CITY OF LINO LAKES
RESOLUTION NO. 20-123
APPROVING PAYMENT NO. 5 AND FINAL FOR THE PHEASANT HILLS CIRCLE
PROJECT
WHEREAS, on May 13, 2019, the City Council passed resolution 19-59, awarding the contract
for the Pheasant Hills Circle Project to T.A. Schifsky & Sons, Inc. in the amount of $158,878.30;
WHEREAS, on August 12, 2019, the City Council passed resolution 19-97, approving Change
Order No. 1 for service repairs in the amount of $65,524.25;
WHEREAS, a complete summary of costs are detailed in Payment No. 5 (Final) where the final
Base Bid amount was $166,334.85 and the Change Order No. 1 was $59,591.94;
NOW, THEREFORE, BE IT RESOLVED by the City Council of Lino Lakes that Payment
Request No. 5 (Final) is approved for a final contract amount of $227,926.79.
Adopted by the Council of the City of Lino Lakes this 26th day of October, 2020.
The motion for the adoption of the foregoing resolution was introduced by Council Member
Ly ct.en and was duly seconded by Council Member S-tbe s Z and upon
vote being taken thereon, the following voted in faavor{-thereof:
Lydevt, Sfioest Ru (a-wd C�.Vecv�. Ra,o
v -41
The following voted against same:
ATTEST:
f4- blILr
fferty, Mayor