required to provide professional services in violation of applicable law. If professional design services or
<br />certifications by a design professional related to systems, materials or equipment are specifically required of the
<br />Contractor by the Contract Documents, the Owner and the Architect will specify all performance and design criteria
<br />that such services must satisfy. The Contractor shall cause such services or certifications to be provided by a
<br />properly licensed design professional, whose signature and seal shall appear on all drawings, calculations,
<br />specifications, certifications, Shop Drawings and other submittals prepared by such professional. Shop Drawings
<br />and other submittals related to the Work designed or certified by such professional, if preparedby others, shall bear
<br />such professional's written approval when submitted to the Architect. The Owner and the Architect shall be entitled
<br />to rely upon the adequacy, accuracy and completeness of the services, certifications and approvals performed or
<br />provided by such design professionals, provided the Owner and Architect have specified to,the Contractor all
<br />performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.19,- the =Architect -will_ _ -
<br />review, approve or take other appropriate action on submittals only for the limited purpose of checking for
<br />conformance with information given and the design concept expressed in the Contract Documents. The Contractor
<br />shall not be responsible for the adequacy of the performance and design criteria specified iii the Contract
<br />Documents.
<br />§ 3.13 USE OF SITE ;-
<br />The Contractor shall confine operations at the site to areas permitted by applicable laws, statutes, ordinances, codes,
<br />rules and regulations, and lawful orders of public authorities and the Contract Documents and shall not unreasonably
<br />encumber the site with materials or equipment.
<br />§ 3.14 CUTTING AND PATCHING
<br />§ 3.14.1 The Contractor shall be responsible for cutting, fitting or patching required to complete the Work or to make
<br />its parts fit together properly. All areas requiring cutting, fitting and patching shall be restored to the condition
<br />existing prior to the cutting, fitting and patching, unless otherwise required by the Contract Documents.
<br />§ 3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed
<br />construction of the Owner or separate contractors by cutting, patching or otherwise altering such construction; or by
<br />excavation. The Contractor shall not cut or otherwise alter such construction by the Owner pr separate bntratoi
<br />except with written consent of the Owner and of such separate contractor; such consent shall not be unreasonably
<br />withheld. The Contractor shall not unreasonably withhold from the Owner or a separate contractor the Contractor's
<br />consent to cutting or otherwise altering the Work.
<br />§ 3.15 CLEANING UP
<br />§ 3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of waste materials or
<br />rubbish caused by operations under the Contract. At completion of the Work, the Contractor shall:remove waste
<br />materials, rubbish, the Contractor's tools, construction equipment, machinery and surplus materials from and about:
<br />the Project.
<br />§ 3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, the Owner may do so and Owner
<br />shall be entitled to reimbursement from the Contractor.
<br />§ 3.16 ACCESS TO WORK f
<br />The Contractor shall provide the Owner and Architect access to the Work in preparation and progress wherever
<br />located.
<br />§ 3.17 ROYALTIES, PATENTS AND COPYRIGHTS _
<br />The Contractor shall pay all royalties and license fees. The Contractor shall defend suits or claims' for infringement
<br />of copyrights and patent rights and shall hold the Owner and Architect harmless from loss on account thereof, bit''
<br />shall not be responsible for such defense or loss when a particular design, process or product of*particular
<br />manufacturer or manufacturers is required by the Contract Documents, or where the copyright violations are
<br />contained in Drawings, Specifications or other documents prepared by the Owner or Architect. However, if the
<br />Contractor has reason to believe that the required design, process or product is an infringement�of a copyright or a
<br />patent, the Contractor shall be responsible for such loss unless such information is promptly furnished to the
<br />Architect.
<br />AIA Document A201a' — 2007. Copyright O 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997 and 2007 by The
<br />American Institute of Architects. A11 rights reserved. WARNING: This AM' Document is protected by U.S. Copyright Law and International
<br />Treaties. Unauthorized reproduction or distribution of this AIX' Document, or any portion of it, may result in severe civil and criminal
<br />penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 15:05:44 on