HomeMy WebLinkAbout06/29/2022 EB Packet
CITY OF LINO LAKES
ENVIRONMENTAL BOARD MEETING
Wednesday, June 29, 2022
6:30 p.m.
Council Chambers
AGENDA
1. CALL TO ORDER AND ROLL CALL
2. PLEDGE OF ALLEGIANCE
3. APPROVAL OF AGENDA
4. APPROVAL OF MINUTES: May 4, 2022
5. OPEN MIKE
6. ACTION ITEMS
A. Villas on Vicky Concept Plan Review
7. DISCUSSION ITEMS
A. MS4 Annual Report and Public Comment Opportunity
8. UPDATES
A. Introducing new Recycling Intern Tori Philippi
B. Recycling Updates
C. General Updates
9. ADJOURN
DRAFT MINUTES
CITY OF LINO LAKES
ENVIRONMENTAL BOARD MEETING
I. CALL TO ORDER AND ROLL CALL:
Chair Sullivan called the Lino Lakes Environmental Board meeting to order at 6:30 p.m.
on May 4, 2022.
II. PLEDGE OF ALLEGIANCE
III. APPROVAL OF AGENDA
The agenda was adjusted to include discussion item 6C regarding the possible
implementation of No Mow May.
IV. APPROVAL OF MINUTES:
Mr. Parsons made a MOTION to approve the February 23, 2022 meeting minutes.
Motion was supported by Ms. Holmes. Motion carried 4 – 0.
V. OPEN MIKE
Mr. Sullivan declared Open Mike at 6:33 p.m.
There was no one present for Open Mike.
Open Mike was closed at 6:33 p.m.
VI. ACTION ITEMS
A. Otter Lake Animal Care Center Conditional Use Permit Amendment & Site
Plan Review
Andy Nelson, Environmental Coordinator, presented the staff report.
DATE: May 4, 2022
TIME STARTED: 6:30 P.M.
TIME ENDED: 7:41 P.M.
MEMBERS PRESENT: John Sullivan, Lindsay Buchmeier, Shawn Holmes,
Jonathan Parsons
MEMBERS ABSENT: Ella McNulty, Cassie Cavegn, Alex Schwartz
STAFF PRESENT: Andy Nelson
Environmental Board
May 4, 2022
Page 2
DRAFT MINUTES
Otter Lake Animal Care Center is located at 6848 Otter Lake Road. Dr. Wayne
Scanlan, the applicant, is proposing to construct a 2,850 sq. ft. addition to the existing
4,000 sq. ft. building. The applicant is also proposing to expand the existing parking
lot. The current site is approximately 1.51 acres.
The Board briefly discussed the location of the trash enclosure and the on-site storm
water pond. Overall, the Board supported staff’s recommendations.
Ms. Holmes made a MOTION to recommend the Otter Lake Animal Care Center
conditional use permit amendment and site plan review be forwarded to the Planning
and Zoning Board and City Council subject to conditions listed in the staff report.
Motion was supported by Mr. Parsons. Motion carried 4 – 0.
B. Otter Crossing 2nd Addition Preliminary Plat and Tidal Wave Auto Spa
Conditional Use Permit & Site Plan Review
Andy Nelson, Environmental Coordinator, presented the staff report.
Tyme Properties, LLC. submitted a land use application for a preliminary plat for
Otter Crossing 2nd Addition in order to create two (2) commercial lots. Bowman
submitted a separate land use application for a conditional use permit and site plan
review for a commercial car wash called Tidal Wave Auto Spa which will be located
on Lot 1 of the preliminary plat.
Mr. Parsons asked if Tidal Wave Auto Spa would be able to recycle the stormwater
runoff through the car wash system.
Mr. Nelson said he would investigate whether or not recycling the stormwater could
be a viable option.
Ms. Buchmeier asked, since the holding pond is located at the end of the street, will
the street forever remain a dead end.
Mr. Nelson explained it is unlikely the street will remain a dead end. He added the
City’s engineering team will ultimately be responsible for the development of the
street.
Ms. Buchmeier inquired if there are any rare and unique species on the property.
Mr. Nelson said Blanding’s turtles have been found nearby. He recommended the
Board add a recommendation to add protections pertinent to Blanding’s turtles.
Chair Sullivan referred to Caribou Coffee’s landscaping to ask Mr. Nelson how tree
planting, appropriate spacing of trees, and the removal of diseased trees will be
handled for the Tidal Wave Auto Spa site.
Environmental Board
May 4, 2022
Page 3
DRAFT MINUTES
Mr. Nelson explained Caribou Coffee’s landscaping has not yet received final
acceptance. He stated it is his responsibility to conduct the final review of the
landscaping for all projects to ensure the plantings are alive and the landscaping
matches the approved plan. Regarding the spacing of trees, he said open space is
typically reserved for underground utilities and for access to stormwater ponds.
Ms. Buchmeier made a MOTION to recommend the preliminary plat for Otter
Crossing 2nd Addition and the conditional use permit and site plan review for Tidal
Wave Auto Spa be forwarded to the Planning and Zoning Board and City Council
subject to conditions listed in the staff report including two additional
recommendations from the Board to add applicable protections for Blanding’s turtles
and to implement the reuse of stormwater though the car wash system. Motion was
supported by Ms. Holmes. Motion carried 4 – 0.
C. No Mow May
Andy Nelson, Environmental Coordinator, presented the staff report.
No Mow May is an intiative which promotes avoiding the mowing of lawns during
the month in order to provide additional flowers which benefit pollinator species.
Ms. Buchmeier asked if City Council approves the No Mow May initiative, would
parks and City property be included.
Mr. Nelson informed the Board they could make the recommendation to include
parks and City property within the initivative; however, he cautioned such
recommendation may not be approved by City Council since those spaces are often
rented and utilized by sporting groups.
Chair Sullivan made a MOTION to recommend support of the No Mow May
initiative by suspending tall grass ordinance enforcement for the month of May in
order to benefit pollinators. Motion was supported by Ms. Holmes. Motion carried 4
– 0.
VII. UPDATES
A. General Updates
Mr. Nelson informed the Board of Mary Fogarty’s retirement from the City after 27
years. He expressed his appreciation working with Ms. Fogarty and thanked her
specifically for her work with the community gardens and the City’s annual tree sale.
Mr. Nelson also gave the Board a verbal update regarding the EAB grant. He stated
all of the diseased trees and stumps have been removed and the new bare root trees
have been planted, mulched, and watered.
Environmental Board
May 4, 2022
Page 4
DRAFT MINUTES
B. Recycling Update
Mr. Nelson informed the Board interviews for the Recycling Intern position have
been conducted and upon acceptance of the offer, the intern will start within a few
weeks.
C. Other Business
Ms. Holmes asked about the status of the proposed development by Anderson
Companies on the corner of Lake Drive and Main Street and if any updates will be
provided to the various Boards.
Mr. Nelson said he would look into her inquiry and provide the Board with an update
at next month’s Environmental Board meeting.
VIII. ADJOURNMENT
Ms. Holmes made a MOTION to adjourn the meeting at 7:41 p.m. Motion was supported
by Ms. Buchmeier. Motion carried 4 – 0.
Respectfully submitted,
Janele Waterman, Community Development Administrative Assistant
1
ENVIRONMENTAL BOARD
AGENDA ITEM 6A
STAFF ORIGINATOR: Andy Nelson, Environmental Coordinator
MEETING DATE: June 29, 2022
REQUEST: Villas on Vicky PUD Concept Plan Review
APPLICANT: Ranger Development
Attn: Jon Blattman
4247 117th Ave. NE
Blaine, MN 55449
OWNER: Jeff and Mary Jo Joyer
8174 Lake Drive
Lino Lakes, MN 55014
BACKGROUND
The applicant submitted a land use application for a Planned Unit Development Concept
Plan review. The proposed residential development is located on an approximately 4.9
acre parcel west of the intersection of Lake Drive and Kelly Street. The concept plan
proposes 23 single unit townhomes, all slab on grade with the option of one or two levels.
The applicant is proposing varying lot sizes and setbacks that would require PUD
flexibility.
This staff report is based on review of the following submittals:
• Concept Plan prepared by E.G. Rud and Sons, Inc., dated 5-26-22
• Aerial Resource Map prepared by E.G. Rud and Sons, Inc., dated 5-26-22
• Narrative and House Elevations prepared by Ranger Development, dated 6-09-22
2
ANALYSIS
EXISTING CONDITIONS
The site is currently a vacant, approximately 4.9 acre parcel with scattered trees and
grasses on sandy soil.
Land Cover
Pre-settlement land cover (Marschner) was oak openings and barrens.
Minnesota Land Cover Classification System (MLCCS) data indicates: long grasses with
sparse tree cover on upland soils, oaks with 11-25% impervious cover on the south
perimeter, and short grasses and mixed trees with 26-50% impervious cover. The
impervious cover noted in the MLCCS data is associated with developed residential lots
nearby.
Soils
Soil types according to the Natural Resources Conservation Service Soil Survey
Geographic Database include:
Soderville fine sand with 0 to 3% slopes (approximately 80%) which are moderately well
drained with rapid permeability in the upper part and moderately rapid in the lower part.
Runoff is negligible. Water table may be at 2-3.5 feet from April to June.
Zimmerman fine sand with 1-6% slopes (approximately 20%) which are excessively
drained soils with rapid permeability and negligible to low runoff.
Shoreland District
Site does not fall within Shoreland District.
Alternative Urban Areawide Review (AUAR) Considerations
The site is not within the AUAR environmental review boundary.
Drinking Water Protection
The site is not within in the Drinking Water Supply Management Area (DWSMA).
3
PROPOSED CONDITIONS
The concept plan shows 23 single-family townhome lots ranging from 5,358-11,066
square feet in size. There are stormwater ponds shown on the 10,026 square foot Outlot
B and in two areas along the east perimeter on Lake Drive.
The proposed project would also include construction of private streets and a realignment
of Vicky Lane to match with Kelly Street just east of this site.
Rezoning
The property is currently zoned R1, single family residential. The property would need
to be rezoned to PUD, Planned Unit Development in order to allow for a variety of lot
sizes and setbacks.
The intent of Planned Unit Development is to provide for the grouping of lots or
buildings for development as an integrated, coordinated unit as opposed to traditional
parcel by parcel, piecemeal, or sporadic approach to development. It is intended to
introduce flexibility of site design and architecture for the conservation of land and open
space through clustering of lots, buildings and activities, which promote the goals
outlined in the Comprehensive Plan or serve another public purpose.
The applicant would need to provide additional public benefit, such as additional open
space and trails, in order to be considered for PUD zoning.
Flood Plain
The site does not fall within the flood management zone.
Rare, Unique, or Significant Resources
The following rare plants and animals have been documented within one mile of the site:
Blanding’s turtle (Emydoidea blandingii), Toothcup (Rotala ramosior), Lance-leaved
violet (Viola lanceolata), and Autumn Fimbry (Fimbristylis autumnalis).
These species are all associated with wetland habitat and there are no wetlands on site.
Protections for wildlife will be included through adherence to city specifications already
in place. These protections include surmountable curbs for residential streets and natural
netting erosion blanket where needed for soil stabilization.
Staff does not find additional environmental assessments for rare, unique, or significant
resources necessary for this site.
4
Stormwater Management
Under existing conditions, most stormwater on this site infiltrates into the soil. The rest
collects in the city stormwater system that heads to ponds in Lino Park.
There are stormwater ponds noted in the concept plan. Native vegetation buffers shall be
included around all ponds.
Greenway System and Trails
A trail and on-street bike lane are proposed in the 2040 Comprehensive Plan, which
should be considered as part of this project.
Wetlands
There are no wetlands indicated on the proposed project site.
LANDSCAPE PLAN
A Tree Survey, Tree Preservation and Mitigation Plan, and Landscape Plan in
compliance with Section 1007.043 (17), Required Screening, Landscaping and Buffer
Yards shall be submitted. Note that additional landscaping may be required as a
condition of the PUD.
Staff notes that a 6 foot buffer and screen will be required around the entire site due to the
adjacent, less intense land uses, and the presence of the arterial road (Lake Drive). There
does not appear to be enough room for these buffers or the required open space plantings
in the current proposed plan.
RECOMMENDATIONS
Staff recommends the Villas on Vicky PUD Concept Plan be forwarded to the Planning
and Zoning Board and City Council with the following comments:
1. There does not seem to be room for required buffer and screen plantings or open
space plantings.
2. The project narrative mentions two trees will be planted in each front yard. There
should be only one boulevard tree per frontage planted in the right-of-way per
property. This is one tree per lot or two trees for corner lots. If there is a second
tree planted in the front yards, they should not be located in the right-of-way.
3. A proposed trail appears on this site in the 2040 Comprehensive Plan and should
be considered as part of this project.
5
4. A diverse mix of native plants and plants beneficial to pollinators shall be utilized
wherever possible and/or practical. This includes vegetative buffers around
stormwater management features and also in required open space and landscape
plantings.
ATTACHMENTS
1. Villas On Vicky Aerial Photo
2. Concept Plan
3. Aerial Resource Map
Villas On Vicky Aerial
Legend
Parcels
June 24, 2022
Map Powered By DataLink
1 in = 752 ft
±
ENVIRONMENTAL BOARD
AGENDA ITEM 7A
STAFF ORIGINATOR: Andy Nelson
MEETING DATE: June 29, 2022
REQUEST: Discussion only
TOPIC: MS4 Annual SWPPP Report and Public Comment
Opportunity
Background
The Municipal Separate Storm Sewer System (MS4) general permit is mandated by
federal regulations under the Clean Water Act and administered by the Minnesota
Pollution Control Agency. The permit allows for owners of storm sewer systems to
discharge stormwater into lakes, rivers, and wetlands provided certain regulatory
requirements are met.
The City of Lino Lakes has been operating the storm sewer system s under the MS4
permit since 2006. The City’s system includes approximately 288 storm ponds, 49.86
miles of storm sewer, and 128 outfalls into public waters.
The permit requirements include the preparation of an annual Storm Water Pollution
Prevention Program (SWPPP) report. The City’s SWPPP report for 2021 activity is
comprised of 6 components, referred to as Minimum Control Measures (MCMs) that
provide for implementation of the permit requirements:
1. Public education and outreach, which includes teaching citizens about better
stormwater management
2. Public participation: Include citizens in solving stormwater pollution problems.
This includes a required public annual meeting and an annual report.
3. A plan to detect and eliminate illicit discharges to the stormwater system (like
chemical dumping and wastewater connections)
4. Construction-site runoff controls
5. Post-construction runoff controls
6. Pollution prevention and municipal “good housekeeping” measures, like covering
salt piles and street-sweeping
Staff will provide an overview of the activities completed in 2021 at the meeting.
Requested Environmental Board Direction
None required, information only.