BID TABULATION
<br />Page 2
<br />TOLTZ, KING, DUVALL, ANDERSON
<br />2001 SURFACE WATER MANAGEMENT PROJECTS
<br />AND ASSOCIATES, INCORPORATED
<br />CITY OF LINO LAKES, MINNESOTA
<br />ENGINEERS -ARCHITECTS -PLANNERS
<br />COMMISSION NO. 12327-01
<br />TABULATION OF BIDS
<br />BIDS OPENED: 8/21/01
<br />*DENOTES ERROR IN BIDDER'S CALCULATION
<br />ENGINEER'S ESTIMATE FOREST LAKE CONTRACTING
<br />ITEM
<br />UNIT
<br />TOTAL UNIT
<br />TOTAL
<br />NO. DESCRIPTION
<br />QUANTITY
<br />UNIT PRICE
<br />AMOUNT PRICE
<br />AMOUNT
<br />CAROLES ESTATES 2ND ADD.
<br />1 MOBILIZATION
<br />1
<br />LS
<br />$2,000.00
<br />$ 2,000.00
<br />$ 6,000.00
<br />$ 6,000.00
<br />2 CLEAR & GRUB TREE
<br />9
<br />EA
<br />$300.00
<br />$ 2,700.00
<br />$ 200.00
<br />$ 1,800.00
<br />3 REMOVE 15" CMP STORM SEWER PIPE & APRONS
<br />202
<br />LF
<br />$15.00
<br />$ 3,030.00
<br />$ 6.00
<br />$ 1,212.00
<br />4 REMOVE 27" RCP STORM SEWER PIPE & APRON
<br />133
<br />LF
<br />$10.00
<br />$ 1,330.00
<br />$ 8.00
<br />$ 1,064.00
<br />5 REMOVE CATCH BASIN/MANHOLE
<br />1
<br />EA
<br />$200.00
<br />$ 200.00
<br />$ 300.00
<br />$ 300.00
<br />6 18" RCP, CLASS 5 STORM SEWER PIPE
<br />202
<br />LF
<br />$32.00
<br />$ 6,464.00
<br />$ 38.00
<br />$ 7,676.00
<br />7 27" RCP, CLASS 3 STORM SEWER PIPE
<br />133
<br />LF
<br />$40.00
<br />$ 5,320.00
<br />$ 47.00
<br />$ 6,251.00
<br />8 18" RCP, FLARED END SECTION
<br />2
<br />EA
<br />$800.00
<br />$ 1,600.00
<br />$ 800.00
<br />$ 1,600.00
<br />9 27" RCP, FLARED END SECTION W/ TRASH GUARD
<br />1
<br />EA
<br />$1,000.00
<br />$ 1,000.00
<br />$ 1,200.00
<br />$ 1,200.00
<br />10 CONST. CATCH BASIN/MANHOLE MNDOT PLATE 40
<br />1
<br />EA
<br />$2,500.00
<br />$ 2,500.00
<br />$ 3,000.00
<br />$ 3,000.00
<br />11 CONNECT TO EXISTING 27" RCP STORM SEWER PI
<br />1
<br />EA
<br />$200.00
<br />$ 200.00
<br />$ 250.00
<br />$ 250.00
<br />12 RIP RAP, CL. III
<br />15
<br />CY
<br />$120.00
<br />$ 1,800.00
<br />$ 125.00
<br />$ 1,875.00
<br />13 DITCH EXCAVATION (EV)
<br />125
<br />CY
<br />$50.00
<br />$ 6,250.00
<br />$ 40.00
<br />$ 5,000.00
<br />14 POND EXCAVATION (EV)
<br />60
<br />CY
<br />$50.00
<br />$ 3,000.00
<br />$ 25.00
<br />$ 1,500.00
<br />15 SODDING
<br />325
<br />SY
<br />$3.50
<br />$ 1,137.50
<br />$ 3.00
<br />$ 975.00
<br />SUBTOTAL
<br />$ 38,531.50
<br />$ 39,703.00
<br />WEBER ADD. & SHENANDOAH 2ND ADD.
<br />1 MOBILIZATION
<br />1
<br />LS
<br />$2,000.00
<br />$ 2,000.00
<br />$ 6,000.00
<br />$ 6,000.00
<br />2 CLEAR & GRUB TREE
<br />40
<br />EA
<br />$300.00
<br />$ 12,000.00
<br />$ 175.00
<br />$ 7,000.00
<br />3 COMMON BORROW (P) (LV)
<br />500
<br />CY
<br />$10.00
<br />$ 5,000.00
<br />$ 10.00
<br />$ 5,000.00
<br />4 15" RCP, CLASS 5 STORM SEWER PIPE
<br />175
<br />LF
<br />$28.00
<br />$ 4,900.00
<br />$ 42.00
<br />$ 7,350.00
<br />5 15" RCP, FLARED END SECTION W/ TRASH GUARD
<br />2
<br />EA
<br />$750.00
<br />$ 1,500.00
<br />$ 1,000.00
<br />$ 2,000.00
<br />6 CONST. STORM MANHOLE TYPE 409
<br />1
<br />EA
<br />$2,000.00
<br />$ 2,000.00
<br />$ 2,000.00
<br />$ 2,000.00
<br />7 RIP RAP, CL. III
<br />8
<br />CY
<br />$120.00
<br />$ 960.00
<br />$ 125.00
<br />$ 1,000.00
<br />8 DITCH EXCAVATION (EV)
<br />200
<br />CY
<br />$50.00
<br />$ 10,000.00
<br />$ 45.00
<br />$ 9,000.00
<br />9 POND EXCAVATION (EV)
<br />50
<br />CY
<br />$50.00
<br />$ 2,500.00
<br />$ 40.00
<br />$ 2,000.00
<br />10 SILT FENCE
<br />80
<br />LF
<br />$4.00
<br />$ 320.00
<br />$ 4.00
<br />$ 320.00
<br />11 SODDING
<br />500
<br />SY
<br />$ 3.50
<br />$ 1,750.00
<br />$ 3.00
<br />$ 1,500.00
<br />SUBTOTAL
<br />$ 42,930.00
<br />$ 43,170.00
<br />TOTAL BID PROPOSAL
<br />$ 127,682.50
<br />$ 136,491.00
<br />BID TABULATION
<br />Page 2