HomeMy WebLinkAbout2022-048 Council Resolution CITY OF LINO LAKES
RESOLUTION NO.22-48
APPROVING THE CONSTRUCTION SERVICES CONTRACT
WATER TOWER NO.2 REHABILTATION PROJECT
WHEREAS,pursuant to the City Council awarding a construction contract to Classic Protective
Coatings,Inc. in the amount of$1,188,857.80 on February 14,2022; and
WHEREAS,WSB and Associates and KLM Engineering has submitted a proposal to complete
the construction services for the Water Tower No. 2 Rehabilitation Project in the amount of
$127,600.00; and
WHEREAS,the City Council finds that it would be in the best interests of the city to proceed with
the construction oversight and administration,
NOW,THEREFORE,BE IT RESOLVED by the City Council of the City of Lino Lakes,the
Mayor and Clerk are hereby authorized and directed to enter into a contract with WSB and
Associates and KLM Engineering, in the name of the City of Lino Lakes for the construction
services of Water Tower No. 2 Rehabilitation Project.
Adopted by the Council of the City of Lino Lakes this 9th day of May, 2022.
The motion for the adoption of the foregoing resolution was introduced by Councilmember
Cavegn and was duly seconded by Councilmember Lyden and upon vote being taken thereon,
the following voted in favor thereof: Lyden, Ruhland, Stoesz, Cavegn, Rafferty
The following voted against same: None
Rob Rafferty, Mayor
ATTEST:
'\..Tuli e Bartell, City ler —
CITY COUNCIL
AGENDA ITEM 5A
STAFF ORIGINATOR: Diane Hankee PE, City Engineer
MEETING DATE: May 9, 2022
TOPIC: Consider Resolution No. 22-48, Approving Construction Services
Contract, Water Tower No. 2 Rehabilitation Project
VOTE REQUIRED: 3/5
INTRODUCTION
Staff is requesting City Council's consideration to approve a construction services contract for
the Water Tower No. 2 Rehabilitation Project.
BACKGROUND
On February 14,2022,the City Council awarded the construction contract for the Water Tower
No. 2 Rehabilitation Project to Classic Protective Coatings,Inc. in the amount of$1,188,857.80.
The project is expected to last approximately 16 weeks and be completed in the fall of 2022.
WSB and Associates and KLM Engineering have submitted a proposal to complete the
construction services for the Water Tower No. 2 Rehabilitation Project in the amount of
$127,600.00. Funding for the project is through the Water Operating Fund.
RECOMMENDATION
Staff recommends adoption of Resolution No. 22-48,Approving the Construction Services
Contract for the Water Tower No. 2 Rehabilitation Project, in the amount of$127,600.00.
ATTACHMENTS
1. Resolution No. 22-48
2. WSB &KLM Proposal
Wsb
April 14, 2022
Mr. Justin Williams
Public Works Superintendent
City of Champlin
600 Town Center Pkwy
Lino Lakes, MN 55014-1182
Re: Proposal for Construction Phase Services
Water Tower Rehabilitation No. 2
City of Lino Lakes, MN
Dear Mr. Williams,
We appreciate the opportunity to submit this letter proposal to the City of Lino Lakes to
provide construction administration, full-time construction observation services, and
post construction services for the rehabilitation of the City's Water Tower No. 2
Rehabilitation. WSB will provide all construction administration and KLM will work as a
subconsultant to WSB and provide the construction observation and a post construction
2-year warranty inspection of the tower.
Construction Services
We will provide the following construction phase services for this project:
a) Print and distribute construction contracts to Owner and Contractor.
b) Coordinate and attend a preconstruction meeting with the Contractor.
c) Provide full-time construction observation and determine if the work is
proceeding in general accordance with the Contract Documents and AWWA
standards. Inspection time includes full-time construction observation for a
duration of 12 weeks. The NACE certified inspector will primarily focus on areas
of abrasive blasting, surface preparation, and documentation of environmental
(temperature, relative humidity, etc.) to verify that adequate conditions are
present for work to proceed.
d) Provide daily construction administration and correspondence with the
Contractor.
e) Maintain job site files for shop drawings, correspondence, field inspection
reports, construction photographs, field orders, change orders, etc.
Review the Contractor's applications for payments with the Engineer.
g) Coordinate and manage on-site meetings with the City and the Contractor to
discuss progress.
Mr. Justin Williams
April 14, 2022
Page 3
h) Review site and prepare punch lists.
Post Construction Services (2-Year Warranty Inspection)
a) The work will be specified with a standard 2-year warranty. It is critical to inspect
a water tower just prior to the end of the 2-year warranty period because coatings
that fail within 2-years will likely continue to fail after the warranty expires. A
certified NACE inspector will conduct the warranty inspection to identify defects
with the interior wet coatings. The interior dry and exterior coatings will also be
inspected. An inspection report will be prepared, and the Contractor will be
notified to repair any defects that are identified during the 2-year warranty
inspection. Post construction inspection services for repair work are not included
in this proposal but can be provided for additional fees if the Contractor is
required to make warranty repairs if requested by the City.
Schedule
We will begin the construction phase services immediately after authorization. The
proposed schedule includes the following milestone dates:
Task Dates
Substantial Completion August 15, 2022
Final Completion September 12, 2022
Post Construction (Warranty Inspection) August 15, 2024
Estimated Fees
WSB and KLM will complete the proposed design and bidding services for an hourly,
not-to-exceed cost of$127,544.00. We estimated the following fees for this project
based on a 12-week construction period. Actual charges will be based on the time
required for each task during the construction phase. Additional services, if requested
and approved by the City, will be invoiced on the basis of actual hours spent at current
billing rates. All services will be invoiced monthly. The following table and attached
spreadsheet provide a breakdown of the estimated task hours and fees.
Task WSB Fees KLM Fees Total Fees
I. Construction Phase Services $20,453.00 $102,798.00 $123,251.00
II. Post Construction Phase Services $1,093.00 $3,200.00 $4,293.00
Total Construction and Post Construction Services $21,546.00 $105,998.00 $127,544.00
This letter represents our understanding of the construction phase and post
construction phase services for the Water Tower No. 2 Rehabilitation project. If you
are in agreement with the scope of services and proposed fee, please sign in the
appropriate space below and return one copy to us.
Mr. Justin Williams
April 14, 2022
Page 3
Sincerely,
WSB
Greg F. Johnson, PE
Director of Water/Wastewater
Cc: Rick DeGardner, City of Lino Lakes
Michael Grochala, City of Lino Lakes
Diane Hankee, WSB
ACCEPTED BY:
City of Lino Lakes, Minnesota
By
Its
Date
Estimate of Hours and Fees
WS b City of Lino Lakes,Minnesota
Water Tower No.2 Rehabilitation Construction and Post Construction Services
Estimated Hours
Prof City Engineer Admin
Manager Total Hours Cost
Task Deseri lion Greg Johnson Diane Hankee Karla Pederson
1 Constriction Services
1.1 Print and distribute Construction Contracts to Owner and Contractor. 2 2 $194.00
Coordinate and attend a preconstruction meeting with the Contractor and distribute
1.2 meeting minutes. 3 1 4 $790.00
1.3 Provide ail construction administration and comes ondence with the Contractor. 66 4 1 71 $14,381.00
Maintain job site files for shop drawings,correspondence,field inspection reports,
1.4 onstruction halo ra hs,field orders,change orders,etc. 0.5 1 1.5 $200.00
1.5 Review the Contractors applications for payments with the En in 3 3 3 9 $1,425.00
1.6 Attend month) meetings with the Ci and the Contractor to discuss r 10 2 _ 12 $2,404.00
1.7 Review site and repares unch lists. 3 2 1 6 $1,059.00
1.8 KLM Fees $102,798.00
Task 3 Total Estimated Hours and Fees 85.5 12 8 105.5 123,251.00
2- Post-Construction Services T—Year Warranty Inspection)
2.1 Provide two-earwarran administration and protect management 4 1 1 B $1,093.00
2.2 Provide two a ection and re art b KLM. $3,200.00
Task 2 Total Estimated Hours and Fees 4 1 1 6 $4,293.00
Total Estimated Houmfor All Tasks 89.5 1 13 1 9 111.5
Average Hourly Billing Rate 206 172 97