HomeMy WebLinkAbout02/09/2000 Council PacketWORK SESSION AGENDA
LINO LAKES CITY COUNCIL
WEDNESDAY
February 9, 2000
5:30 p.m.
1. Stadium Update — Jeff Smyser
2. Outdoor Storage - Jeff Smyser
3. Traver Variance Shoreland Setback — Jeff Smyser
4. JADT Final Plat Update — Jeff Smyser
5. Town Center Development Update — Jeff Smyser /Mary Alice Divine
6. Comprehensive Plan Update — Jeff Smyser
7. Reiling Settlement Update — Mary Alice Divine
8. 2000 Park Board Goals — George Lindy Park Board Chair
9. Wenzel Farms /City of Hugo Water Service Joint Powers Agreement and Easement
Vacation Request — John Powell
10. West Shadow Lake Drive Utility Petition — John Powell
11. West Bald Eagle Boulevard Utility Petition - John Powell
12. Apollo Drive Phase 4 Status Report — John Powell
13. Oak Brook Peninsula Easement Vacation Status Report — John Powell
14. Regular Agenda Items
15. Adjourn
February 8, 2000 (2:30 p.m.)
•
PAGE 1
•
•
•
MEMORANDUM
February 9, 2000
to: City Council
from: Jeff Smyser
subject: Schedule of Actions for Stadium
cc: Linda Waite Smith, Brian Wessel
At the January 19 work session, the City Council asked staff to address what actions the
City would need to take regarding the stadium. The Council also asked staff to address
impacts the stadium might have on the City overall.
Environmental Impact Statement
The most important thing to know is that an environmental impact statement (EIS) will
be necessary. By state law, an EIS is mandatory because the proposed stadium crosses
the size threshold for a mandatory EIS. When an EIS is required, a project may not be
started and a final governmental decision may not be made to grant a permit, approve a
project, or begin a project, until the EIS is completed.
The process for preparing an EIS is laid out in MN Rules 4410. The attached table
briefly summarizes the EIS process.
An EIS is a major endeavor. I estimate that the EIS process would require 15 months.
This is not unusual. The cost of an EIS is borne by the project proposer and typically the
cost is significant. Just preparing the scoping document and going through the scoping
process takes several months.
The EIS would be the method to determine what impacts the stadium would have.
Without a full study, we can only speculate. However, we should not underestimate the
impacts of a development such as the proposed stadium. Remember how the old stadium
in Bloomington supported or catalyzed development around it.
I'i) IU 631 -')£i 2- 24)O • F.�v: (> -i l -,)ti 2 -2400 • F{)1): (»1- 98? -_'-J I U
•
City Council
Stadium Schedule
February 9, 2000
page 2
Other City Actions
All the following issues, and more, would be studied in an EIS. Even without the EIS,
we can start to grasp the scope of the changes that would ensue from a stadium. In
response to what we find out from the EIS, the City would have to take many actions. I
expect the needed actions would include, at a minimum:
• Comprehensive Plan amendment: for the site, surrounding lands, and other areas
impacted by roadway improvements and land value effects
• Rezoning, including: preparation of new zoning district and standards
rezoning surrounding lands
regional and local, including freeway accesses, Main St.,
20th Ave., others
regional (sewer) and local (sewer and water)
needed to manage growth and deliver quality services —
planning, law enforcement, building inspection,
environmental, administration, etc.
• Roadway improvements
• Utility improvements
• City staff
Potential Impacts
Economic Development: Clearly, a major league stadium and surrounding
development would generate significant tax revenues. This is the most important positive
element of the stadium.
Transportation: For a stadium of 70,000 seats, let's assume three people per
vehicle, which means 23,000 vehicles for a football game. And let's not forget baseball
games on a more regular basis, though with fewer vehicles per game. The immediate
area around the stadium would require major roadway improvements.
Freeway interchange improvements alone would have significant impacts on the area.
The existing single Main St. interchange on I -35E would not be sufficient, and an
additional interchange on I -35W would return to the front burner for discussion. Other
access points on freeways and other major roadways would be analyzed.
Traffic from other roadways would impact existing and future land use. Imagine how the
23,000 vehicles will find their way to the stadium on a Sunday morning using the several
potential routes through Lino Lakes. Of course, after the game they would go the other
way. How many would use Centerville Rd., 20th Ave., or Main St. through the regional
park?
Land Use: The stadium would accelerate growth in many ways. The area's
desirability for commercial and residential development would increase greatly. The
immediate area would become a focus for regional economic investment.
City Council
Stadium Schedule
February 9, 2000
page 3
Traffic along 80th St. and 20th Ave. in that area would create a market for retail services
along those roads. The stadium would require utilities, and the utilities would enable
commercial and residential development throughout that part of the City. The pressure
would call into question plans to keep much of the northeast portion of Lino Lakes in
rural land uses for the near and mid -term future.
Utilities: The stadium would require major improvements in regional sewer and
local sewer and water facilities. Utilities would need to serve surrounding development
as well as the stadium itself. Major facilities to be added to the area also would include
electricity, gas, telephone, cable, etc.
Town Center: The stadium would most likely help the Town Center because of
its proximity to the stadium. The Town Center would provide a good pre -game location
because of the restaurants and lodgings we envision there. The residential units would
also have another amenity, being close to the stadium while still separated by the regional
park.
Natural Environment: The impacts of development on the natural environment are
yet unknown. We would need to study the wetlands, drainage patterns, vegetative cover,
and other natural features that would be affected. Generally speaking, we should expect a
large facility and the surrounding development to have the potential for significant
impacts. Whatever exists on the site now would be replaced by high intensity urban land
uses. Stormwater facilities to handle runoff from large areas of impervious surface would
themselves have impacts.
This is only a partial list of issues.
For your information, I've attached a summary of the EIS process.
•
City Council
Stadium Schedule
February 9, 2000
page 4
Preparation of an Environmental Impact Statement (EIS) is governed by MN Rules 4410, under
the authority of MN Statutes 116D, the Minnesota Environmental Policy Act.
EIS STEPS
TIMELINE
Prepare draft scoping document. The
scoping document establishes the scope of
the EIS by identifying the issues to be
studied, the level of detail, etc.
We would need to begin preparing the RFP
for consultants to prepare the EIS.
no mandated timeline: estimate 90 days
Publish availability of draft scoping
document in EQB Monitor.
published every two weeks
"Scoping period"
Written and other comments taken. At
least one public scoping meeting.
30 days starting with publication date
Final scoping decision.
Within 15 days after scoping period ends.
Complete RFP for consultant to prepare
EIS. We would need the scoping decision
to determine the scope of work.
20 days
EIS preparation notice publication.
Within 45 days after the scoping decision.
Advertise RFP
30 days
Review proposals received and determine
finalists.
30 days
Interview consultants
15 days
Select consultant
15 days
Negotiate cost with project proposer
(project proposer pays all costs of EIS)
30 days
Consultant prepare draft EIS
4 months
Publish availability of draft EIS and
distribute copies of full draft or summary
Informational meeting
no less than 15 days after publication of
availability
Public comment period
minimum 10 days beyond meeting date
Prepare final EIS
??
Publish availability of final EIS and
distribute copies
Public comment
minimum of 10 days starting with
publication of availability of final EIS
Determine adequacy of final EIS
within 280 days after EIS preparation
notice unless extended
TOTAL: approx. 15 months