HomeMy WebLinkAbout2016-005 Council ResolutionCITY OF LINO LAKES
RESOLUTION NO. 16-05
APPROVING PAYMENT NO. 6 AND FINAL FOR THE 21 ST AVENUE EXTENSION
PROJECT
WHEREAS, pursuant to resolution 14-24 of the Council adopted March 10, 2014, awarding the
contract for the 21St Avenue Extension Project to A-1 Excavating Inc.
WHEREAS, a complete summary of costs are detailed in Payment No. 6 (Final);
NOW, THEREFORE, BE IT RESOLVED by the City Council of Lino Lakes that Payment
Request No. 6 (Final) is approved for a fmal contract amount of $817,418.46.
Adopted by the Council of the City of Lino Lakes this 25 day of January, 2016.
The motion for the adoption of the foregoing resolution was introduced by Council Member
Kusterman, and was duly seconded by Council Member Maher and upon
vote being taken thereon, the following voted in favor thereof:
Kusterman, Maher, Manthey, Rafferty, Reinert
The following voted against same:
none
ATTEST:
u is e Bartell, City Ilerk
CITY COUNCIL
AGENDA ITEM 6C
STAFF ORIGINATOR: Diane Hankee, City Engineer
MEETING DATE: January 25, 2016
TOPIC: Consider Resolution No. 16-05, Approving Payment No. 6 and
Final, 21' Avenue Extension Project
VOTE REQUIRED: 3/5
INTRODUCTION
Staff is requesting council action to finalize the 21' Avenue Extension Project.
BACKGROUND
The 21' Avenue Extension Project contract was in the amount of $841,971.00 and the final
payment earned by the contractor for this project is $817,418.46. Thus the contract was under
budget by $24,552.54. The fmal payment to A-1 Excavating Inc. is for $80,910.96.
This project is funded through assessments to the benefitting property owners and the City's
trunk utility unit fund. The cost allocations for the assessments are through a Petition and
Waiver agreement with ALino LLC., and a Joint Powers Agreement with the City of
Centerville. Staff will proceed to prepare the assessments for future Council consideration.
RECOMMENDATION
Approve Resolution No. 16-05, Approving Payment No. 6 and Final, 21' Avenue Extension
Project in the amount of $80,910.96 to A-1 Excavating Inc.
ATTACHMENTS
1. Resolution 16-05
2. Pay Request No. 6 & Final
WSB
AMEMENSEL
Associates, Inc.
Owner: City of LIno Lakes
600 Town Center Parkway
Lino Lakes, MN 55014-1182
For Period: 9/4/2015 to 1/15/2016
Contractor: A-1 Excavating, Inc.
PO Box 90
Bloomer, WI 54724
Pay Voucher
LINO - 21st Avenue Extension
Client Contract No.:
Protect No.: 02029-11
Client Project No.:
Date: 1/15/2016
Request No.: 6 & FINAL
Prolect Summary
1
Original Contract Amount
$ 841,971.00
2
Contract Changes - Addition
$17,505.21
3
Contract Changes - Deduction
• $0.00
4
Revised Contract Amount
$859,476.21
b
Value Completed to Date
$817,418.46
6
Material on Hand
$0.00
7
Amount Earned
$817,418,46
8
Less Retainage
$0.00
9
Subtotal
$817,418.46
10
Less Amount Paid Previously
$736,507.60
11
Liquidated Damages
$0,00
12
AMOUNT DUE THIS PAY VOUCHER NO. 6 & FINAL
$80,910,96
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT THE CONTRACT HAS BEEN
COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF
THE WORK PERFORMED IN ACCORDANCE WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL
VOUCHER.
Recommended for Approval by:
WSB &Associates, Inc.
Approved by Contractor:
A-1 Excaypting, Ipc.
Constructing Observer:
Approved by Owner:
City of Lino Lakes
Specified Contract Completion Date: Date:
6/30/2015
Comment:
Projoct Material Status
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity
to Date
Current
Quantity
Amount to
Date
Sanitary Sewer Improvements
1
2021.501
MOBILIZATION
LUMP SUM
$3,800.00
1
1
0
$3,800.00
2
2451.609
GRANULAR FOUNDATION AND/OR BEDDING
TON
$30.00
10
0
0
$0.00
3
2503.602
CONNECT TO EXISTING SANITARY SEWER
EACH
$1,500,00
1
1
0
$1,500.00
4
2503.603
CONSTRUCT 8" OUTSIDE DROP •
LIN FT
$150.00
45
45.5
0
$6,825,00
5
2503.603
18" PVC PIPE SEWER - SDR 26
LIN FT
$73.00
1260
1196.5
0
$87,344,50
6
2503.603
TELEVISE SANITARY SEWER
LIN FT
$0,80
1460
1374
0
$1,099.20
7
2503.603
8" PVC PIPE SEWER - SDR 35
LIN FT
$23.00
235
177
0
$4,071.00
8
2506.516
CASTING ASSEMBLY
EACH
$545.00
41
4
0
$2,180.00
9
2506.603
CONSTRUCT 48" DIAMETER SANITARY SEWER MANHOLE
LIN FT
$180.00
125
129
0
$23,220.00
Totals For Section Sanitary Sewer Improvements:
$130,039.70
Storm Sewer Improvements
10
2021.501
MOBILIZATION
LUMP SUM
$1,800.00
1
1
0
$1,800.00
11
2451.609
GRANULAR FOUNDATION AND/OR BEDDING
TON
$24.00
10
0
0
$0,00
12
2501.515
15" RC PIPE APRON WITH TRASH GUARD
EACH
$930.00
5
5
0
$4,650.00
13
2501.515
18" RC PIPE APRON WITH TRASH GUARD
EACH
$1,020.00
3
3
0
$3,060.00
14
2501.602
SKIMMER
EACH
$2,300.00
3
3
0
$6,900,00
15
2502.541
4" PERF PE PIPE DRAIN
LIN FT
$5.00
600
600
0
$3,000.00
16
2503.541
12" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$23.50
80
70
0
$1,645.00
17
2503.541
15" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$25,00
550
518
0
$12,950.00
18
2503.541
18" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$28.00
450
345
0
$9,660.00
19
2§03.602
CONNECT TO EXISTING STORM SEWER
EACH
$800.00
1
. 1
0
$800.00
20 -
2608.501
CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4020
LIN FT
$860.00
32
29.82
0
$25,645.20
21
2506.502
CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL (2'X31)rEACH
$1,400.00
4
4
0
$5,600.00
22
2506.516
CASTING ASSEMBLY
EACH
$520.00
7
9
0
$4,680.00
23
2511.501
RANDOM RIPRAP CLASS III - GROUTED
CU YD
$85.00
30
30
0
$2,550.00
24
2511.515
GEOTEXTILE FABRIC TYPE III
SQ YD
$7.00
80
120
0
$840,00
Totals For Section Storm Sewer improvements:
$83,780.20
Surface Improvements
25
2021.501
MOBILIZATION
LUMP SUM
$11,500.00
1
1
0
$11,500.00
26
2101.501
CLEARING
ACRE
$500.00
1.41
1.53
0
$766.00
27
2101.506
GRUBBING
ACRE
$500.00
1.41
1.53
0
$765.00
28
2104.501
REMOVE CONCRETE CURB AND GUTTER
LIN FT
$2.00
240
340
0
$680.00
29
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
$1.00
850
918
0
$918.00
30
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$2.00
170
192
0
$384.00
31
2105.501
COMMON EXCAVATION (P)
CU YD
$3.30
2500
5235
2735
$17,275.50
32
2105.507
SUBGRADE EXCAVATION
CU YD
$3.80
220
558
0
$2,120,40
33
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
$14.80
3180
2751.6
0
$40,723.68
34
2105.523
COMMON BORROW (CV)
CU YD
$11.70
6000
5256.29
2223
$61,498,59
35
2105.607
POND EXCAVATION (EV)
CU YD
$3.80
2100
2100
0
$7,980.00
36
2112.501
SUBGRADE PREPARATION
ROAD STA
$75.00
13
13
0
$975.00
37
2123.610
STREET SWEEPER (WITH PICKUP BROOM)
HOUR
$75.00
20
4.5
3
$337.50
38
2130,501
WATER (DUST CONTROL)
M GALLONS
$21.00
10
24
0
$504.00
39
2211.501
AGGREGATE BASE CLASS 5
TON
$13.00
4200
4520.86
0
$58,771.18
40
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
$2,50
420
330
0
$825.00
41
2360.501
TYPE SP 12.5 WEARING COURSE MIXTURE (3,B)
TON
$70.00
940
963.31
9
$67,431.70
42
2360.502
TYPE SP 12.5 NON WEARING COURSE MIXTURE (3,B)
TON
$70.00
940
873.19
0
$61,123.30
43
2506.522
ADJUST FRAME & RING CASTING ( SANITARY)
EACH
$175.00
1
1
0
$175,00
44
2521.501
6" CONCRETE WALK
SQ FT
$5.25
1570
1593
408
$8,363.25
45
2521.511
2.5" BITUMINOUS WALK
SQ FT
$2.20
8400
8576.5
0
$18,868.30
46
2531.501 _CONCRETE
CURB & GUTTER DESIGN B618
LIN FT
$9.60
3300
3132
0
$30,067.20
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
47
2531.602
CONCRETE MEDIAN NOSE DESIGN 7113
EACH
$325.00
2
2
0
$650.00
48
2531.604
7" CONCRETE VALLEY GUTTER
SQ YD
$65.00
20
0
0
$0.00
49
2531.618
TRUNCATED DOMES
SQ FT
$35.00
128
144
0
$5,040.00
50
2563.601
TRAFFIC CONTROL
LUMP SUM
$1,500.00
1
1
0
$1,500.00
51
2563.602
TYPE III BARRICADES
EACH
$150.00
14
8
0
$1,200.00
52
2564.531
SIGN PANELS TYPE C
SQ FT
$35.00
30
30
30
$1,050.00
53
2564.602
PAVEMENT MESSAGE (THRU ARROW) EPDXY
EACH
$150.00
2
5
0
$750,00
54
2564.602
SALVAGE AND REINSTALL SIGN
EACH
$100.00
1
1
0
$100.00
55
2565.616
REVISE SIGNAL SYSTEM
SYS
$12,000.00
1
1
0
$12,000.00
56
2573.502
SILT FENCE, TYPE MACHINE SLICED
LIN FT
$1.40
3600
3400
0
$4,760.00
57
2573.530
STORM DRAIN INLET PROTECTION
EACH
$80.00
11
9
0
$720.00
58
2573.602
TEMPORARY ROCK CONSTRUCTION ENTRANCE
EACH
$400.00
1
1
0
5400.00
59
2573.603
BIOROLL
LIN FT
$5.50
100
100
0
5550.00
60
2575.502
SEED MIXTURE 260
POUND
56.00
110
110
0
$660.00
61
2575,502
SEED MIXTURE 310
POUND
$7.00
70
70
0
$490.00
62- -
2575.506
SODDING, TYPE LAWN (INCL. TOPSOIL & FERT.)
SQ YD
$3.40
1900
750
0
$2,560.00
63
2575.511
MULCH MATERIAL TYPE 1
TON
$210.00
10
10
0
$2,100.00
64
2575.519
DISK ANCHORING
ACRE
$100.00
1.6
0
0
$0.00
65
2575.523
EROSION CONTROL BLANKETS CATEGORY 3
SQ YD
$1,20
3900
3600
0
54,320,00
66
2575.605
SEEDING (INCL. TOPSOIL & FERTILIZER)
ACRE
52,800.00
2.4
2.4
0
56,720.00
67
2582.501
PAVEMENT MESSAGE (LEFT ARROW) PAINT
EACH
$100.00
2
2
0
$200.00
68
2582.501
PAVEMENT MESSAGE (RIGHT ARROW) PAINT
EACH
$100.00
3
3
0
$300.00
69
2582.501
PAVEMENT MESSAGE (THRU ARROW) PAINT
EACH
$100.00
2
3
0
5300.00
70
2582.501
PAVEMENT MESSAGE (RIGHT ARROW) EPDXY
EACH
5150.00
3
4
0
5600.00
71
2582.501
PAVEMENT MESSAGE (LEFT ARROW) EPDXY
EACH
$150.00
2
2
0
$30Q.00
72
2582.502
4" SOLID LINE WHITE -PAINT
LIN FT
50.50
530
466
0
$233.00
73
2582.502
4" SOLID LINE YELLOW -PAINT
LIN FT
$0.50
400
0
0
$0.00
74
2582.502
4' DOUBLE SOUD LINE YELLOW -PAINT
LIN FT
51.00
1860
977
0
$977.00
75
2582.502
4" DOUBLE SOLID UNE WHITE-EPDXY
LIN FT
50.75
530
341
0
5255.75
76"'
2682.602
4" DOUBLE SOLID UNE YELLOW-EPDXY
LIN FT
$0.75
200
0
0
50.00
77
2582.502
4" DOUBLE SOUD LINE YELLOW-EPDXY
LIN FT
50.75
1860
934
0
$700.50
Totals For Section Surface Improvements:.
$441,477.85
Watermain Improvements
78
2021.501
MOBILIZATION
LUMP SUM
$1,800.00
1
1
0
51,800.00
79
2104.523
SALVAGE GATE VALVE & BOX
EACH
5200.00
2
2
0
$400.00
80
2104.523
SALVAGE HYDRANT
EACH
5250.00
2
2
0
5500.00
81
2451.609
GRANULAR FOUNDATION AND/OR BEDDING
TON
$24.00
10
0
0
$0,00
82
2504.602
CONNECT TO EXISTING WATER MAIN
EACH
5600.00
2
2
0
51,200.00
83
2504.602
HYDRANT
EACH
53,350.00
4
4
0
513,400.00
84
2504.602
8" GATE VALVE AND BOX
EACH
$1,325.00
4
4
0
55,300.00
85
2504.602
8" GATE VALVE AND BOX
EACH
$1,775.00
6
4
0
57,100.00
86
2504.602
16' GATE VALVE AND BOX
EACH
56,475.00
2
1
0
56,475,00
87
2504.602
INSTALL SALVAGED HYDRANT
EACH
5450.00
1
1
0
5450.00
88
2504,602
INSTALL SALVAGED GATE VALVE AND BOX
EACH
5200.00
1
1
0
$200.00
89
2504.603
6" WATER MAIN -DUCT IRON CL 52
LIN FT
$27.00
124
132
0
53,564.00
90
2504.803
8" WATER MAIN -DUCT IRON CL 52
LIN FT
$34.00
120
198
0
$6,732.00
91
2504.603
8" WATER MAIN -PVC C900
LIN FT
$17.50
450
446
0
57,805.00
92
2504.603
16" WATER MAIN -DUCT IRON CL 52
LIN FT
$63.00
1300
1189
0
$74,907.00
93
2504.608
DUCTILE IRON FITTINGS
POUND
$4.50
4600
3285
0
514,782.50
Totals For Section Watermain Improvements:
$144,615.50
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
Work Order 1
94 198183 ADD 8 X 6 REDUCER LUMP SUM $736.50
1
1 0
$736,5Q
Totals For Work Order 1:
$736,50
Work Order 2
96 981841LOCATE 21" STUB OUT OF MH LUMP SUM $1,795.50
1
1 0
$1,795,50
Totals For Work Order 2:
$1,795,50
Work Order 3
96 981851INSTALL TOPSOIL LUMP SUM1$6,930.00
1
1 0
$6,930.00
Totals For Work Order 3:
$6,930.00
Work Order 4
97 198225 PAINTING ZEBRA STRIPES !EACH 1 $86,401
161
16 0
$1,382.40
Totals For Work Order 4:
$1,382.40
Work Order 5
98
98226 PAINT DIAGONAL CROSS 'SF 1 55.501
241
24_ 0
$132.00
Totals For Work Order 5:
$132.00
Work Order 6
99 983741CUT E DITCH BETWEEN PONDS LUMP SUM $1,258.00
11
11 • 0
$1,258.00
Totals For Work Order 6:
$1,258.00
Work Order 7
100 983751MILL AND PATCH ASPHALT CRACK LUMP SUM' $1,575.00
11
11 0
$1,575.00
Totals For Work Order 7:
$1,575.00
Work Order 8
101 98699 SPRINKLER SYSTEM REPAIR AND INSTALLATION LS $3,695.811
11
1 1
$3,695.81
Totals For Work Order 8:
$3,695.81
Project Totals:
$817,418.46
Project Payment Status
Owner: City of Lino Lakes
Client Project No.:
Client Contract No.:
Project No.: 02029-11
Contractor. A-1 Excavating, inc.
Contract C
No.
Type
Date
Description
Amount
WO3
Work Order
6/19/2015
Install topsoil In ditch along Metro Translt as requested by City Engineer
$6,930.00
WO1
Work Order
6/19/2015
Add 8x6 reducer
$736.50
WO2
Work Order
6/19/2015
Locate 21" stub @ 85' out of MH
$1,795.50
W04
Work Order
7/21/2015
ADDED PAINTING - ZEBRA STRIPES AT "T'
$1,382.40
WO6
Work Order
9/3/2015
Cut Ditch on East Side of Road between 2 ponds.
$1,258.00
W08
Work Order
1/15/2016
Sprinkler system repair and installation
$3,695.81
WO7
Work Order
9/3/2015
Mill and patch crack in Asphalt from utilities lack of compaction
$1,575.00
W05
Work Order
7/21/2015
PAINTING DIAGONAL CROSS
$132.00
Change Order Totals:
$17,505.21
Pa Gilt Summ
No.
From
Date
To Date
Payment
Total
Payment
Retainage Per
Payment
Total
Retainage
Total Payment +
Retainage
Work Certified Per
Payment
Total Work
Certified
1
6/23/2014
7/18/2014
$273,284.12
$273,284.12
$14,383.38
$14,383.38
$287,667.50
$287,667.50
$287,667.50
2
7/19/2014
8/18/2014
$210,335.48
$483,619.60
$11,070.28
$25,453.66
$509,073.26
$221,405,76
$509,073.26
3 -
8/19/2014
10/31/2014
$162,314.20
$635,933.80
$8,016.54
$33,470.20
$669,404.00
$160,330.74
$669,404.00
4 : --t,
11/1/2014
6/22/2015
$29,218.86
$665,152,66
$1,537.84
$35,008.04
$700,160.70
$30,756.70
$700,160.70
5 :
6/23/2015
9/3/2015
$71,354.84
$736,507.50
$3,755,51
$38,763.55
$775,271.05
$75,110.35
$775,271.05
6 &
FINAL
9/4/2015
1/15/2016
$80,910.96
$817,418.46
($38,763.55)
$0.00
$817,418,46
$42,147.41
$817,418.46
Payment Totals:
$817,418.46
$0.00
$817,418.46
$817,418.46
Protect Summary
Material On Hand:
Total Payment to Date:
Total Rdtainage:
Total Amount Earned:
$0.00
$817,418.46 Original Contract
$0.00 Contract Changes:
$817,418.46 Revised Contract:
$841,971.00
$17,505.21
$859,476.21