HomeMy WebLinkAbout10-08-2012 Council Minutes COUNCIL MINUTES October 8, 2012
APPROVED
1 CITY OF LINO LAKES
MINUTES
3
4 DATE : October 8,2012
5 TIME STARTED : 6:30 p.m.
6 TIME ENDED : 8:05 p.m.
7 MEMBERS PRESENT : Council Member Stoesz, O'Donnell, Rafferty,
8 Roeser, and Mayor Reinert
9 MEMBERS ABSENT : none
10
11 Staff members present: City Administrator Jeff Karlson; Community Development Director Michael
12 Grochala; City Attorney Joseph Langel; City Engineer Jason Wedel; Chief of Police John Swenson;
13 and City Clerk Julie Bartell
14
15 PUBLIC COMMENT
16
17 No one addressed the council regarding a matter not on the agenda.
18
19 SETTING THE AGENDA
20
21 The agenda was approved as presented.
23 SPECIAL PRESENTATION
25 Charter Amendment Update—Community Development Director Grochala offered information on
26 the charter amendment that will appear on the November 6,2012 ballot. He stressed that city
27 residents should get informed about the amendment that involves how the city deals with public
28 improvements. He noted that information is available on the city Website and at a kiosk at city hall.
29 One question often asked is what is the history on this topic. He noted a report done by a citizen task
30 force in 2008 that makes recommendations on improving the public improvement process. The
31 amendment on the ballot in November is essentially the ordinance recommended by the task force
32 with a couple changes, one being adding a reverse referendum that would bring a question to the
33 voters. He compared the proposed public improvement process to the current process.
34
35 Council Member Roeser confirmed that it was a citizen group that originally brought the changes
36 forward, not the city council. Also he noted that the amendment would be a continuation of this
37 council's efforts to reduce government.
38
39 Mayor Reinert offered the following points:
40 - This proposal is about city roadways, not those under the jursidiction the county or state;
41 - The process is not about maintenance of roadways,but when a road requires reconstruction;
42 - In most cities,the city council makes the decision and everyone is billed for the work. But 30
43 years ago,this city made a different choice recognizing that an increase in property value may
44 occur and he agrees with that different choice. However, since that other choice was decided,
1
COUNCIL MINUTES October 8, 2012
APPROVED
45 only one road has been reconstructed in this city; others have been brought forward for
6 consideration but have failed;
'"47 - It costs money to put forward plans for road construction; for instance a feasibility study is
48 necessary, and if the plans don't proceed,the expense of that study falls to the city;
49 - Mainly this changes the way that people decide how their own street will be treated;
50 - The amendment addresses the problem of scope, allowing the people getting the
51 improvements to vote on what will be done (water, sewer,roadway or a combination).
52
53 He added that the proposed process will still allow for a city wide vote if that is called for. The
54 bottom line is that the city has to get to a point where there is a process that works to get necessary
55 road work done.
56
57 CONSENT AGENDA
58
59 Council Member Rafferty moved to approve the Consent Agenda, Items 1A through 1D. Council
60 Member Stoesz seconded the motion. Motion carried on a unanimous voice vote.
61
62 ITEM ACTION
63
64 Consideration of Expenditures:
65
66 October 8, 2012 (Check No. 94224-
67 94428, $160,903.11) Approved
L168
69 Centennial Fire District(Check No. 5514-
70 5538, $41,145.16) Approved
71
72 September 24, 2012 Council Work Session
73 Minutes Approved
74
75 September 24, 2012 City Council Meeting
76 Minutes Approved
77
78 September 24, 2012 Special Work Session Minutes Approved
79
80 FINANCE DEPARTMENT REPORT
81
82 There was no report from the Finance Department.
83
84 ADMINISTRATION DEPARTMENT REPORT
85
86 3A) Adoption of Minnesota Snow and Ice Control Handbook—Administrator Karlson noted that
87 in July the council approved an agreement with the Rice Creek Watershed District and in order to
88 qualify for the grant funds associated with that agreement,the city must adopt the associated
2
COUNCIL MINUTES October 8, 2012
APPROVED
89 Minnesota Snow and Ice Control Handbook. He noted that staff has already been trained with the
L.20 handbook.
91
92 Council Member O'Donnell moved to approve adoption of the Handbook as submitted. Council
93 Member Roeser seconded the motion. Motion carried on a unanimous voice vote.
94
95 PUBLIC SAFETY DEPARTMENT REPORT
96
97 There was no report from the Public Safety Department.
98
99 PUBLIC SERVICES DEPARTMENT REPORT
100
101 There was no report from the Public Services Department.
102
103 COMMUNITY DEVELOPMENT DEPARTMENT REPORT
104
105 6A) Consideration of Resolution No. 12-59,Establishing Cartway—Community Development
106 Director Grochala noted the resolution before the council that would provide for establishment of a
107 cartway on Otter Lake Drive. This process has been on-going, with a public hearing held by the
108 council in July and discussions at various council meetings.
109
110 City Attorney Langel reviewed the resolution and cartway process. The petition submitted by Adam
11 Johnson(the"Petitioner")requests a cartway between parcels of his land, over a private road and a
L.112 bridge that is owned by a homeowners' association(the"HOA"). The city council is responsible for
113 deciding if the statutory requirements for establishing a cartway are met, deciding on the location of
114 the cartway and determining damages to the owner of the land. The city has received information
115 from the involved parties. Staff feels that the threshold for establishing the cartway has been met.
116 On the question of location,the existing roadway and bridge are the most sensible location(the
117 survey of the proposed cartway was submitted by Petitioner and included in the staff letter). On the
118 question of damages, Mr. Langel noted that both parties submitted information. There is a wide
119 divergence between the two sides on the amount of damages. Staff has put forth in the report one
120 proposed means of determining damages; it is not the only way to make that determination. The
121 Petitioner has to pay damages and construction costs for the cartway. Mr. Langel also noted that the
122 cartway width would be the width of the roadway and the cartway cannot be utilized until all damages
123 have been paid. The resolution submitted to the council now contains the points mentioned this
124 evening and also some blanks for council consideration. On the question of ongoing maintenance,
125 the council is additionally responsible for determining the costs and a formula is proposed.
126
127 The mayor remarked that it appears that the majority of the council has determined that the cartway is
128 allowed under state law. On the matter of damages, Attorney Langel explained in terms the
129 recommendation of the HOA ($748,000) and the recommendation of the Petitioner($1,343.38). The
130 HOA estimate includes three areas of damages:to the land itself(the entirety of Outlot A),to the
131 roadway/bridge, and severance. Mr. Langel noted that his issues of concern about the HOA estimate
132 are mainly on the basis that they used the entirety of the Outlot for the calculations and that severance
L. 133 wouldn't apply in this case. Staff's suggestion(and not the only option) is that the council look at
3
COUNCIL MINUTES October 8, 2012
APPROVED
134 Petitioner's portion of the land,the bridge and the roadway to extent that he will utilize them. With
that basis for calculation,the damages would come to approximately$52,000. Maintenance costs
136 would be beyond the calculation of damages. He explained that the HOA has reported that
137 maintenance costs are not the same every year and there are costs to plan for in the future. The
138 resolution reflects the option that Petitioner would pay 1/6 of the cost of maintenance of the bridge
139 and 1/6 of 12 percent for the roadway.
140
141 Council Member Roeser asked how Mr. Johnson would receive information about maintenance since
142 he would not be a member of the HOA. Attorney Langel explained that damages and future costs
143 would be a private matter between the HOA and Mr. Johnson and he could specify that in the action.
144
145 Council Member O'Donnell clarified that the cartway would,by default, be established as a public
146 cartway but that the HOA could request the council to accept it as a private cartway by resolution.
147
148 Attorney Joe Barnett, on behalf of Petitioner Adam Johnson, addressed the council. He pointed out
149 that it is clear that the threshold for establishing the cartway is met. Mr. Johnson is concerned that, in
150 determining damages,the council should clearly understand that his use of the roadway and bridge
151 will just be access and he will have no ownership rights. The damage estimate offered by Mr.
152 Johnson represents that best. He won't be causing a burden to the HOA.
153
154 Mark Smith, HOA member,told the council that he believes the professional appraisal of damages
155 submitted by the HOA represents best, or even under, a fair assessment of the damages. He believes
'56 that the Petitioner should be able to move across the bridge and then directly down to his property-
Ll57 that would be less use of the roadway. Mr. Smith also pointed out that the roadway also has a storm
158 drain element that was very expensive; he's not certain that is being taken into consideration. Also
159 how would enforcement be handled? Attorney Langel responded that the damage amount determined
160 by the council would eventually become a judgment and would be enforceable as such.
161
162 The council discussed establishment of the cartway and the following elements:
163 - The threshold for a cartway is there;
164 - The private bridge and roadway involved are quite expensive;
165 - The suggestions for the amount of damages range from $1,800 to more than $700,000; the
166 attorney is presenting a damage suggestion between those two;
167 - A question of drainage infrastructure and how it may serve the Petitioner's property has been
168 raised;
169 - A suggestion has been raised to shorten the cartway to the end of the bridge but it's unclear if
170 that is topographically possible; would a shortened cartway mean lower maintenance cost;
171 - Use of the property may be discussed but not as part of establishment of the cartway;
172
173 Some council members indicated that they still have questions about establishment of the cartway.
174 The council concurred that a special meeting would be held on October 15, 2012 at the site of the
175 proposed cartway and bridge.
176
177 Council Member Roeser indicated that he sent information to the city administrator including an
,178 alternative for this situation. He asked that staff share that information with the council.
4
COUNCIL MINUTES October 8, 2012
APPROVED
179
'to Council Member Rafferty moved to postpone consideration of this agenda item to the next work
-r>t 1 session on October 22, 2012. Council Member Roeser seconded the motion. Motion carried on a
182 unanimous voice vote.
183
184 6B) Consideration of Resolution No. 12-103,Approving the final payment for sealcoat striping
185 —City Engineer Wedel explained that the resolution authorizes for the separated portion of the
186 sealcoat project that provides for striping. He explained the costs and savings involved in separating
187 this element.
188
189 Council Member O'Donnell moved to approve Resolution No. 12-103 as presented. Council
190 Member Roeser seconded the motion. Motion carried on a unanimous voice vote.
191
192 UNFINISHED BUSINESS
193
194 There was no Unfinished Business.
195
196 NEW BUSINESS
197
198 There was no New Business.
199
200 COMMUNITY CALENDAR
--�01
L J2 Community Calendar—A Look Ahead
203 October 8,2012 through October 22,2012
204
205 45, Monday, October 22 5:30 pm, Community Room Council Work Session
206 Monday, October 22 6:30 pm, Council Chambers City Council Meeting
207
20$ COMMUNITY EVENTS
209
210 Gobbler Games at Centennial Middle School on November 3, 10:00 a.m. to Noon—This Free
211 family event is sponsored by the Lino Lakes Parks and Recreation Department. The event consists of
212 low-key competition in a variety of athletic events,pairing up children(ages 4-14)with adults.
213 Refreshments will be available to enjoy after completion of the events. This is a free event and no
214 pre-registration is required.
215
216 Lino Lakes Recycling Saturday, October 20, 10:00 a.m. to 2:00 p.m.,Lino Park, 7850 Lake
217 Drive. Recycling Day in Lino Lakes is now every third Saturday-Join residents in dropping off
218 items such as electronics,tires, batteries, household goods and computers. For more information,
219 contact city hall at 651-982-2424. This is part of an effort to expand our city's residential and
220 business recycling—"LINO LAKES RECYCLES AT HOME, AT WORK AND ON THE GO!"
221
222
''23
5
COUNCIL MINUTES October 8, 2012
APPROVED
224 ADJOURN
` �5
226 There being no further business, Council Member Rafferty moved to adjourn at 8:05 p.m. Council
227 Member Roeser seconded the motion. Motion carried unanimously.
228
229 These minutes were considered and approved at the regular Council ►A -- '.•_ :• October 22 2012.
230
231
232 aloo
2,i l Gum A
234 u 1.4 e Bartell, City lerk Jeff Rei'e , ayor
235
6