Laserfiche WebLink
TKDA <br />Engineers - Architects- Planners Saint Paul, Minnesota 55101 <br />PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS <br />Estimate No. 4 Period Ending November 30 , 20 04 Page 1 of 1 Comm. No. 12623 -01 <br />Contractor W.B. Miller, Inc. Original Contract Amount $824.186.70 <br />Project Holly Drive Improvements <br />Location City of Lino Lakes, Minnesota <br />Total Contract Work Completed <br />Total Approved Credits <br />Total Approved Extra Work Completed - CO 1 <br />CO 2 <br />Approved Extra Orders Amount Completed <br />ioTotal Amount Earned This Estimate <br />$ 583,010.47 <br />$ 0.00 <br />37,826.00 <br />11,066.70 <br />$ 48,892.70 <br />$ 631,903.17 <br />Less Approved Credits $ 0.00 <br />Less 5 % Retained $ 31,595.16 <br />Less Previous Payments $ 546,562.84 <br />Total Deductions $ 578,158.00 <br />Amount Due This Estimate <br />$ 53,745.17 <br />Contractor Date <br />W.B. Miller, Inc. <br />Engineer Date December 8, 2004 <br />Scott A. Brink, P.E. <br />