
<br />5 TOPSOIL CY 20.0 $ 50.00 $ $ (1,000.00) $ 1,000.00
<br />6 SILT FENCE LF 30.0 20.0 $ 5.00 $ 100.00 $ (50.00) $ 150.00
<br />7 SPRINKLER REPAIR LS 1.0 - $ 650.00 $ - $ (650.00) $ 650.00
<br />8 SOD SY 1,000.0 150.0 $ 4.00 $ 600.00 $ (3,400.00) $ 4,000.00
<br />• 9 DRAINTILE TEES WITH CAPS EA - 3.0 $ 150.00 $ 450.00 $ 450.00 $
<br />• 10 REMOVE BUSH AT HOMEOWNER'S REQUEST LS 1.0 $ 250.00 $ 250.00 $ 250.00 $
<br />SUBTOTAL PROJECT 1 $ 11,881.00 $ (4,300.00) $ 16,181.00
<br />PROJECT 2 - OLD BIRCH STREET
<br />1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00 $ - $ 400.00
<br />2 CLEAN STORM SEWER PIPE LF 90.0 90.0 $ 10.00 $ 900.00 $ - $ 900.00
<br />3 CLEAN /OPEN STORM SEWER OUTFALL EA 6.0 6.0 $ 1,200.00 $ 7,200.00 $ - $ 7,200.00
<br />4 SEED / RESTORATION LS 1.0 1.0 $ 700.00 $ 700.00 $ - $ 700.00
<br />SUBTOTAL PROJECT 2 $ 9,200.00 $ - $ 9,200.00
<br />PROJECT 3 - BIRCH STREET
<br />1 MOBILIZATION EA 1.0 $ 400.00 $ - $ (400.00) $ 400.00
<br />2 COMMON EXCAVATION CY 40.0 $ 75.00 $ - $ (3,000.00) $ 3,000.00
<br />3 SOD SY 200.0 $ 4.00 $ - $ (800.00) $ 800.00
<br />4 SILT FENCE LF 50.0 $ 5.00 $ - $ (250.00) $ 250.00
<br />SUBTOTAL PROJECT 3 $ - $ (4,450.00) $ 4,450.00
<br />PROJECT 4 - RUFFED GROUSE COURT
<br />1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00 $ - $ 400.00
<br />2 CLEAN /OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,500.00 $ 2,500.00 $ - $ 2,500.00
<br />0 SEED / RESTORATION LS 1.0 1.0 $ 1,000.00 $ 1,000.00 $ - $ 1,000.00
<br />DITCH TO DRAIN LF - 50.0 $ 10.00 $ 500.00 $ 500.00 $ -
<br />REMOVE CLUMP OF TREES LS 1.0 $ 500.00 $ 500.00 $ 500.00 $
<br />SUBTOTAL PROJECT 4 $ 4,900.00 $ 1,000.00 $ 3,900.00
<br />PROJECT 5 - OSPREY COURT
<br />1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00 $ - $ 400.00
<br />2 CLEAN /OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,500.00 $ 2,500.00 $ - $ 2,500.00
<br />3 SEED / RESTORATION LS 1.0 1.0 $ 550.00 $ 550.00 $ - $ 550.00
<br />SUBTOTAL PROJECT 5 $ 3,450.00 $ - $ 3,450.00
<br />PROJECT 6 - HODGSON ROAD
<br />1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00 $ - $ 400.00
<br />2 CLEAN /OPEN STORM SEWER OUTFALL EA 1.0 1.0 $ 2,000.00 $ 2,000.00 $ - $ 2,000.00
<br />3 DITCHING LF 150.0 100.0 $ 14.00 $ 1,400.00 $ (700.00) $ 2,100.00
<br />4 SEED / RESTORATION LS 1.0 1.0 $ 1,000.00 $ 1,000.00 $ - $ 1,000.00
<br />SUBTOTAL PROJECT 6 $ 4,800.00 $ (700.00) $ 5,500.00
<br />PROJECT 7 - LAMOTTE CIRCLE
<br />1 MOBILIZATION EA 1.0 1.0 $ 400.00 $ 400.00 $ - $ 400.00
<br />2 CLEAN STORM SEWER PIPE LF 500.0 500.0 $ 10.00 $ 5,000.00 $ - $ 5,000.00
<br />3 SEED /RESTORATION LS 1.0 1.0 $ 1,500.00 $ 1,500.00 $ - $ 1,500.00
<br />• 4 ADDITIONAL MOBILIZATION LS 1.0 $ 1,500.00 $ 1,500.00 $ 1,500.00 $ -
<br />• 5 CLEAN /OPEN STORM SEWER OUTFALL LS 1.0 $ 2,500.00 $ 2,500.00 $ 2,500.00 $
<br />• 6 CLEAR AND GRUB BRUSH /SMALL TREES LS 1.0 $ 500.00 $ 500.00 $ 500.00 $
<br />• 7 EXTEND OUTFALL PIPE LS 1.0 $ 800.00 $ 800.00 $ 800.00 $
<br />• 8 PLACE RIP RAP, ABOUT 8 CY LS 1.0 $ 1,600.00 $ 1,600.00 $ 1,600.00 $ -
<br />SUBTOTAL PROJECT 7 $ 13,800.00 $ 6,900.00 $ 6,900.00
<br />•
<br />
|