COUNCIL MINUTES JUNE 26, 2000 <br />from the project. Stubs will be added at that property and costs will come out of the amount being <br />assessed. <br />Staff entered into the record two -(2) letters that have been received from residents. The first letter is <br />from Mr. Pete Schroeder, 7981 Nancy Drive. Mr. Schroeder's letter indicated his objection to the <br />assessments. Staff read the letter in its entirety. <br />The second letter was received from Mr. Raymond Johnson at 7977 Nancy Drive. The letter <br />expressed his concerns regarding the project. Staff addressed the concerns raised in the letter. <br />Copies of the letters can be found in the City Clerk's office. <br />Council Member Carlson clarified the amount of reduction in the project if bituminous is used instead <br />of concrete for curb and gutter. She referred to the letter from Mr. Johnson and asked if the blacktop <br />that is currently at the end of Vicky Lane will be replaced. <br />Staff advised the bituminous was restored as part of another project. d to a map indicating <br />where the curb will begin and end. <br />Council Member Carlson advised one property owner has pe <br />the map. She stated the cost is now spread over the re <br />happen when that property owner does want to ho <br />Staff advised the property owner would p <br />will be comparable or may be slightly <br />lit., <br />Council Member Carlson clar' <br />1 <br />icated that property on <br />owners. She asked what will <br />• <br />es if a future hook up is desired. The cost ID <br />nal assessments would not go back to the property <br />owners if that resident hoo ture. <br />The City Administrato long the bituminous curb would last. She also asked who pays for <br />it if it has to be replace <br />Staff advised concrete curb and gutter lasts much longer. Concrete will last about 10-15 years. <br />Repair of bituminous comes out of the Public Service budget. <br />Council Member Reinert inquired about the criteria for opting out of the project. Staff advised the <br />criteria is per the City Charter. There is a 60 -day waiting period after the hearing held last Fall. <br />Residents would submit a letter to the City. If most residents want the project to be ended, the <br />Council has to determine if the project should proceed based on financial information. <br />Council Member O'Donnell stated that if the appraisals are done and show the increase of value to <br />the property only $10,000, assessments can only be in that amount. <br />Staff advised that is correct. The City will then have to determine if there are enough assessment <br />funds to pay for the project. <br />4 <br />