TABULATION OF BIDS
<br />ELM STREET RECONSTRUCTION
<br />CITY OF LINO LAKES
<br />COMMISSION NO. 12390 -03
<br />BIDS OPENED: JUNE 3, 2003, AT 10 AM
<br />*DENOTES ERROR IN BIDDERS CALCULATION
<br />MN/DOT BARBAROSSA & SONS NORTHDALE CONSTRUCTION
<br />ITEM SPEC. UNIT TOTAL UNIT TOTAL
<br />NO. NO. DESCRIPTION QUANTITY UNIT PRICE AMOUNT PRICE AMOUNT
<br />niKDA
<br />1
<br />ENGINEERS • ARCHRECTS• PLANNERS
<br />FRIEDGES CONTRACTING
<br />UNIT TOTAL
<br />PRICE AMOUNT
<br />ELM STREET RECONSTRUCTION
<br />1
<br />2021.501
<br />MOBILIZATION
<br />1
<br />LS
<br />$ 67,000.00
<br />$ 67,000.00
<br />$ 91,345.00
<br />$ 91,345.00
<br />$ 75,397.78
<br />$ 75,397.78
<br />2
<br />2101.502
<br />CLEARING
<br />139
<br />TR
<br />$ 55.00
<br />$ 7,645.00
<br />$ 250.00
<br />$ 34,750.00
<br />$ 264.19
<br />$ 36,722.41
<br />3
<br />2101.507
<br />GRUBBING
<br />139
<br />TR
<br />$ 50.00
<br />$ 6,950.00
<br />$ 150.00
<br />$ 20,850.00
<br />$ 264.19
<br />$ 36,722.41
<br />4
<br />2104.501
<br />REMOVE PIPE (CULVERT OR STORM SEWER)
<br />798
<br />LF
<br />$ 10.00
<br />$ 7,980.00
<br />$ 10.00
<br />$ 7,980.00
<br />$ 11.60
<br />$ 9,256.80
<br />5
<br />2104.501
<br />REMOVE CURB & GUTTER
<br />280
<br />LF
<br />$ 2.00
<br />$ 560.00
<br />$ 1.61
<br />$ 450.80
<br />$ 330
<br />$ 924.00
<br />6
<br />2104.501
<br />REMOVE FENCE
<br />154
<br />LF
<br />$ 10.00
<br />$ 1,540.00
<br />$ 10.00
<br />$ 1,540.00
<br />$ 5.67
<br />$ 873.18
<br />7
<br />2104.501
<br />REMOVE WATERMAIN
<br />106
<br />LF
<br />$ 10.00
<br />$ 1,060.00
<br />$ 10.00
<br />$ 1,060.00
<br />$ 10.77
<br />$ 1,141.62
<br />8
<br />2104.503
<br />REMOVE CONCRETE PAVEMENT
<br />1544
<br />SF
<br />$ 0.60
<br />$ 926.40
<br />$ 1.00
<br />$ 1,544.00
<br />$ 2.51
<br />$ 3,875.44
<br />9
<br />2104.505
<br />REMOVE BITUMINOUS SURFACING
<br />20816
<br />SY
<br />$ 130
<br />$ 27,060.80
<br />$ 2.00
<br />$ 41,632.00
<br />$ 2.24
<br />$ 46,627.84
<br />10
<br />2104.509
<br />REMOVE MANHOLE OR CATCH BASIN
<br />4
<br />EA
<br />$ 300.00
<br />$ 1,200.00
<br />$ 500.00
<br />$ 2,000.00
<br />$ 472.30
<br />$ 1,889.20
<br />11
<br />2104.509
<br />REMOVE CONCRETE APRON
<br />19
<br />EA
<br />$ 300.00
<br />$ 5,700.00
<br />$ 100.00
<br />$ 1,900.00
<br />$ 216.41
<br />$ 4,111.79
<br />12
<br />2104.511
<br />SAWCUT CONCRETE PAVEMENT (FULL DEPTH)
<br />150
<br />LF
<br />$ 5.00
<br />$ 750.00
<br />$ 6.00
<br />$ 900.00
<br />$ 5.14
<br />$ 771.00
<br />13
<br />2104.513
<br />SAWCUT BITUMINOUS PAVEMENT (FULL DEPTH)
<br />950
<br />LF
<br />$ 3.00
<br />$ 2,850.00
<br />$ 4.00
<br />$ 3,800.00
<br />$ 3.56
<br />$ 3,382.00
<br />14
<br />2104.521
<br />SALVAGE FENCE
<br />50
<br />LF
<br />$ 25.00
<br />$ 1,250.00
<br />$ 26.88
<br />$ 1,344.00
<br />$ 27.25
<br />$ 1,362.50
<br />15
<br />2104.523
<br />SALVAGE MAIL BOX SUPPORT
<br />37
<br />EA
<br />$ 30.00
<br />$ 1,110.00
<br />$ 91.38
<br />$ 3,381.06
<br />$ 32.52
<br />$ 1,203.24
<br />16
<br />2104.523
<br />SALVAGE SIGN (INCL. POST & ASSEMBLY)
<br />20
<br />EA
<br />$ 20.00
<br />$ 400.00
<br />$ 26.88
<br />$ 537.60
<br />$ 21.99
<br />$ 439.80
<br />17
<br />2104.523
<br />SALVAGE HYDRANT '
<br />4
<br />EA
<br />$ 300.00
<br />$ 1,200.00
<br />$ 500.00
<br />$ 2,000.00
<br />$ 1,886.44
<br />$ 7,545.76
<br />18
<br />2104.523
<br />SALVAGE GATE VALVE & BOX
<br />5
<br />EA
<br />$ 50.00
<br />$ 250.00
<br />$ 500.00
<br />$ 2,500.00
<br />$ 151.77
<br />$ 758.85
<br />19
<br />2105.501
<br />COMMON EXCAVATION (P)
<br />19500
<br />CY
<br />$ 6.10
<br />$ 118,950.00
<br />$ 6.21
<br />$ 121,095.00
<br />$ 8.83
<br />$ 172,185.00
<br />20
<br />2105.501
<br />POND EXCAVATION
<br />9675
<br />CY
<br />$ 5.20
<br />$ 50,310.00
<br />$ 529
<br />$ 51,180.75
<br />$ 9.88
<br />$ 95,589.00
<br />21
<br />2105.522
<br />SELECT GRANULAR BORROW (CV) (P)
<br />7562
<br />CY
<br />$ 10.00
<br />$ 75,620.00
<br />$ 9.87
<br />$ 74,636.94
<br />$ 10.93
<br />$ 82,652.66
<br />22
<br />2105.525
<br />TOPSOIL BORROW (LV)
<br />453
<br />CY
<br />$ 8.00
<br />$ 3,624.00
<br />$ 8.39
<br />$ 3,800.67
<br />$ 9.35
<br />$ 4,235.55
<br />23
<br />2105.603
<br />CRUSHED ROCK 6' DEPTH (TRENCH STABILIZING)
<br />3151
<br />LF
<br />$ 2.50
<br />$ 7,877.50
<br />$ 3.00
<br />$ 9,453.00
<br />$ 7.09
<br />$ 22,340.59
<br />24
<br />2123.610
<br />EXPLORATORY DIGGING
<br />20
<br />HR
<br />$ 150.00
<br />$ 3,000.00
<br />$ 475.00
<br />$ 9,500.00
<br />$ 503.73
<br />$ 10,074.60
<br />25
<br />2211.501
<br />AGGREGATE BASE CLASS 5
<br />12000
<br />TN
<br />$ 11.00
<br />$ 132,000.00
<br />$ 10.90
<br />$ 130,800.00
<br />$ 12.51
<br />$ 150,120.00
<br />26
<br />2350.501
<br />TYPE LV AGG. 3 WEARING COURSE (B)
<br />2025
<br />TN
<br />$ 32.00
<br />$ 64,800.00
<br />$ 35.85
<br />$ 72,596.25
<br />$ 32.52
<br />$ 65,853.00
<br />27
<br />2350.501
<br />TYPE LV AGG. 4 WEARING COURSE FOR TRAIL (B)
<br />550
<br />TN
<br />$ 47.00
<br />$ 25,850.00
<br />$ 46.17
<br />$ 25,393.50
<br />$ 35.15
<br />$ 19,332.50
<br />28
<br />2350.502
<br />TYPE LV AGG. 3 NON - WEARING COURSE (B)
<br />2025
<br />TN
<br />$ 31.00
<br />$ 62,775.00
<br />$ 36.87
<br />$ 74,661.75
<br />$ 31.99
<br />$ 64,779.75
<br />29
<br />2350.503
<br />TYPE LV AGG. 4 WEARING COURSE 2" THICK FOR DRIVEWAYS
<br />(B)
<br />1500
<br />SY
<br />$ 10.00
<br />$ 15,000.00
<br />$ 10.54
<br />$ 15,810.00
<br />$ 7.25
<br />$ 10,875.00
<br />30
<br />2357.502
<br />BITUMINOUS MATERIAL FOR TACK COAT
<br />880
<br />GAL
<br />$ 1.50
<br />$ 1,320.00
<br />$ 1.83
<br />$ 1,610.40
<br />$ 2.82
<br />$ 2,481.60
<br />31
<br />2501.515
<br />15' RC PIPE APRON W/ TRASH GUARD
<br />6
<br />EA
<br />$ 440.00
<br />$ 2,640.00
<br />$ 560.02
<br />$ 3,360.12
<br />$ 686.35
<br />$ 4,118.10
<br />32
<br />2501.515
<br />21" RC PIPE APRON W/ TRASH GUARD
<br />2
<br />EA
<br />$ 550.00
<br />$ 1,100.00
<br />$ 682.50
<br />$ 1,365.00
<br />$ 810.83
<br />$ 1,621.66
<br />33
<br />2502.541
<br />4" PERF PE PIPE DRAIN (W/ SOCK)
<br />512
<br />LF
<br />$ 10.00
<br />$ 5,120.00
<br />$ 7.97
<br />$ 4,080.64
<br />$ 16.07
<br />$ 8,227.84
<br />34
<br />2503.541
<br />15` RC PIPE SEWER CLASS V DESIGN 3006
<br />2733
<br />LF
<br />$ 30.00
<br />$ 81,990.00
<br />$ 31.76
<br />$ 86,800.08
<br />$ 30.11
<br />$ 82,290.63
<br />35
<br />2503.541
<br />18' RC PIPE SEWER CLASS V DESIGN 3006
<br />830
<br />LF
<br />$ 33.00
<br />$ 27,390.00
<br />$ 33.89
<br />$ 28,128.70
<br />$ 32.13
<br />$ 26,667.90
<br />36
<br />2503.541
<br />21' RC PIPE SEWER CLASS 111 DESIGN 3006
<br />902
<br />LF
<br />$ 38.00
<br />$ 34,276.00
<br />$ 36.02
<br />$ 32,490.04
<br />$ 34.90
<br />$ 31,479.80
<br />37
<br />2503.602
<br />CONNECT TO EXISTING MANHOLES (SANITARY SEWER)
<br />1
<br />EA
<br />$ 1,500.00
<br />$ 1,500.00
<br />$ 2,375.00
<br />$ 2,375.00
<br />$ 9,225.19
<br />$ 9,225.19
<br />38
<br />2503.602
<br />8 "X4' PVC WYE (SCHEDULE 40)
<br />30
<br />EA
<br />$ 100.00
<br />$ 3,000.00
<br />$ 181.95
<br />$ 5,458.50
<br />$ 39.01
<br />$ 1,170.30
<br />39
<br />2503.603
<br />8° PVC, SDR 35 PIPE SEWER (10' -12' DEPTH)
<br />69
<br />LF
<br />$ 77.00
<br />$ 5,313.00
<br />$ 54.13
<br />$ 3,734.97
<br />$ 23.02
<br />$ 1,588.38
<br />40
<br />2503.603
<br />8' PVC, SDR 35 PIPE SEWER (12' -14' DEPTH)
<br />620
<br />LF
<br />$ 77.00
<br />$ 47,740.00
<br />$ 58.65
<br />$ 36,363.00
<br />$ 24.12
<br />$ 14,954.40
<br />41
<br />2503.603
<br />8" PVC, SCR 35 PIPE SEWER (14' -16' DEPTH)
<br />430
<br />LF
<br />$ 77.00
<br />$ 33,110.00
<br />$ 64.99
<br />$ 27,945.70
<br />$ 29.18
<br />$ 12,547.40
<br />42
<br />2503.603
<br />8" PVC, SDR 35 PIPE SEWER (16' -18' DEPTH)
<br />626
<br />LF
<br />$ 77.00
<br />$ 48,202.00
<br />$ 74.49
<br />$ 46,630.74
<br />$ 35.65
<br />$ 22,316.90
<br />Page 4