HomeMy WebLinkAbout26-121 - Resolution - RJM Const Prof Services ContractCITY OF LINO LAKES
RESOLUTION NO. 26-121
APPROVING PROFESSIONAL SERVICES CONTRACT WITH RJM CONSTRCUTION,
CONSTRUCTION MANAGER AS AGENT, PUBLIC WORKS BUILDING
WHEREAS, the City entered into a contract with RJM Construction in June of 2026, and
WHEREAS, following award of contracts for the project the total budget and Cost of Work
have been updated to reflect estimated expenditures; and
WHEREAS, the contract provides for a contract amendment based on the Cost of Work of
the project and the provision of site services throughout construction of the project, and
WHEREAS, it is appropriate to amend the contract to document the revised scope of
project and adjustment to compensation,
NOW, THEREFORE, BE IT RESOLVED by the City Council of Lino Lakes, Minnesota approves
the amendment to the Agreement between the City of Lino Lakes and RJM Construction attached
hereto as Exhibit A.
BE IT FURTHER RESOLVED that the Mayor and Clerk are hereby authorized to execute a
contract on behalf of the City.
Adopted by the City Council of the City of Lino Lakes this 22nd day of June, 2026.
Ro a erty, Mayor
ATTEST:
Roberta Colotti, CMC, City Clerk
Exhibit A
AMENDMENT TO AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
This Amendment to Agreement Between Owner and Construction Manager ("Amendment") amends the
terms of the AIA C132 Agreement between the City of Lino Lakes ("Owner") and RJM Construction LLC
("Construction Manager") dated May 8th, 2025 ("Agreement") effective June 15th, 2026.
A. Owner and Construction Manager are parties to the Agreement, as defined above.
B. Owner and Construction Manager desire to amend certain terms of the Agreement, as
provide for in this Amendment.
NOW, THEREFORE, in consideration of the mutual covenants set forth herein and other good and
valuable consideration, the receipt and sufficiency of which are acknowledged, the parties agree as
follows:
1. Revised Scope of Project.
Section 1.1.1 of the Agreement is amended to state as follows: The Owner's
program for the Project: Approximately 98,000sf new public works facility with
vehicle storage, vehicle maintenance, office space, community meeting space.
Section 1.1.3 of the Agreement is amended to state as follows: The Owners
budget for the Cost of Work, as defined in Section 6.1: The Owner's budget for
the Cost of Work is $26,736,687.
Section 1.1.4.3 of the Agreement is amended to state as follows: Substantial
Completion date or dates: August 19, 2027 (Certificate of Occupancy), pending
issuance of building permit and watershed permit to allow for construction to
commence on June 15, 2026.
2. Compensation Adjustment. The parties agree that the revised compensation set forth
in Exhibit A replaces and supersedes the compensation structure set forth in Section
11.1.2 and Exhibit A of the Agreement as it relates to the original Project budget of
$17,225,000.
All impacts to Construction Manager compensation arising from the increase in Project
size, scope (approximately 98,000 sf), Cost of the Work ($26,736,687), and updated
schedule shall be deemed included in the compensation stated in Exhibit A.
For the avoidance of doubt, and as reflected in Exhibit A, the Construction Manager's
total fee for the revised scope of the Work shall be $384,197, which amount includes
all adjustments to the fee under Section 11.1.2 associated with the increase in the Cost
of the Work.
Construction Phase Site Services shall continue to be billed in accordance with the
Agreement based on actual hours worked at the rates set forth in Section 11.5;
provided, however, that such Site Services shall remain subject to a not -to -exceed
amount of $1,238,900, as reflected in Exhibit A.
Builder's Risk Insurance. The parties agree that Construction Manager will provide the
"all risk" property insurance ("Builder's Risk Insurance") for the Project, which Owner is
required to provide according to its agreements with its prime contractors, AIA form
A132, Exhibit A and General Conditions, AIA form A232. Provided, however, Owner will
remain responsible for deductible amounts payable pursuant to the Builder's Risk
Insurance policy provided by Construction Manager and for losses not covered under
the Builder's Risk Insurance, subject to rights of subrogation, if any, against prime
contractors and others.
4. No Further Modification. Except as expressly modified by this Amendment, all terms
and conditions of the Agreement remain unchanged and in full force and effect.
5. Counterparts. This Amendment may be executed in counterparts and by electronic or
PDF signatures, each of which shall be deemed an original, and all of which together
shall constitute one agreement
City of Lino Lakes
Y
& r /
By:
. Mayor
By:
Its: City Clerk
RIM Construction LLC
By: Curtis Sell, CHC
2
Exhibit A
Revised Cost Information
COST PROPOSAL
CITY OF LINO LAKES
PUBLIC WORKS BUILDING
EXHIBIT A -AMENDMENT
RJM Construction
6/17/2026
7 _7, 7 T 1 P+�3+i bps:
Start Date: 1-Mar-25
Finish Date: 1-Mar-26
12
53
267
2136
Mo.
Wks
Days
Hours
Description
Quantity
Unit
Unit Cost
Total
Principal Executive
100
HRS
$ 200.00
$20,000
Project Manager
75
HRS
$ 145.00
$10,875
Estimator
400
HRS
$ 150.00
$60,000
MEP Director
50
HRS
$ 180.00
$9,000
Travel - Mileage
MO
Included
�btd1 Pa�sceflfpfint1i�e
**Discounted Pre -Construction, RJM will provide the resources and hours noted above for a lump sum amouint of $18,000
Construction Phase Site Services
Start Date: 15-Jun-26
Finish Date: 19-Aug-27
Cost of Work Budget $ 26,736,687.00
Lino Lakes Public Works - Negotiated 6/8/2026
14
62
310
2483
Mo.
Wks
Days
Hours
Description
Quantity
Unit
Unit Cost
Total
Project Executive - Curtis Sell
680
HRS
$ 200.00
$136,000
Project Manager- Aaron Chappuis
2483
HRS
$ 145.00
$359,967
Project Engineer - PresleyKimmes
1986
HRS
$ 115.00
$228,393
Superintendent - John Mackenzie
2,483
HRS
$ 140.00
$347,555
General Superintendent - Curt Sell Sr.
248
HRS
$ 155.00
$38,479
Director of Risk Management - Jim Lockhart
40
HRS
$ 200.00
$8,000
Safety Engineer -John Schramm
0
HRS
$ 115.00
$0
Director of Safety - Kale Fischer
248
HRS
$ 155.00
$38,479
Director of Quality Control (Project> $20M) • Mike Johnson
186
HRS
$ 156.00
$28,859
Administrative Assistant - Ai Yang
214
HRS
$ 85.00
$18,190
Trucking/Deliveries - RJM Shop Foreman
124
HRS
$ 98.00
$12,152
Truck
3,900
HRS
$ 4.50
$17,550
Fuel
1 62
Wks
$ 85.00
$5,275
SUBTOTAL Site Services
$1,238,900
% of Cost of Work 4.63%
Monthly Reimbursables
Start Date: 15•Jun-26
Finish Date: 19-Aug-27
14
62
310
2483
Mo.
Wks
Days
Hours
Description
Quantity
Unit
Unit Cost
Total
Site Construction Trailer
14
MO
$ 950.00
$13,617
Office Supplies/ Equipment
14
MO
$ 350.00
$5,017
Project Technology
62
Wks
$ 400.00
$24,825
Cell Phones
62
Wks
$ 50.00
$3,103
Blue Prints
62
Wks
$ 50.00
$3,103
Postage & Deliveries
62
Wks
$ 50.00
$3,103
Truck - Project Superintendent
MO
included above
Project Construction Mileage
14
MO
$ 75.00
$1,075
Safety Supplies and Signage
14
MO
$ 100.00
$1,433
Superintendent Lodging/ Meals (Per Week)
Wks
NIA
SUBTOTAL Reimbursables
$55,277
Fees
Summary Total for Construction
Preconstruction Services-
Management
Quantity I
Unit
Unit Cost
Total
12
LS
$18,000
$18,000
Construction Phase Site Services
14
Months
$86,434.91
$1,238,900
Reimbursables
14
Months
$3,856.50
$55,277
General Conditions
14
Months
$30,031.75
$420,445
General Liability & Builders Risk Insurance
14
Months
$24,828.86
$347,604
CM Fee
1
Ls
$384,187.001
$384,187
The General Conditions items listed below are now inclusive of the total fee. These costs are strictly a pass thru cost and all savings will
accrue back to the City of Lino Lakes.
General Conditions
Blueprinting Site Fencing Temporary Roads
Progress photos
Builders Risk Insurance
Construction Cleaning
Dumosters
Temporary Toilets
Winter Conditions
Temporary Enclosures
Test and Balance
Temporary Services
Tools/ Equipment
Snow Plowing
Final Cleaning