My WebLink
|
Help
|
About
|
Sign Out
Home
Search
12-28-2015 Council Packet
LinoLakes
>
City Council
>
City Council Meeting Packets
>
1982-2020
>
2015
>
12-28-2015 Council Packet
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
1/13/2016 3:22:06 PM
Creation date
1/5/2016 2:07:20 PM
Metadata
Fields
Template:
City Council
Council Document Type
Council Packet
Meeting Date
12/28/2015
Council Meeting Type
Regular
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
444
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
parties are unable to agree as to the amount or extent thereof, Contractor may make a Claim <br />therefor as provided in Paragraph 10.05. <br />13.05 Owner May Stop the Work <br />A. If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable <br />materials or equipment, or fails to perform the Work in such a way that the completed Work <br />will conform to the Contract Documents, Owner may order Contractor to stop the Work, or <br />any portion thereof, until the cause for such order has been eliminated; however, this right of <br />Owner to stop the Work shall not give rise to any duty on the part of Owner to exercise this <br />right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or <br />entity, or any surety for, or employee or agent of any of them. <br />13.06 Correction or Removal of Defective Work <br />A. Promptly after receipt of written notice, Contractor shall correct all defective Work, whether or <br />not fabricated, installed, or completed, or, if the Work has been rejected by Engineer, remove it <br />from the Project and replace it with Work that is not defective. Contractor shall pay all claims, <br />costs, losses, and damages (including but not limited to all fees and charges of engineers, <br />architects, attorneys, and other professionals and all court or arbitration or other dispute <br />resolution costs) arising out of or relating to such correction or removal (including but not <br />limited to all costs of repair or replacement of work of others). <br />B. When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07, <br />Contractor shall take no action that would void or otherwise impair Owner's special warranty <br />and guarantee, if any, on said Work. <br />13.07 Correction Period <br />A. If within one year after the date of Substantial Completion (or such longer period of time as <br />may be prescribed by the terms of any applicable special guarantee required by the Contract <br />Documents) or by any specific provision of the Contract Documents, any Work is found to be <br />defective, or if the repair of any damages to the land or areas made available for Contractor's <br />use by Owner or permitted by Laws and Regulations as contemplated in Paragraph 6.11.A is <br />found to be defective, Contractor shall promptly, without cost to Owner and in accordance with <br />Owner's written instructions: <br />1. repair such defective land or areas; or <br />2. correct such defective Work; or <br />3. if the defective Work has been rejected by Owner, remove it from the Project and replace it <br />with Work that is not defective, and <br />4. satisfactorily correct or repair or remove and replace any damage to other Work, to the <br />work of others or other land or areas resulting therefrom. <br />EJCDC C-700 Standard General Conditions of the Construction Contract <br />Copyright © 2007 National Society of Professional Engineers for EJCDC. All rights reserved. <br />Page 51 of 62 <br />00 72 05 <br />
The URL can be used to link to this page
Your browser does not support the video tag.