HomeMy WebLinkAbout26-117 - Resolution - Otter Lk Rd Ext - Award ContractCITY OF LINO LAKES
RESOLUTION NO. 26-117
ACCEPT BID AND AWARDING A CONSTRUCTION CONTRACT
OTTER LAKE ROAD EXTENSION PROJECT
WHEREAS, pursuant to an advertisement for bids for the construction of the Otter Lake
Road Extension project, bids were received, opened and tabulated according to law, and the
following bids were received complying with the advertisement; and
Contractor
Base Bid
North Pine Aggregate, Inc.
$10,598,386.85
Forest Lake Contracting, Inc.
$10,886,743.57
LaTour Construction, Inc.
$11,030,188.66
S R Weidema, Inc.
$11,909,252.00
Park Construction Company
$11,909,780.46
Meyer Contracting Inc.
$11,989,456.95
S.M. Hentges & Sons, Inc.
$12,961,985.64
A-1 Excavating, LLC
$12,969,969.00
Dresel Contracting, Inc.
$16,317,548.90
WHEREAS, it appears that North Pine Aggregate, Inc is the lowest responsible bidder; and
WHEREAS, the base bid amount is within the budgeted amount and the City Council
finds that it would be in the best interest of the city to proceed with the project,
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Lino Lakes:
The Mayor and Clerk are hereby authorized and directed to enter into a contract with
North Pine Aggegate, Inc. of Forest Lake, Minnesota in the amount of$10,598,386.85 by
the name of the City of Lino Lakes for the construction of the Otter Lake Road Extension
Project according to the plans and specifications approved by the City Council and on file in
the office of the City Clerk.
The City Clerk is hereby authorized and directed to return forthwith to all bidder the Bid
Bonds made with their bids, except that the deposits of the successful bidder and the next
two lowest bidders shall be retained until a contract has been signed.
Adopted by the Council of the City of Lino Lakes this 22nd day of June, 2026.
Z-�' i-L 1 11,4'
R a ferty, Mayor
ATTEST: b R
Roberta Colotti, City Clerk