HomeMy WebLinkAbout2016-100 Council ResolutionCITY OF LINO LAKES
RESOLUTION NO. 16-100
APPROVING PUD FINAL PLAN/FINAL PLAT FOR WOODS EDGE
WHEREAS, the City has received an application for PUD Final Plan/Final Plat for Woods Edge
hereafter referred to as "Development"; and
WHEREAS, City staff has completed a review of the "Development" based on the following:
• Application and plans submitted to the City on July 18, 2016.
• Revised plans received by the City on August 19, 2016 and August 26, 2016.
• Revised building plans and elevations received by the City on August 24, 2016.
WHEREAS, a public meeting was held before the Planning & Zoning Board on August 10,
2016 and the Board recommended approval of the "Development"; and
NOW, THEREFORE BE IT RESOLVED by The City Council of The City of Lino Lakes
hereby makes the following:
FINDINGS OF FACT
Per Section 1007.024(1) Purpose and Intent, the PUD, by allowing deviation from the strict
provisions of this Ordinance related to setbacks, heights, lot area, width and depths, yards, etc.,
by conditional use permit or a mixture of uses by rezoning to a PUD District, is intended to
encourage:
1. A development pattern in harmony with the objectives of the Comprehensive Plan.
The residential development is consistent with the goals and policies of the comprehensive plan
which anticipated development of this residential block as part of the mixed use Lino Lakes
Town Center. Woods Edge is consistent with land and density requirements and provides market
driven housing products that support life -cycle housing.
2. Innovations in development that address growing demands for all styles of economic
expansion, greater variety in type, design, architectural standards, and siting of
structures through the conservation and more efcient use of land in such developments.
The project site was planned as the residential neighborhood block with the mixed use Town
Center. The development will add urban townhomes in this planned development. This master
planned community offers housing options not available nowhere else in the community.
3. The preservation and enhancement of desirable site characteristics such as existing
vegetation, natural topography and geologic features and the prevention of soil erosion.
The site has limited natural desirable site characteristics. The site has been mass graded and has
no significant tree stands. The storm water management system that was previously constructed
will be upgraded and will incorporate additional improvements to meet current standards.
4. A creative use of land and related physical development which allows a phased and
orderly transition of varying land uses in close proximity to each other.
The master planned Town Center anticipated a mix of residential, commercial, office and public
uses. This project will allow development of the residential block.
5. An efficient use of land resulting in smaller networks of utilities and streets thereby
lowering development costs and public investments.
The residential development will use existing streets and trunk utilities, which will reduce the
development costs and required public investments.
6. Promotion of a desirable and creative environment that might be prevented through the
strict application of City zoning and subdivision regulations.
The purpose of the Town Center PUD was to create a mixed use development that could not
otherwise have been constructed under the standard zoning and subdivision regulations.
BE IT FURTHER RESOLVED by the City Council of The City of Lino Lakes hereby
establishes that Woods Edge shall be developed in accordance with the standards in the Lino
Lakes Town Center Design & Development Guide as amended by Ordinance No. 06-16.
BE IT FURTHER RESOLVED by the City Council of the City of Lino Lakes that the PUD
Final Plan/Final Plat is consistent with preliminary approvals granted by Resolution No. 16-67.
BE IT FURTHER RESOLVED by The City Council of The City of Lino Lakes hereby.
approves the PUD Final Plan/Final Plat for Woods Edge subject to the following conditions:
1. All comments from the City Engineer letter dated August 31, 2016 shall be addressed.
2. A Development Contract shall be executed by the City and the developer and recorded by
the developer.
3. A Maintenance Agreement for Stormwater Management Facilities shall be executed by
developer for privately maintained facilities.
4. Approval from Rice Creek Watershed District shall be required prior to recording of the
final plat.
5. Wetland conservation easement documents and exhibits shall be executed by the
developer cover that portion of Outlot C as defined in the Wetland Buffer Plan, dated
August 23, 2016.
6. Homeowner Association documents shall be required to be approved by the City
Attorney and filed with PUD Final Plan/Final Plat.
7. Park dedication for the Woods Edge plat shall be cash in lieu of land for 60 units. The
remaining park dedication shall be due with the final plat for Phase II.
2
8. Landscape Plan comments;
a. Outlot C is proposed to be seeded with MnDOT 33-261 which is a native mix.
While appropriate for the area, the developer will need to enter into a 3 year
maintenance contract with a qualified firm, to ensure establishment of the native
area. The contract should describe the annual maintenance activities prescribed
for each year of the contract.
9. A lighting plan must be submitted to show proposed private drive and driveway lighting.
Adopted by the Council of the City of Lino Lakes this 12th day of September 2016.
The motion for the adoption of the foregoing resolution was introduced by Council Member
Kusterman and was duly seconded by Council Member Maher and upon
vote being taken thereon, the following voted in favor thereof:
Kusterman, Maher, Manthey, Rafferty, Reinert
The following voted against same:
none
ATTEST:
-Jul`. ne Bartell, Ci y Cler
CITY COUNCIL
AGENDA ITEM 6A
STAFF ORIGINATOR: Kendra Lindahl, Landform
MEETING DATE: September 12, 2016
TOPIC: Woods Edge PUD Final Plan and Final Plat
(Case File No. FP2016-003 and PF2016-001)
i) Consider Resolution No. 16-100 Approving PUD Final
Plan/Final Plat
ii) Consider Resolution No. 16-101 Approving Development
Agreement (To Follow)
iii) Consider 2nd Reading of Ordinance No. 08-16 Vacating
Drainage and Utility Easements, Outlot B and Outlot D
of The Village No. 3*
*Council may vote to dispense with full reading of ordinance
* Roll call vote is required for adoption of the ordinance
�..., VOTE REQUIRED: 3/5
INTRODUCTION
Staff is requesting City Council consideration of the PUD Final Plan/Final Plat, Development
Agreement and Easement Vacation for Woods Edge.
Complete Application Date:
July 19, 2016
Environmental Board Meeting:
July 27, 2016
EDAC Meeting:
N/A
Park Board Meeting:
N/A
P & Z Board Meeting:
August 10, 2016
City Council Work Session
September 6, 2016
City Council Meeting:
September 12, 2016
60 -Day Review Date:
September 17 , 2016
60 -Day Extension:
November 16, 2016
1
BACKGROUND
Woods Edge is part of the Lino Lakes Town Center PUD that was approved in 2004. The
Planning & Zoning Board reviewed the PUD Development Stage/Preliminary Plat review and a
text amendment for the "Lino Lakes Town Center Design & Development Guide" on June 8,
2016 and the City Council approved the project on July 11, 2016. The proposed development is a
112 unit attached townhome project on 11.2 acres in the Town Center (Outlots B and C of the
Village No. 3). The Final Plat and PUD Final Plan request is for approval of Phase I of this
project.
The project also includes a request for vacation of a drainage and utility easement, which will be
considered at a public hearing at the August 22nd and September 12th Council meetings.
Previous Council approvals include:
• Resolution No. 16-67 approving PUD development stage plan and preliminary plat
• Ordinance No. 06-16 ordinance text amendment to modify the residential development
standards for Lino Lakes Town Center for Woods Edge established by Ordinance No. 04-
04
• Resolution No. 16-74 Approving Summary Publication of Ordinance No. 06-16
The current Land Use Application is for consideration of the following:
• PUD Final Plan/Final Plat
The Planning Commission reviewed the request at their August 10th meeting and recommended
approval.
ANALYSIS
Revisions to PUD Development Stage Plan/ Preliminary Plat
Resolution No. 16-67 approved the PUD Development Stage Plan/Preliminary Plat with
conditions required prior to approval of the PUD Final Plan/Final Plat. The conditions have been
satisfied unless otherwise noted in this report.
Land Use and Density
The property is guided Mixed Use and zoned PUD as part of the Town Center master plan. The
density is 10 units per acre (112 units on 11.2 acres). This is consistent with the Town Center
standards, which require a minimum of 10 units per acre and a maximum of 24 units per acre.
The final plat is for phase 1, which includes 65 lots and 13 outlots. The plat includes 60 homes as
well as common lots maintained by the HOA and outlots for future development or permanent
2
open space. The remaining 52 homes will be a second phase of construction. The applicant will
submit a final plat for that 2nd phase for City approval.
PUD Final Plan/Final Plat
Conformity with the Comprehensive Plan and Zoning Code
The PUD Final Plan/ Final Plat has been reviewed for compliance with the comprehensive plan,
zoning and subdivision ordinance. The proposed development meets the performance standards
of the subdivision and zoning ordinance.
Blocks and Lots
The final plat creates 65 lots and 13 outlots. Outlots A and B are the internal private streets that
will be built to serve the project. Outlot C primarily stormwater ponds and wetland. The
remaining outlots are for future townhome development.
Easements
Standard drainage and utility easements are being dedicated on individual lots and over
stormwater management facilities.
The drainage and utility easements are being dedicated over Outlot C for protection of the
stormwater management ponds, wetlands and wetland buffers.
There is also a drainage and utility easement over Lot 8, Block 2 for the stormwater management
area.
Street and Utilities
The public streets that will provide access to the site were previously constructed and will
provide the primary access to the site. New private streets will be constructed to provide internal
access and they will be owned and maintained by the homeowners association (HOA). These
private drives are currently shown as 26 -feet wide (back-to-back). This is consistent with City
standards.
Architecture
The applicant is proposing a mix of 4-8 unit buildings. The buildings all provide access via new
private streets and have front porches facing the existing public streets (Town Center Parkway,
Village Drive and Woods Edge Boulevard). All of the townhomes will be part of a homeowners
association (HOA) that will be responsible for maintenance of the common areas, including the
private streets. The HOA will provide snow removal and landscape maintenance for the
individual lots and the common areas.
The City Council did approve a text amendment allowing vinyl siding on the homes. However,
there was much discussion about the appearance of vinyl. In order to retain the higher quality
3
appearance of buildings in the Lino Lakes Town Center, the applicant has revised the plans to
provide LP or Hardi-board trim on the units rather than vinyl. Only the horizontal trim will be
vinyl to ensure seamless siding installation—all window and vertical trim on the buildings will
be LP or Hardi-board.
Park Dedication
Park dedication shall be cash in lieu of land at $2,500 per unit ($150,000 total for the 60 units in
Phase I). Outlot D will be conveyed to the City for public trail purposes.
Additionally, the City is working with Anoka County Parks to development a playground south
of Outlot C and Outlot D.
Development Agreement
A Development Agreement has been drafted by the City and shall be executed by the developer.
Easement Vacation
The applicant has submitted a land use application requesting the vacation of drainage and utility
easements of Outlot B and Outlot D, The Village No. 3.
The easement on Outlot B is over stormwater ponds and drainage areas. New drainage & utility
easements will be rededicated on the final plat of Woods Edge. The easement on Outlot D is over
an existing watermain. This watermain is being relocated under the private road (Outlot A,
Woods Edge) and the easement no longer is needed.
On August 22, 2016, the City Council held a public hearing and approved the 1St reading of
Ordinance No. 08-16.
RECOMMENDATION
The Planning & Zoning Board reviewed the PUD Final Plan/Final Plat on August 10, 2016. The
Board and staff recommend approval of the following items with conditions as listed in the
following documents:
1. Resolution No. 16-100 Approving PUD Final Plan/Final Plat
2. Resolution No. 16-101 Approving Development Agreement
3. Ordinance No. 08-16 Approving Easement Vacation
4
ATTACHMENTS
1. Resolution No. 16-100
2. PUD Final Plan
3. Final Plat
4. City Engineer Letter dated August 31, 2016
5. Resolution No. 16-101
6. Development Agreement and Planned Unit Development Agreement (To Follow)
7. Ordinance No. 08-16