APPROVAL OF MINUTES
It was moved by Mr. Colgan to approve the minutes from February 2, 2017. The motion was
seconded by Mr. Kohler and passed unanimously.
DISCUSSION ITEMS
A. Great River Energy – Data Center
Mr. Grochala explained that the City has had a long time goal of developing a business park
along the I-35 corridor. He discussed the emergence of data centers as a potential high value
economic development opportunity for this area. He introduced Mr. Tom Lambrecht of Great
River.
Mr. Lambrecht provided an overview of Great River Energy’s role as an energy provider in the
metro area and their Data Center Site Certification program. He explained that the 35E corridor
had several positives related to data center siting including is relative proximity to the MSP
airport. Mr. Lambrecht noted that data centers can be large multimillion dollar facilities. Great
River established the site certification program in part because data centers are large and steady
energy users. Minnesota has become a target for center location to because of attractive tax
exemptions provided by the state. Mr. Lambrecht provided the board with a description of
different facility types. He explained that there are co-location centers which lease building area
to multiple companies as well and large enterprise facilities serving a single company.
2
The committee members asked what the benefits are to the community. Mr. Lambrecht stated
that while they don’t create a lot of permanent on-site jobs they do have a lot of contractors
servicing the site. The buildings are typically have a high tax value and place a minimal demand
on public services.
Mr. Lambrecht noted that Great River Energy started the Qualifying City program in 2007. The
intent was to expedite the site selection process. The program has a standard format/pre-
qualification checklist to qualify the site in a quick transaction.
Mr. Masonick asked where the closest data center is. Mr. Lambrecht stated that Wells Fargo has
their facilities off of County Road J. Mr. Masonick asked what type of investment is made by
the company. Mr. Lambrecht provided an example of a project in Chaska that was a 268 million
dollar project.
EDAC discussed the merits of assisting with the site certification process. Mr. Grochala noted
that site certification provides a marketing advantage and can streamline the approval process.
However, the City could choose to what extent it wants to contribute or potentially cost share
with property owners.
Mr. Kohler asked how many sites where currently in the GRE program. Mr. Lambrecht stated
they currently have 4. EDAC continued to discuss the site certification process, City’s role, and
how cost sharing and potential reimbursement would work.
The Committee requested further discussion on the program and more specifically, data centers
at a future EDAC meeting.
B. Project Updates
Mr. Grochala explained that Mattamy Homes, developer of Watermark, is selling all of their
Minnesota holdings. This includes the Lino Lakes site. Mattamy is actively marketing the site
and working with a potential buyer.
ADJOURNMENT
It was moved by Mr. Colgan to adjourn the meeting. The motion was seconded by Mr. Vojtech.
The meeting was adjourned at 9:25 AM.