September 7 , 1982
�\ The regular meeting of the Lino Lakes Park Board was called to order
at 7 :30 P.M. , September 7 , 1982 with the following members present;
Arntzen, Scherer, Flannery , K. Johnson . Absent; R . Johnson, LaBlond ,
Lindy .
MINUTES
Mr . Scherer moved to approve the minutes of July 6 , 1982 as presented.
Seconded by Mr. Arntzen . Motion carried unanimously .
COUNTRY LAKES PARK
Mr . K. Johnson turned the meeting over to Mr. John Davidson, City
Engineer, to discuss the plans for the development of Country Lakes
Park.
Mr . Davidson noted that he had worked with the concept as prepared by
Mrs . Doris Sullivan . He had prepared a suggested schedule for the
phase development of the park starting with the beach area . He reported
that in dredging the beach area , the DNR is not concerned with the
dredging, but with the storage of the dredged material . A suitable
place will be needed to store the material for drainage . This material
can be allowed to dry and possibly be used for top dressing in some other
area of the park. The next step would be to fill the dredged area with
sand, if needed . The second phase of the beach area would be to con-
struct the beach shore area . This would entail the removal of all
vegation , preparing the soils and the filling with beach sand . Mr .
Davidson noted that the beach area should be clearly defined by some
sort of a harried - railroad ties , concrete bumpers , etc .
The third phase of the development in the beach area would be the con-
struction of the beach house . This will involve the drilling of a water
well and the installation of a septic system. These should be done be-
fore the actual construction of the building begins . Then the trail
system to connect the beach area with the parking lots will be necessary .
Mr. Davidson outlined the procedure for the preparation and construction
of this system. This would then cover the first phase of construction .
The Second phase would include the roadway system and parking lots . Mr.
Davidson explained the steps necessary to construct the roadways .
The Third phase , as suggested by Mr . Davidson , would be the installation
of the trailer parking and the boat launch . There would be some extra
work necessary in this area .
The Fourth phase would be the construction of the picnic area . Mr.
Davidson wondered if this phase should not be switched with phase three .
Mr. Davidson suggested, in developing the picnic area , perhaps some area
for shoreline fishing should be provided . He outlined the steps to be
taken in the development of this area noting that the picnic tables
should be either cement tables or cemented into a slab to prevent
vandalism.
Park Board
September 7, 1982
Page Two
There was discussion on the possibility that the access road may need
to be relocated. The depth of the lake and possible problems in dealing
with this problems was also discussed.
Mr. Lindy had arrived.
There was a motion (could not hear who made the motion) to approve the
following development plan for Country Lakes Park
Phase I - BEACH AREA
a) Lake Development
b) Construction of Beach Area
c) Construction of connecting Trail System
Phase II - ACCESS ROAD - PARKING FACILITIES
a) Access Road
b) Parking Lot A
c) Parking Lot B
d) Parking Lot C
PHASE III - CONSTRUCTION OF BATH HOUSE
a) Drill water well
b) Construct Septic system
c) prepare footing and pour slab
d) Construct building
PHASE IV - FISHING & PICNIC AREA
a) Lake Development
b) Picnic Area
c) Trail system
PHASE V- BOAR LAUNCH FACILITY
a) Lake Development
b) Access Facility
c) Trailer Parking Lot
Mr. Scherer moved to approve the above schedule of development .
Seconded by Mr. Flannery . Motion carried unanimously .
Mr. Flannery moved to recommend a feasibility report on all phases of
the development of the park. Seconded by Mr. Arntzen . Motion carried
unanimously .
There was discussion on the construction of the bathhouse - design ,
materias , changing areas need, interior facilities needed , etc. There
was suggestion that Mr . Schumacher discuss this with an architect -
just the basics to determine the size of a building with an estimated
cost . This would give the Park Board some place to start . Mr. Arntzen
and Mr. Lindy were appointed to work with the architect from Hugo on
this matter.
Park Board
September 7 , 1982
Page Three
OLD BUSINESS
Mr. Flannery - Study on Recreational Needs - Mr. Flannery reported that
he had worked up two items to include a survey . Mr. Flanner presented
the surveys that he had prepared noting that he had worked with a Mr .
Fox from Washington County .
He asked the Members to take a Zook at the survey he had designed, come
back with any suggestions they might have and discuss at the next
meeting. Mr . Flannery had also put together some estimated costs -
79 . 00 per thousand in the manner in which he has presented.
There was general discussion on the type of information this survey
would generate and how this could affect the plans for parks in this
City in the future .
Clerk ' s Note :
There was discussion concerning the LAWCON Grant , the Park building
at City Hall Park and the Budget . However, there is no tape on these
discussions . If there were items that you wish included in the minutes ,
please correct and include on the tapes and I will see that it is
recorded. Thank You .