HomeMy WebLinkAbout01/18/2006 Council PacketWORK SESSION AGENDA
CITY OF LINO LAKES
Wednesday
January 18, 2006
CITY COUNCIL WORK SESSION
Community Room (not televised)
5:30 P.M.
1. Super Rink Request — Centennial Youth Hockey Assn
2. Lino Lakes YMCA Project
(Item 6D in Council Meeting packet)
3. Hardwood Creek - Comprehensive Plan Amendment
(Item 6E in Council Meeting packet)
4. Draft Planning Study, Hodgson/CR J Area
5. Petition to Amend City Charter
6. Winter Parking Ordinance — Update from Police Department
7. Regular Agenda Items
8. Survey Question on Sports Stadium
9. 2006 Council Work Session Schedule
10. ..Charter Commission Files Location
11. Adjourn
PAGE 1
•
To:
From:
Date:
WORK SESSION MEMORANDUM
City Council
Rick DeGardner
January 18, 2006
WS -1
Re: Super Rink Request — Centennial Youth Hockey Association (CYHA)
Representatives from the CYHA have requested to be placed on the work session agenda
to present their proposal for a partnership with the cities of Lino Lakes, Circle Pines, and
Centerville for the construction of an indoor hockey rink at the National Sports Center.
City staff has attended some of the Super Rink Expansion Advisory Board meetings and
has met with Ms. Lisa Hockert, President of CYHA, and Mr. Paul Erickson, Executive
Director of the Minnesota Amateur Sports Commission (MASC). Ms. Hockert and Mr.
Erickson have prepared a presentation for the council's consideration. While staff
certainly feels that this is a worthwhile and needed project, we have been very
straightforward with the current financial situation the city of Lino Lakes currently faces.
For example, we have indicated that the 2006 General Fund Budget has already been
adopted and there are zero dollars in the city's contingency fund.
1/12/2006
J: \Ricks Folder \Correspondence \Cen Hockey funding 1- 06.doc
•
•
•
WS -4
MEMORANDUM
January 13, 2006
To: City Council
From: Jeff Smyser
Subject: Planning Study for 49/J Area
We have been working the past year on a study of the land and infrastructure around the
intersection of Hodgson Road (CSAH 49) and County Road J (Ash Street). The goal is a
planning document that will be adopted by the City Council as the guide for development
of the area.
We are providing December 8, 2005 draft report to bring the City Council up to date.
This draft is unfinished and in no way should it be considered a final report. The
Planning & Zoning Board saw this draft document in December, and the P & Z supported
the proactive approach to planning. They also supported a senior housing campus
concept.
There are two prospective developments in the area. The larger infrastructure planning
issues are the priority, but we should remember that these developments would construct
or contribute toward the provision of needed infrastructure.
The Study
The main points of the study so far include:
• The 49/J area needs improvement.
• Infrastructure improvements are needed to support future, new development or
expansion of existing businesses.
• Street access and circulation is inadequate or nonexistent.
• Municipal water and sanitary sewer are not available within the area.
• The lack of loops for existing water trunk lines bordering the area must be addressed..
• It usually is most cost effective for new roads and utilities to be in the same locations,
but there are options.
•
•
• Municipal water and sanitary sewer are Lino Lakes issues.
• The roadway system is multi jurisdictional.
• It is up to the City to provide internal roads.
• Hodgson and CR J are county roads. Because CR J is the border of Anoka and
Ramsey Counties, it is managed jointly by the two counties. Cooperation with the
counties and the City of Shoreview is necessary to find solutions to the
transportation infrastructure issues.
• Planning for land uses in the area should look to the future while also recognizing
current uses.
We held a neighborhood meeting in March and discussed an initial concept plan. We
received good information and comments from the land owners and residents in the area.
We have met with several land owners since then. This input was very important and
helped guide revisions to the concept plan. The attached draft (unfinished) report
provides background information and traces the planning process. Additional
information will be added and revisions made as needed. This is a work in progress.
Development Interest
Several landowners in the area want to develop their properties. Two developments in
particular are ripe. Staff have had several discussions with both of these developers
throughout the planning process for the 49/J study project. Because the infrastructure
issues are not yet resolved, these developers have not submitted development
applications.
The Jensen family owns the 17 acres north of the northwest corner of Hodgson and CR J.
They are working with a developer to create a senior complex that would include several
types of senior housing.
The property owners of the northwest corner of Ware Rd. and CR J are interested in
creating a new townhome neighborhood.
Growth Management Issues
Lino Lakes has a growth management policy that limits the number of new housing units
to be platted each year. One question we have not faced is how to count assisted living
senior units, which generate little traffic, wastewater, and other infrastructure impacts. If
we need infrastructure and development would provide it, we would need the
development to occur.
Recommendation
Staff is not making recommendations for a final plan at this time. That will come after
more discussions with developers, land owners, other government jurisdictions, P & Z,
and the City Council. Ultimately, the plan will need to provide guidance on alignments
of water, sanitary sewer, and the roads needed for proper access and circulation.
CSAH 49 & CR J
Hodgson Road & Ash Street
Master Plan
City of Lino Lakes
•
DRAFT DECEMBER 8, 2005
S
•
Table of Contents
BACKGROUND
Master Plan Study Objectives
Study Area
Roads
Existing Land Uses
Comprehensive Plan Proposed Land Uses and Zoning
Park Plan
DEVELOPMENT ISSUES
Roads, Access
Water Main
Sanitary Sewer
Wetlands, Water Table
CONCEPT PLANS
MASTER PLAN
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 1
•
•
BACKGROUND
In August of 2004, the City of Lino Lakes began a master planning process for the area
surrounding the intersection of Hodgson Road and County Road J. The intersection of
Hodgson Rd. and CR J is an important gateway into Lino Lakes, but the current
appearance of this location needs improvement. While this has been known for some
time, landowner interest in redeveloping the restaurant site on the northwest corner
catalyzed the master planning project and focused attention on the area. The area is
dominated by parking lots and automobiles. The restaurant/bar is boarded up, and other
lands are vacant. In order to address these deficiencies, redevelopment of some parcels is
as important as developing unused or underused properties.
Northwest corner of Hodgson /CR J intersection, viewed from the north
Northwest corner of Hodgson /CR J intersection
Northeast corner of Hodgson /CR J intersection
photos by Landform
DRAFT December 8, 2005 Hodgson/CR J Master Plan
page 2
•
However, a number of shortcomings must be corrected in order to support development.
The Hodgson/CR J intersection functions poorly at peak periods. Very little traffic at this
intersection is generated by business in the area, and traffic will continue to increase.
The area lacks sufficient internal roadways, and access to existing arterial and collector
roads is unplanned and random. Any business expansion will require extensive site
planning. This includes safe access to the major roads that currently are the only roads.
An overall road and access plan is needed.
There is no public water or sanitary sewer service available to most of the study area.
The intersection area is a hole in an area where utilities exist to the north, west, east, and
in Shoreview to the south. Solutions have been suggested, such as new trunks down
Hodgson Road or Laurene Ave. in the Rohavic Oaks neighborhood. However, the City
has not addressed how to serve this area with utilities. Existing homes and businesses
have onsite wells and individual wastewater treatment systems, which are not sufficient
to support contemporary development. Any expansion of the businesses will require
municipal utilities.
In addition to these infrastructure issues, development planning for the area should
include gateway elements. The visual appearance of this entrance to Lino Lakes should
be considered in the overall planning. At the outset of the project, the list of objectives
included design of the gateway elements for this entrance to the community. The
gateway idea has expanded to become a project of its own, to address other gateways and
possibly the design of a consistent gateway theme.
It is very important to note that there are several viable commercial businesses within the
study area. One of the challenges of the study is to plan both for current and future use of
land in the area. To be clear, this planning study is not an attempt to relocate existing
businesses. However, there are a number of issues to be resolved for the existing
businesses as well as for future development or redevelopment.
Master Plan Study Objectives
• Plan for redevelopment of 49 Club corner and potentially other sites
• Identify appropriate land uses (present & future) in study area
• Plan for road improvements to provide good access and circulation
• Identify routing & phasing solutions for utilities to facilitate future
development
• Propose gateway design elements
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 3
• Study Area
The study area includes approximately 37 acres of land in the southwest part of Lino
Lakes. Starting at CR J (Ash St.) on the south, the study area runs 1/4 mile north along
Hodgson Rd. (CSAH 49). The primary study area includes a triangular area on the west
side of Hodgson of about 17 acres. On the east side of Hodgson, the primary study area
includes 20 acres, but out of necessity the study looked at land extending to Ware Road.
Primary
Study
Area
n
map by Landform
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 4
•
•
Hodgson Road
Roads
Hodgson Road (CSAH 49) is an arterial road that runs from Lino Lakes south into central
St. Paul. County Road J, (CSAH 1, CSAH 32 or Ash Street), is an arterial running across
much of Anoka County, from State Trunk Highway 65 on the west to I -35E on the east.
Co. Rd. J forms the boundary between Lino Lakes and Shoreview. It also is the
boundary of Anoka County and Ramsey County, which share responsibilities for CR J.
Existing Land Uses
The study area includes a variety of residential and commercial uses. A garden center,
used auto lot, and auto repair business line the east side of Hodgson Rd. The auto sales
business owner has acquired a five -acre lot immediately east of the existing sales lot. On
the periphery of the study area, several single family homes exist on large, rural lots
without water or sanitary sewer services.
A closed bar /restaurant sits on the corner of Hodgson Rd. and CRJ. North of that is an
insurance office and a liquor store in separate buildings. A 17 -acre parcel north of those
lines the west side of Hodgson.
Several existing neighborhoods border the study area: Woodridge Estates and Blomquist
Addition to the west, Rohavic Oaks to the north, as well as the homes south of CR J in
Shoreview.
• The figures below show these uses.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 5
•
Discussions with property owners at a March open house and throughout 2005 were a
vital part of the study. Some want to develop their site, some want to continue the
existing use for now, but have plans for future development. Others have no plan to
change their use of their site.
Existing Land Uses, General Overview
2.5 acre residential
Residential
Large lot, rural
residential
Commercial
Lino Lakes County Road J Masterplanning Study
LANC)FO tM 0 Sao 200 400
January 20, 2005
LN04004
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 6
•
Existing Land Uses, Specific Properties
liquor store
insurance office
closed restaurant/bar
Comprehensive Plan Land Use Map and Zoning
The Lino Lakes Comprehensive Plan guides the study area for Mixed Use, Commercial,
and Medium Density Residential. The area is entirely within the Stage 1 (pre -2010)
development area. The primary study area is within the existing MUSA. The 20 acres on
the west side of Ware Road is not within the current MUSA.
The zoning of the study area includes General Business and Rural, with R -1X Single
Family Executive zoning to the west.
South of CR J, in the City of Shoreview, land is guided and zoned for single family
residential except for the commercial land at the corners of Hodgson and CR J.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 7
Proposed Land Use Plan, Lino Lakes Comprehensive Plan (Detail)
SEWERED
RESIDENTIA
Co. Rd. J (Ash St.)
t,
Commercial
Residential
1
City of Shoreview Comprehensive Plan Land Use Map (Detail)
(Lino Lakes and Shoreview maps are shown at approximate scale.)
ITY
ED
IAL
NSITY
ED
NTIAL
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 8
Lino Lakes Zoning Map (Detail)
Planned Unit
Development
(single family)
Co. Rd. J (Ash Street)
City of Shoreview Zoning Map (Detail)
(Lino Lakes and Shoreview maps are shown at approximate scale.)
DRAFT December 8, 2005 Hodgson /CR J Master Plan page 9
•
Park Plan
The Parks, Natural Open Space /Greenways and Trail System Plan shows a potential trail
crossing the northern part of the study area and continuing to the west. It is unlikely that
this could be implemented because of the existing Woodridge Estates neighborhood.
The parks plan also shows Natural Resource Protection Areas in the northeast area.
These are wetland areas that will be protected by existing wetland law or may be
important plant communities. The Natural Resource Conservation Areas in the northeast
and northwest portions of the study area are uplands with features that have high
ecological value. These areas should be examined for the potential for protection. A
Natural Resource Enhancement Corridor is shown to indicate that an area could be
considered for a trail to connect the two other areas.
Preliminary Park,Greenway& Trail System Plan (Detail)
DRAFT December 8, 2005 Hodgson/CR J Master Plan
page 10
Environmental Issues: Wetlands, Water Table
Wetlands exist in the area between Hodgson and Ware Roads, and the water table in the
overall study area is shallow. The shallow water table constrains some development
options that would require below -grade construction. Wetlands create some challenges
for routing roads and utilities.
However, the wetlands also can be viewed as the basis of an open space amenity area that
can be incorporated into site designs. Proper buffering of the wetlands can protect water
quality and enhance the quality of these open spaces. This perspective fits with the City's
conservation development philosophy, whereby new development would create
significant public values beyond those achievable under conventional development
n; `4;:.:
Wetland Inventory
Lino Lakes County Road J November 11, 2004
Masterplanning Study
LN04004
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 11
•
DEVELOPMENT ISSUES
Land Use
The existing land uses are illustrated in the previous figures. Any development of the
study area must recognize the existing neighborhoods of Woodridge Estates, Blomquist
Addition, Rohavic Oaks, and Ware Road residents in Lino Lakes as well as the existing
residential development south of CR J in Shoreview. These will continue as stable
residential neighborhoods. Design of new development must take into account potential
impacts on the neighbors.
Also noted previously, some property owners want to develop their site, some want to
continue the existing use for now, but have plans for future development. Others have no
plan to change their use of their site.
For example, a garden center and an auto sales business exist on Hodgson Road. Both
these businesses are are consistent with the comprehensive plan future land use map: the
sites are guided for commercial use. The garden center owner wants to continue the
business on the site and hopes to construct a new retail building. The location and size of
this building has yet to be determined. Immediately to the south, the auto sales lot owner
plans to continue doing business on the site.
However, either one of these two sites could be redeveloped. The garden center has
several buildings, but the entire site could be redeveloped either for expansion of the
garden sales business or for a completely different use. The auto sales property is mostly
undeveloped and could be used for a variety of things, including auto sales.
Land at the northwest corner of CR J and Ware Road is owned by a developer hoping to
create a small townhome development on the site. This is consistent with the
comprehensive plan future land use map, which guides the site for medium density
residential use.
On the west side of Hodgson Road, a developer is assembling land for a project that
would include redeveloping the northwest corner of Hodgson/CR J with new retail uses.
It also would create a senior housing campus on 17 acres to the north of the retail area.
No specific plans have been offered on the other properties in the study area.
The important point is that road, utility, and development plans for the area should
provide for future development as well as allow for the existing businesses to continue on
the site. Planning for both possibilities at the same time poses challenges.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 12
•
Roads, Access
Creating new local access and circulation is vital to development in the study area.
Creating new road alignments must address three issues: access and circulation,
development parcel size, and road right of way width.
Hodgson Road
Ware Road
primary study area
roads
Access and Circulation: The figure above shows the roadway system in the area.
Hodgson Road and CR J are the only two roads providing access to the primary study
area. Ware Road on the east provides access to the general area as well. However, no
local streets exist to provide access within the study area.
The intersection of Hodgson and CR J functions poorly now at peak periods. Traffic will
continue to increase, further degrading traffic conditions at the intersection. This traffic
is generated outside of the study area. Development within the area will require good,
safe access and circulation. Planning for the study area must acknowledge that the
intersection must be improved. This requires improvements to Hodgson Rd. and CR J,
but also requires designing clearly defined access points and internal circulation within
the study area.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 13
•
Access management is an important aspect of planning new road alignments. A number
of studies have demonstrated a relationship between the number of full access points on
major roadways and the number of crashes. Managing access to the arterial roads in the
study area supports several goals, including• maintaining an acceptable level of mobility
on the roads; reducing the potential for safety problems; promoting appropriate property
access; and facilitating cooperation between different agencies and jurisdictions.
The Anoka County Highway Department has adopted access spacing guidelines for
intersections on county roads. The table below lists spacing for minor arterial roads.
Access Spacing Guidelines: Anoka County Highway Dept.
Functional
Class
Route
Speed
(mph)
Area or
Facility
Type
Primary Full
Movement
Intersection
Conditional
Secondary
Intersection
Signal
Spacing
Private
Access
Minor
Arterial
50 -55
Rural
1/2 mile
% mile
% mile
subject to
conditions
40 -45
Urbanizing
1/4 mile
1/8 mile
1/4 mile
by
exception
or deviation
< 40
Urban Core
1/8 mile
300 -660 feet
1/4 mile
subject to
conditions
Source: Anoka County Highway Department Development Review Process Manual, December
2003
Both Hodgson Road and CR J are classified as minor arterials. The speed limit is 50 mph
on Hodgson north of CR J, but 45 mph to the south in Ramsey County. On CR J, the
speed limit is 35 mph at the Hodgson intersection. The speed limit increases to 50 mph
approximately 2,000 feet to the west and about 2,600 feet to the east of Hodgson Rd.
Defining the access points also includes recognizing that access to the arterial roads will
be limited. The intent is that access to land will be via the new local roads rather than
with individual driveways onto Hodgson and CR J.
One of the important benefits of creating new access points will eliminating existing
driveways that now access the arterial roads. If internal roadways are created, there
would be one access to Hodgson from each side. There also would be one access to CR J
between Hodgson and Ware, and one access between Hodgson and Woodridge.
Approximately 15 existing driveway access points on Hodgson and CR J would be
reduced to four access points: three at public road intersections and one parking lot
access (the CR J access west of Hodgson). This reduction from 15 individual, random
driveways to four properly designed access points would be a significant public safety
improvement .
Parcel Size: In addition to access needs, road alignments should allow for the
creation of parcels of property that are large enough to develop. The parcels must
accommodate buildings, parking, access drives, and site amenities such as landscaping or
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 1.4
Road Size: Road rights of way must be large enough to accommodate vehicle
movement, pedestrian sidewalks or trails, utility easements, and landscaping. While it is
possible to have utilities in separate easements, this uses additional land. It is most
efficient to include utilities in the road rights of way.
Utilities: Water and Sanitary Sewer
If the area is to develop, it must have municipal municipal water and sanitary sewer
service. Providing these utilities to the study area poses numerous challenges. The
figures below shows the location of existing municipal utilities.
Location of Existing Municipal Utilities
MIMI MIME
•
Location of Lino Lakes Water and Sanitary Sewer Trunk Lines
• • • • • • • • • • Sanitary Sewer Served By Shoreview System
other features. The street system must take into account existing uses as well as the
• potential for future development.
•
DRAFT December 8, 2005 Hodgson/CR J Master Plan
page 15
•
Several potential locations for utility service connections have been considered:
• Shoreview
• Ware Road
• Woodridge Lane
• White Pine Road, approximately 1/4 mile to the north of the study area, on the
west side of Hodgson Road
• Ravens Court, approximately 1/8 mile north of the study area, on the east side
of Hodgson Road
There are several common issues for water and sanitary sewer service in this area. For an
area that lacks both utilities, it is financially cost effective to plan both in the same
alignment. This avoids the need to acquire easements for separate alignments, and both
can be constructed at the same time. However, there are some issues that apply to one
but not to the other. In particular, the need to loop the water system. Issues for utility
service are described below.
Water Main
All the properties in the area with existing uses have individual wells for water. Homes
on Woodridge Lane have municipal water, but there is no service between the Woodridge
Estates neighborhood and Ware Rd.
The City of Lino Lakes has recognized the need to connect its two trunk lines in
Woodridge Lane and Ware Rd. The loop is needed in order to provide adequate water
service, particularly fire protection. Both trunks end near the Hodgson/CR J area, which
raises the possibility of inadequate flow. Looping the system allows for better flow and
water pressure. Looping also provides alternative service if water is interrupted from one
direction.
Shoreview: The Cities of Lino Lakes and Shoreview have a water interconnect at
Woodridge Lane. In the past, this interconnect provided ongoing, supplementary water
availability. Shoreview has closed this connection. It is available for emergency water
service, but not available on an ongoing basis. This has increased the importance of
looping the Lino Lakes system.
Woodridge Lane: Connecting to the Woodridge Lane pipe on the west of the study
area is more difficult. There is no corridor between existing homes for a utility easement
to connect to the Woodridge Lane utilities. The water loop could run along CR J, then
turn north through new development in the study area. The CR J right of way is 100 feet
wide in this location (50 feet on each side of the centerline). There are numerous private
utility services in this right of way such as natural gas, electricity, cable tv, and fiber
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 16
•
optics. Running a new water pipe would require moving these utilities or acquiring a
new easement. Moving the private utilities would be exceedingly expensive. The
remaining option is to purchase new easement outside of the existing road right of way
for a water trunk line.
White Pine Road: There is service available in White Pine Road, about '/4 mile north
of the study area. Connecting to this would require either an easement through the
Rohavic Oaks residential properties or running along Hodgson to Rohavic Lane, and
running the pipe in Rohavic Lane and Laurene Ave. There is no location for a utility
easement between the home lots. This route would not immediately address the need to
loop the water system between Woodridge and Ware, though it could provide a loop from
Woodridge. The Ware Road trunk could be connected to this new trunk when
development fills in the gap.
In addition, the comprehensive plan guides the Rohavic Oaks neighborhood as
Unsewered Low Density Residential and the City has received only one inquiry from this
neighborhood about utility service. Without property owner participation, there would be
insufficient funding for utilities and road reconstruction.
Ravens Court: Connection to the Ravens Court water is possible. However, this would
not immediately address the need to loop the water system between Woodridge and
Ware, though it could provide a loop from Woodridge. The Ware Road trunk could be
connected to this new trunk when development fills in the gap.
Ware Road: As property develops along Ware Road, the trunk can be brought from
that side. The Ware Rd. properties are undeveloped, so the opportunity exists to plan
utility service alignment as land develops. However, it will be necessary to provide the
water loop to Woodridge as development is planned.
Preferred Options (PRELIMINARY): It is necessary to loop the water system. The area
between Ware and Woodridge is largely undeveloped or underdeveloped. This area
offers the best route for a new utility alignment to provide water looping. Therefore, the
preferred option is to plan a water trunk either between Ware Road and Woodridge Lane
or between Woodridge and Ravens Hollow.
With the first option, a trunk would run from Ware Rd., through the study area within
new development, along property lines, and cross Hodgson. On the west side of
Hodgson, the water service would go through new development, south to CR J, then
connect to the existing Woodridge Lane trunk. This likely would require an additional
easement along CR J.
With the second option, the trunk would run from Woodridge, along CR J in a new
easement, and through the new development. Then it would run up Hodgson to the
Ravens Hollow development, crossing Hodgson at some point.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 17
•
The City needs to loop the water even if no new development occurs. New development
provides new easements because it needs utility service. If no new development occurs,
the City faces the need to acquire new easements solely at City cost.
Sanitary Sewer
The majority of properties in the study area have onsite septic systems for wastewater
treatment. Only a few properties in the area have municipal sewer service . These are all
west of Hodgson. They include homes on the north side of CR J, the closed
bar /restaurant site, the existing insurance building, and the existing liquor store.
Shoreview: The properties with sewer service are served by a special service pipe that
connects to the City of Shoreview sewer system. Shoreview has stated that it will not
plan to accommodate additional Lino Lakes development through this service line.
Therefore, service for the study area must be provided from one of the Lino Lakes pipes.
Woodridge Lane: As noted in the description of water service, there is no corridor
between existing homes for a utility easement to connect to the Woodridge Lane utilities.
Connecting to this sewer line would require an easement along CR J that would be larger
than a water line easement.
White Pine Road: Also as described above, there is service available in White Pine
• Road, about 1/4 mile north of the study area. Connecting to this would require running the
pipe in Laurene Avenue and Rohavic Lane. It also would require either an easement
through the Rohavic Oaks residential properties or running along Hodgson to Rohavic
Lane. In addition, the comprehensive plan guides this neighborhood as Unsewered
Residential (no utilities to be provided) and the City has not received only one inquiry
from this neighborhood about providing utilities. Without property owner participation,
there would be insufficient funding for utilities and road reconstruction.
Ravens Court: Connection to the Ravens Court sanitary sewer is possible,
depending on depth issues and the potential need for a lift station.
Ware Road: As property develops along Ware Road, the trunk can be brought from
that side. The Ware Rd. properties are undeveloped, so the opportunity exists to plan
utility service alignment as land develops. The Ware Road trunk is relatively shallow.
Depending on grade elevations for new development, a lift station may be needed.
Preferred Option: ....................... to be determined along with water service, likely will
use the same alignment and easements
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 18
•
Concept Plans
The study produced several concept plans. These concept plans were intended to provide
a basis for discussion as the study progressed. An initial plan was presented to a
neighborhood meeting on March 22, 2005. This plan intended to accomplish the
following:
• preservation of natural resource areas
• allow for phased development and utilities (connect to utilities in Ware Road)
• good access and circulation
• provide access for new development
• provide for stormwater treatment and management
• conservation development: create significant public values beyond those achievable
under conventional development, including:
• preserving natural habitat
• creating more open space for natural habitat, neighborhood recreation and
trails
• design quality, well - landscaped neighborhoods
The March concept plan also attempted to address gateway design issues. This included
keeping the corner buildings close to the street corners and other elements to create a
human scale environment, friendly to pedestrians and bicyclists. A major trail along
Hodgson is an important part of the City's Parks and Trails Plan. Residential
development in the area should have easy walking and biking access to this transportation
trail and to new businesses as well.
By its very nature, a concept plan is inexact, a collection of ideas. The concept plan is
not intended to eliminate existing businesses. Rather, it is intended to generate
discussion by showing a general land use design with some specifics, such as road
alignments and access points. The design of individual parcels will be up to the land
owners. However, because infrastructure design is the driving force of the study,
individual parcel design must take into account the infrastructure needs for the larger
study area.
The March concept plan generated a very informative discussions and helpful input from
landowners and residents. Several business owners didn't see their businesses pictured
on the concept plan and worried that the City was trying to drive them out. They stated
they intended to remain on their site, even expand their existing businesses. This
misunderstanding enforced the need for further communication and led to several
conversations and letters clarifying the goals of the study.
The March concept plan is shown below.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 19
•
March 2005
CONCEPT PLAN
COUNTY Roo J R!DE'vELO utEriT 1 ASTER PLAN
C411 Qt U140 Loom
li&ottA 22, 2905
DRAFT December 8, 2005 Hodgson/CR J Master Plan
page 20
•
The discussions also led to a second set of concept plans. In fact, the second round
resulted in two concepts in June 2005. Knowing that some of the existing businesses
planned to remain led to realigning the new roads to follow existing property lines. This
provides for new road and utility corridors without breaking up existing properties. It
avoids breaking up both the garden center and auto sales lot, each of which includes
several contiguous tax parcels. Expansion is possible, and the new road and utility
corridors provide access to utilities and to Hodgson and CR J. Concepts A and B differ
in the specific alignments of the internal roads. The alignments result in different
approaches to designing the land at the northwest corner of CR J and Ware Road. The
actual layout of that site has yet to be determined by the developer there. However, both
Concepts A and B provide a corridor to Ware Road for utilities, through the development
site.
It would preferable to align the new road access to CR J with the existing Kent Street in
Shoreview, as in Concept B. However, aligning it with the property boundary is
acceptable, even though it creates an offset. The likelihood of a median in CR J makes a
full access there somewhat questionable. Though both concepts show a full access, this
has yet to be determined.
The June concept plans led to further, more detailed planning and discussions with land
owners. On the west side of Hodgson, one developer is assembling a plan to redevelop
the sites with existing buildings and develop the 17 acres to the north. This would
include new retail as well as a senior housing campus. The land owner at the northwest
corner of Ware Road and CR J is pursuing a townhome development. If utilities for the
study area connect to Ware Road, this townhome development would include a corridor
for the water and sanitary sewer.
The June concept plans also formed the basis of discussions with the Anoka County
Highway Dept., Ramsey County Public Works., the City of Shoreview City Engineer,
and Lino Lakes staff. All agreed that the Hodgson/CR J intersection needs improvement,
and a collaborative solution is needed. Anoka County Hwy. is putting together a plan for
the intersection. Lino Lakes is preparing a traffic study. Ramsey County contributed
data for the study. All jurisdictions will need to examine funding possibilities and
cooperative planning.
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 21
June 2005: CONCEPT A
LANDFORM
uu�
Lino Lakes County Road J Masterplanning Study
o 100 208
rrK'�_ - eet
dune 13, 2005
LN04004
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 22
•
•
•
June 2005: CONCEPT B
4\
•
0 I
LJ
-4444-4
014..
ocrho-4--)
LANDF004
)r
Legend
• teekrx
moswyjet.
wav_omks
o 100 200 4
temir=armsam■ eet
Lino Lakes County Road J Masterplanning Study
June 13, 2005
LN04004
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 23
•
FINAL MASTER PLAN TO BE DETERMINED
DRAFT December 8, 2005 Hodgson/CR J Master Plan page 24
ii
RI) W ic 9s5 ton.
r 5 A.H. NO 49
(H OD G SON HOA))
T
31'
WOODRIOGL 1 A NE
A33 \ 33333'
d 1-53,
N
WATER
SERVICE
PROPOSED TENANT
45,000 SF.
•
PROPOSED RerAN. TENANTS
20000 5R,
SENIO R APARTMENTS
49 UNITS
W/ UNDERGROUND
PARKING
took.14**,/
ASSISTED LIVING
44 UNITS
SLSZA
PROPOSED
BUILDING
5,000 514
PROPCSED
BUILL ING
5,000 5E4
PARKING
9,4
0
•
•
•
0
N.
S
•
•
e
S
e
S
S
S
•
5555
---
44_4_
A.H. NO. 4 9
LINO LAKES SITE PLAN
OVERALL DELVELOPMENT AND COMFORTS OF 1-,OME
r,441,1_,LN 41/4,,
14,
L3,
r 0
U)
C ,
TN
SCALE: 1" = 50'-0"
16 JANUARY 2006
.R.I.S.B.I.E
ARCHITECTS, INC
210 N. Second St., Suite 204 I River Falls, WI 54022
r Mir MU Drew,: =.70K
W01.1P040
OFECr
;All 10.8070.
1••••1
COMFORTS
OF HOME
PROPOSED
SENIOR
LIVING
LINO LAKES
MINNESOTA
PROJECT NO
AA
11 JANUARY 2005
•
•
•
WK - 5
WORK SESSION STAFF REPORT
Work Session Item No. 5
Date: January 18, 2006
To: City Council
From: Gordon Heitke
Re: Petition for Charter Amendment
Background
The City Council received a petition to not allow City Council Members (including the
Mayor) to also be members of the Lino Lakes Charter Commission at its September 26,
2005 meeting. A question was raised by Councilmember Carlson as to whether the
petition followed all the requirements for petitions set forth in the charter. A legal
opinion was sought to address that question. (See attached opinion.)
Due to other agenda issues and since there was no immediate need to consider the
petition request; consideration of the petition was deferred for a future time. The person
submitting the petition recently requested that the petition be discussed at the January 18,
2006 Council work session.
Requested Council Direction
Staff is seeking Council direction on the petition.
Attachment
City Attorney's opinion on the petition.
•
•
LAW OFFICES OF
William G. Hawkins and Associates
WILLIAM G. HAWKINS
BARRY A. SULLIVAN
October 7, 2005
Legal Assistants
TAMMI J. UVEGES
HOLLY G. PROVO
Ms. Jean Viger
Deputy Clerk
City of Lino Lakes
600 Town Center Parkway
Lino Lakes, MN 55014
Re: Petition
Dear Jean:
2140 FOURTH AVENUE NoRrtt
ANOKA, MINNESOTA 55303
PHONE (763) 427-8877
FAX (763) 421 -4213
E -MAn HawkLawl @aol.com
I am responding to your fax regarding the petition submitted by Robert Bening and Al
Demotts to the City Council at the September 26, 2005 City Council meeting.
I have reviewed the petition as well as the State statute pertaining to amendment of a
charter. The provisions in the City Charter are not applicable to the subject matter
that is listed in the petition since this is a request to amend the City Charter. The
applicable statute that would govern this procedure is Minn. Stat. § 4.10. Based upon
a review of the information submitted and the discussion at the City Council meeting,
it does not appear to me that the Petitioners are attempting to institute an amendment
to the Charter by petition as authorized in Minn. Stat. § 1y12. The form of the
petition does not meet the requirements of State law.
shout 10
It is my opinion that this is merely an advisory petition submitted to the City Council
requesting that the Council initiate a proposed ordinance to amend the Charter as
provided for in Minn. Stat. § 410, Subd. 5. The Council would have the discretion on
whether or not10-pmpose such an ordinance, submit it to the Charter Commission
followed by submission to the voters for approval or rejection.
In conclusion, the Council has the discretion to determine whether or not to proceed
on this request but is not mandated to do so by the petition. If you have any
questions, please contact me.
William G. Hawkins
WGH /tju
• Robert Bening Al Demotts 09/26/2005
6788 E Shadow Lake Road 7140 Rice Lake Road
The Petition.
Petition To Stop A Conflict Of Interest
We the undersigned, who are registered voters in the City of Lino Lakes (the City),
request the City Council and /or the City Charter Commission to place on the
November, 2006 state general election a referendum. This referendum would amend
the City Charter to not allow the City Council members (including the Mayor) to also
be members of the Lino Lakes Charter Commission.
Proposed change to the Charter.
On page three of the Lino Lakes City Charter.
In Chapter II Section 2.04 insert "be a member of the City Charter Commission, ".
Section 2.04 would be as follows:
Section 2.04. Incompatible Offices. No member of the Council shall be a member of
the City Charter Commission, hold any paid municipal office or employment through
the City other than that to which elected. Further, until one (1) year after the expiration of
his/her term, no Mayor or Council Member shall be appointed or employed by the City in
a compensated position which was created, or the compensation for which was increased,
during his/her term as Mayor or Council Member.
Change to the Minnesota State Statutes
Chapter 410 Section .05 before August 1, 2004
Subdivision 1. Appointment.
No person shall be disqualified from serving on a charter
commission by reason of holding any other elective or appointive
office other than Judicial.
After August 1, 2004
Except as otherwise provided in the charter, no person shall be
disqualified from serving on a charter commission by reason of
holding any other elective or appointive office other than
judicial. The charter may provide that members of the governing
body of the city cannot serve on the charter commission.
•
Petition To Stop A Conflict Of Interest
We the undersigned, who are registered voters in the City of Lino Lakes (the City), request
the City Council and /or the City Charter Commission to place on the November, 2006 state
general election a referendum. This referendum would amend the City Charter to not allow
the City Council members (including the Mayor) to also be members of the Lino Lakes
Charter Commission.
Signature:
Address:
cis
671 (9 ` ' Iti1 keno 014-Tr
A Please print last name A
Zip Code: j S19 cF;
Signature:
Address: Gj �►
Signature:
(t r r
Address: cC J
at( i
. Address:
Signature:
1-4
A Please print last name A
Zip Code:�� 3
^ Please print last name A
Zip Code: 5-5--&
3'
A Please print last name A
%% Zip Code: -S
Ati �u, -4
A Please print last name ^
Zip Code: 0-03 3 e
Address: 6 72/ fii'i/VIzw '- -
1
Signature: fti
Address:
ukt
A PI'ea print last name A
Zip Code: SIC-0 6 9
Signature: 1V(
Address: / 3 (0 L I I lvlO. it }vv%f Trt
Signature.
54u a '/ (r
-
A Please print last name A
Zip Code: 6-6-03
Address: ! � T' Lam` -a'k ( -
Signature:
Address:
A Please print last name A
Zip Cod p•
A Please print last name A
Zip Code: ,c623 i
Signature:
'015
A Please print last name A
Zip Code:
I
•
•
•
WS - 8
WORK SESSION STAFF REPORT
Work Session Item No. 8
Date: Council Work Session January 18, 2006
To: City Council
From: Gordon Heitke
Re: Sports Stadium Survey Question
Background
At the November 28, 2005 special work session, the council reviewed and approved the
questions for the community survey. On December 19, 2005, the Council approved
having Decision Resources, Inc. add to the survey to determine public opinion on Anoka
County holding a referendum prior to the implementation of a county -wide sales tax to
partially fund a sports stadium. Decision Resources Ltd. (DRL) drafted questions to
ascertain public opinion on that issue and the council reviewed the proposed sports
stadium survey questions at the January 4, 2006 work session meeting. There was an
objection to the questions as drafted by Decision Resources Ltd. A transcript of that
portion of the meeting was sent to DRL for their review. They have submitted the
attached alternative question for your consideration.
Requested Council Direction
Staff requests direction as to which of the submitted DRL questions is to be incorporated
into the survey, or if there are other comments or instructions for DRL.
Attachments
1. Survey questions as submitted by DRL (January 4, 2006)
2. Survey question as submitted by DRL (January 18, 2006)
1
• PROPOSED STADIUM QUESTIONS (January 4, 2006)
As you may know, Anoka County and the Minnesota Vikings are proposing to construct a sports
stadium in the City of Blaine, with a portion of the stadium funded by a county -wide sales tax.
1. Do you support or oppose the construction of the sports stadium? (WAIT FOR RESPONSE)
Do you feel strongly that way?
IF "OPPOSE" OR "STRONGLY OPPOSE," ASK:
2. Why do you feel that way?
IF "SUPPORT" OR "STRONGLY SUPPORT," ASK:
3. Would you still support this stadium proposal if Anoka County imposed the county -wide
sales tax increase without allowing county residents to vote on the sales tax increase?
•
• PROPOSED STADIUM QUESTION (January 18, 2006)
As you may know, Anoka County and the Minnesota Vikings are proposing to construct a sports
stadium in the City of Blaine, with a portion of the stadium funded by a three- quarter percent
county -wide sales tax.
1. Should Anoka County hold a county -wide referendum to allow
residents to vote on the proposed three- quarter percent
county -wide sales tax? (WAIT FOR RESPONSE) Do you feel
strongly that way?
e
•
•
•
•
.- _
br RESMIReES, s
3128 Dean Court
Minneapolis, Minnesota 55415
(612) 920 -0337
TO: Gordon Heitke
FROM: Decision Resources, Ltd.
DATE: January 18, 2006
SUBJECT: Stadium Question
We have now submitted two different types of questions surrounding the debate of the
referendum for the sales tax increase for the Viking Stadium.
The first set of questions sent to the Council was designed to explore the effect of the
referendum issue on residents' support or opposition to the construction of the stadium.
We believe it would be helpful to a decision - making body to understand whether the
position a resident holds on the referendum is based on their support or opposition for the
project overall.
The second question sent to the Council is a simple question of support or opposition for
a referendum. This question does not have the depth of the previous set and will not
provide an understanding of residents' opinions, only their desire to vote on a tax
increase.
At the end of the day, the Council will have to make a decision about what they hope to
learn from this question. We do not tell clients what questions they have to ask; we only
tell them how to ask what questions they have in a neutral and meaningful way.
• WS - 10
•
WORK SESSION STAFF REPORT
Work Session Item No. 10
Date: Council Work Session, 2006
To: City Council
From: Gordon Heitke
Re: Charter Commission Records Storage
Background
In order to maintain the current security policy related to the City Hall offices, staff
relocated the files of the Charter Commission into a new locking file cabinet which is
secured to the wall within the Community Room storage closet.
The Charter Commission has objected to this resolution to the security issue. They wish
to continue to have their records in the file cabinet that was purchased in 2000 out of their
budget. The design and size of the cabinet will limit the ability for tables and chairs to be
stored in the Community Room closet. Staff's response to the request to have their files
placed back into their original cabinet was to secure it to the wall in the corner of the
Community Room.
Since this decision was made, the Charter Commission has indicated that this is
unacceptable as they do not feel it is secure. (The cabinet is locked and the Community
Room is locked except for times that it is in use by staff or groups that have reserved the
room. Only staff has keys to this room.)
Requested Council Direction
Staff is seeking direction from the Council as to how it wishes to accommodate the
Charter Commission's records in City Hall. Another option that has not been suggested
for consideration is to put casters under the existing Charter Commission cabinet and
move it into the room for their meetings and other times when they wish to access their
records.
1