I. CALL TO ORDER AND ROLL CALL
II. APPROVAL OF AGENDA
III. APPROVAL OF MINUTES: Sept. 14 minutes postponed to Oct. 12 Meeting
IV. OPEN MIKE
V. ACTION ITEMS
A. CONTINUED PUBLIC HEARING for Comprehensive Plan Amendment for
Village of Hardwood Creek — Jeff Smyser
VI. DISCUSSION ITEMS
A. None
VII. ADJOURN
AGENDA ITEM V. A
STAFF ORIGINATOR: Jeff Smyser
P & Z MEETING DATE: September 27, 2005
TOPIC: •CONTINUED PUBLIC HEARING:
Comprehensive Plan Amendment
Village of Hardwood Creek
•General Concept Plan, Planned Unit Development
BACKGROUND
We have received an application from Village of Hardwood Creek, LLC, to amend the
comprehensive plan. A public hearing is required for a comprehensive plan amendment.
A comprehensive plan amendment requires a formal vote. The application also includes
a general concept plan for a planned unit development. The concept plan review is
informal and does not require a vote. It is important to note that approval of this
comprehensive plan amendment does not grant or imply any right to an approval of the
PUD application that will follow.
The growth management policy, laid out in Ordinance No. 24 -04, was prepared to
implement the intent of the comprehensive plan. The growth management policy
requires that several issues be addressed if the City is to accommodate this application.
This project application is the first one that requires an amendment to the comprehensive
plan as directed by the growth management ordinance. Review of the relevant parts of
the comprehensive plan resulted in recommendations to add or change several passages.
The amendment to the comprehensive plan would involve a number of elements.
This application does not include a planned unit development or preliminary plat. It does
not include the detailed information normally part of such applications. Because of this,
we cannot analyze the project to see if it would qualify for the exemptions to certain
growth management limits as a conservation development. In additions, there are some
limits from which we cannot grant exemptions. Therefore, a comprehensive plan
amendment is needed to address growth issues as well as changing the land use
designation for the site.
Basically, three parts of the plan amendment relate directly to the application: changing
the land use, adding MUSA, and addressing the growth management issues. Because the
comprehensive plan is a city -wide document, we need to ensure that amendments to the
document support future planning needs.
Comprehensive Plan Amendment
Village of Hardwood Creek
page 3
has a MUSA reserve. As part of the approval of the comprehensive plan in 2002, the
City received additional MUSA reserve acres from the Metropolitan Council. The
amount of MUSA reserve was based on the City's estimates of the need for residential
and commercial /industrial development. There are only 90 acres remaining in reserve for
Stage 1 (pre -2010) residential development and 68.5 acres for commercial /industrial
development.
The development project site requires 363 acres of additional MUSA. The rectangular
exception is about 7 acres, for a total of 370 acres. A request for 370 acres of new
MUSA would be part of the amendment submitted to Metropolitan Council for review.
Under state statute, every municipality in the Metropolitan Area must have a
comprehensive plan, and must submit amendments to the Metropolitan Council for
review. The Met Council compares the city's plan to the regional Development
Framework, which includes plans for the individual systems over which the Met Council
has jurisdiction. These include sanitary sewer treatment, regional open space,
transportation, and airports. Control over MUSA is how the Met Council ensures its
sewer treatment facility planning is not overburdened or underutilized. Underutilization
is wasted capital improvement, and thus poor use of public funds.
Growth Management, Number of Units: The growth policy establishes a
target for the number of dwelling units that can be platted each year: 147. This works
out to a total of 1029 units between 2003 and 2010 (147 x 7 years = 1029). There are 76
units available for year 2007, 147 for 2008, and 147 for 2009. The proposed
development area is intended to accommodate 1200 to 1250 dwelling units over six
years. This would exceed the 1029 total and the 147 per year.
COMPREHENSIVE PLAN AMENDMENTS
The following lists the reasons why a comprehensive plan amendment would be needed:
(1) The proposed land use plan map must be amended if the application is to be
approved. The current designations are Industrial, Medium- Density, and High -
Density Residential. This would be changed to guide the entire site for Mixed Use.
(2) The amendment must include a request for 370 acres of MUSA for the Stage 1
growth area.
(3) In addition, even though our comprehensive plan includes Mixed Use on the
proposed land use map, there is no description of this land use category in the text of
the document. This should be addressed by describing the intent of the Mixed Use
category.
•
Comprehensive Plan Amendment
Village of Hardwood Creek
page 4
(4) The growth management ordinance states that an amendment of the comprehensive
plan shall be required if, in order to accommodate a specific development project, the
annual target for new growth (units /year) would be exceeded (Section 2, 7.). It is
unlikely that the master plan for this development could proceed within the limits of
the target of 147 units per year. (The 1029 units for Stage 1 noted in Section 2,
paragraph 5 of the growth policy, is based on 147 x 7 years.)
(5) The comprehensive plan itself includes a list of Growth Management Policies, which
includes "Limit residential growth to an average of 147 units per year, carrying a
three year supply lot inventory" (page 27). As stated above, this would not
accommodate the anticipated development project. This statement should be
reviewed to accommodate the potential advantages of master planning large areas.
(6) The growth goals described in the comprehensive plan "assume an average of 147
new households annually through the year 2020" (page 63). This statement merits
discussion.
(1) & (2) Land Use Plan Amendment: Land Uses and MUSA
The comprehensive plan includes a "Proposed Land Use" map. The application includes
amending that map. Currently, the site includes land guided Industrial (290 acres),
Medium Density Residential (45 acres), and High Density Residential (25 acres). The
AUAR included a market analysis based on recent development rates in Lino Lakes.
There are 1072 acres guided for industrial uses along 35E. At historic rates, it would take
well over 100 years to develop all this industrial land. Converting some of this to
accommodate the commercial and residential development that would make up the
Village of Hardwood Creek project will not prevent industrial growth in the city.
• The proposed land use for the site should be changed to Mixed Use, as shown on the
attached map "Proposed Amendment To Land Use Plan (Detail) ".
• The amendment should include a request for 370 acres of MUSA for this project. The
resulting MUSA line is shown on the "Proposed Amendment" map.
(3) & (4) Text Amendment: "Mixed Use" Land Use Category and Addressing the
Growth Management Ordinance
The comprehensive plan Proposed Land Use Map includes twelve land use categories.
The text in the Land Use Plan chapter of the document include discussion of nine of the
categories. The three categories not discussed are Public /Semi - Public, Manufactured
Home Park, and Mixed Use. The 35W interchange area of the Legacy at Woods Edge
and the Marketplace developments are the largest areas guided Mixed Use. The other is
•
Comprehensive Plan Amendment
Village of Hardwood Creek
page 5
the area northwest of the Hodgson/CR J intersection. The Mixed Use category should be
described in the text of the comprehensive plan, this project site should be listed, and it
should be clear that the growth management policy requirement has been addressed.
• The following text be added to the comprehensive plan, at the end of the Land Use
Plan chapter, on page 97:
MIXED USE
The Proposed Land Use Map designates several areas for "Mixed Use ". The
Mixed Use designation is intended to accommodate development that includes a
variety of land uses. This could be a development that integrates uses in the
same building, such as residential units above commercial space. It also might
include different uses in separate locations as elements of a larger development,
as part of a master plan. While it is possible that an appropriate development
project in a Mixed Use area could include only one type of land use, other land
use designations are available for development with only one type of land use.
Development in areas guided Mixed Use typically will take advantage of the
flexibility available with the use of a planned unit development. The City does not
require a PUD for development in a Mixed Use area. However, it is the preferred
design tool because development that includes a variety of uses typically will
pose challenges best addressed with the flexibility available with a PUD.
Amending the comprehensive plan to guide new areas for Mixed Use should be
reserved for areas that have undergone significant environmental review.
Commercial development typically will require more impervious surface than
residential development, which raises stormwater management design
challenges. Traffic generation differs between different land uses. The Mixed
Use and use designation envisions varied land uses, and recognizes the
possibility of design challenges, including environmental impact issues. These
can best be addressed with extensive environmental review.
Amending the comprehensive plan to guide new areas for Mixed Use and
development with these areas should be reserved for development that promotes
clearly identified public purposes. Such purposes may include but are not limited
to:
a) provision of housing unit variety that contributes toward meeting housing
goals, such as medium density, high- density, and mixed -use developments in
locations designated for them in the comprehensive plan
b) provision of infrastructure that will provide benefits beyond the project site, in
accordance with City transportation, sewer, or water plans, that is not
financially feasible without the project
•
Comprehensive Plan Amendment
Village of Hardwood Creek
page 6
c) preservation of environmental features that would not occur without the
project
d) provision of economic benefits to the City that would not occur without the
project
Development in areas guided Mixed Use must comply with the following
performance standards:
1. The land use and site design must be sensitive to the surrounding land uses
in the area, including but not limited to building height, exterior composition,
landscaping, and site access.
2. The road network within new development shall promote the safe and
convenient traffic movement. The project design must incorporate access
management design elements for access to arterial and collector roadways.
3. Municipal water and sanitary sewer service must be available.
4. All development shall address environmental concerns with regard to site
planning, landscaping, impervious surfacing, open space, and storm water
management. Stormwater management must incorporate- methods to protect
and improve water quality such as infiltration, buffering of water bodies, and
other natural methods whenever feasible.
5. Commercial site designs shall emphasize pedestrian accessibility,
connections to residential neighborhoods, shared parking, and green space
to create a customer friendly environment and promote a high level of
interaction among local businesses and between businesses and residents.
6. Architectural and site standards shall be applied to establish aesthetically
pleasing, high quality buildings and streetscapes.
Village of Hardwood Creek
The Village of Hardwood Creek development area is located 1/4 mile north of
Main St., between I -35E and CSAH 21 (20th Ave.). This 360 -acre development
site is to be developed with commercial and residential uses. The concept plan
for the development includes 500,000 to 600,000 square feet of commercial
space on 55 to 70 acres of the site. A variety of single family and multi - family
residential development will include approximately 1200 to 1250 dwelling units.
The net residential density is to be approximately 4.5 units per acre, when
including all land not within the commercial area. While these are the
approximate use parameters, the specifics of the development are to be part of a
master plan using a planned unit development approach.
Comprehensive Plan Amendment
Village of Hardwood Creek
page 7
In the northeast corner of the site, a triangle is formed by I -35E, a pipeline, and
the property boundary. This area could be designed to accommodate an office
campus type use, which could be a suitable land use along the freeway. This
would reduce the amount of residential land noted above. Such flexibility is
appropriate for the area.
This site is included in the Alternative Urban Areawide Review (AUAR)
environmental analysis. Development must comply with the mitigation plan that
forms a part of the AUAR.
This area was guided Mixed Use with an amendment to the comprehensive plan
in 2005. This amendment was intended to fulfill the City's growth management
policy requirement that amendment of the comprehensive plan shall be required
if, in order to accommodate a specific development project, the annual target for
new growth (units /year) would be exceeded.
Text Amendment: Planning District 6
The comprehensive plan breaks the city into planning districts. The Village of Hardwood
Creek site is in Planning District 6. The PUD application will be compared to the
recommendations listed for Planning District 6. However, some reference to this site and
its Mixed Use designation is appropriate.
• The following text be added to the comprehensive plan in the Planning District 6
section, on page 153:
Village of Hardwood Creek
The Village of Hardwood Creek development area is located 1/4 mile north of Main
St., between I -35E and CSAH 21 (20th Ave.). This 360 -acre development site is
guided Mixed Use and to be developed with commercial and residential uses. This
site is described in the Mixed Use section of the Land Use Plan chapter. The
specifics of the development are to be part of a master plan using a planned unit
development approach.
(5) Text Amendment: The 147 Statement On Page 27 of Comprehensive Plan
The comprehensive plan includes a great number of goals, policies, objectives,
recommendations, and strategies. The Policy Plan chapter includes a list of growth
management goals and policies. Policy number nine is: "Limit residential growth to an
average of 147 units per year, carrying a three year supply lot inventory." The growth
management ordinance, Ord. 24 -04, provides for amending the comprehensive plan if
this target is to be exceeded:
Comprehensive Plan Amendment
Village of Hardwood Creek
page 8
An amendment of the comprehensive plan shall be required if, in order to
accommodate a specific development project, the annual target for new growth
(units /year)...would be exceeded (Section 2, par. 7.).
The amendment will include the description of the site in the Mixed Use section, as
explained above. However, in order to avoid confusion, it would be advisable to amend
the limiting statement itself to provide for the possibility of amendment described in the
growth management ordinance.
• The statement on page 27 of the comp plan should be amended to read as follows:
9. Limit residential growth to an average of 147 units per year, carrying a three year
supply lot inventory. Specific projects that are found to fulfill specified public
purposes can justify amending this comprehensive plan to exceed this limit. The
City Council shall consider such an amendment only if the specific development
project will promote a clearly identified public purpose. The public purpose may
include but is not limited to:
a) provision of housing unit variety that contributes toward meeting housing
goals, such as medium density, high- density, and mixed -use developments in
locations designated for them in the comprehensive plan
b) provision of infrastructure that will provide benefits beyond the project site, in
accordance with City transportation, sewer, or water plans, that is not
financially feasible without exceeding the target
c) preservation of environmental features that would not occur without
exceeding the target
d) provision of economic benefits to the City that would not occur without
exceeding the target
These four public purpose examples are taken directly from the growth management
ordinance. These are listed as potential reasons to justify an amendment of the comp plan
if a project would exceed the annual growth target. Incorporating them into the comp
plan itself provides consistency between the comprehensive plan and the growth
management policy ordinance.
(6) Text Review: Demographic Goals
The "Local Forecasts" section of the Land Use Plan chapter includes the growth goals for
the next decades: households, population, and employment. This statement is found on
page 63: "The goals assume an average of 147 new households annually through the
year 2020." This statement merits discussion.
Comprehensive Plan Amendment
Village of Hardwood Creek
page 9
To amend this statement raises the question of amending the growth projections, an
important part of planning the community's future. This will be extensively analyzed and
discussed as part of the overall review of the comprehensive plan that must be completed
by the end of year 2008.
• Therefore, we recommend no amendment to this statement in the comprehensive plan.
Conservation Development Issues
Stormwater management methods, open space areas, connecting habitat and trail
greenways are conservation development elements described in several policy
documents. The Parks, Natural Open Space /Greenways and Trail System Plan provides
guidance. The draft Alternative Urban Areawide Review (AUAR) discusses such
elements and will include a number of them in its mitigation plan. As an incentive, the
growth management policy allows conservation development to be exempt from a
number of the growth restrictions.
The applicants originally intended the application to be a conservation development
project. They are aware of the City's desire to encourage conservation design, and have
been following the AUAR project. They also found the growth management incentives
attractive. However, the exemptions from growth limits do not include the Stage 1
MUSA total, so a comp plan amendment would still be necessary.
In addition, we need a great deal of information to classify a project as a conservation
development in order to exempt it from the specified growth restrictions. Specific
information would include such things as stormwater management designs, open space
designs, long term stewardship plans for open space, etc. Such information typically
would be included in a planned unit development /plat application. The current
application for a comprehensive plan amendment does not include detailed information
that would support exempting a "conservation development" from specified growth .
management limits.
Even so, we support the developer's efforts to incorporate as many environmentally
friendly elements as possible as the development design proceeds. The open space,
innovative stormwater management methods and attention to the long term management
of these design features demonstrate good planning by the developer and are consistent
with the City's environmental planning goals.
•
Comprehensive Plan Amendment
Village of Hardwood Creek
page 10
PLANNED UNIT DEVELOPMENT GENERAL CONCEPT PLAN
The developer's intent is to master plan the 363 acres for commercial and residential
uses. The specifics are not finalized yet. As described in the zoning ordinance, the
purpose of a PUD general concept plan is to provide an opportunity for the applicant to
submit an application and plan to the City showing the basic intent and the general nature
of the entire development. The concept plan provides an opportunity for the proposal to
be publicly considered at an early stage.
The following elements of the proposed general concept plan represent the immediately
significant elements for review, as listed in the zoning ordinance.
1) Overall Maximum PUD Density Range.
The application includes ranges of units and acreages. In Lino Lakes, density is
calculated on the net area: simply by subtracting the wetlands from the gross site
acreage. Some rough estimating, which includes open space and right of way data for
the residential area only, leads to a residential density about 4.5 units per acre.
2) General Location of Major Streets and Pedestrian Ways.
The concept plan includes the main collectors and access points envisioned in the
draft AUAR (see attached Figure 21 -1 from AUAR).. A local north/south collector
provides a route through the site. Two collector roads provide access to 20th Ave. on
the west of the site. The north/south collector would continue south to access Main
St., and north to future developments. The concept plan also shows an internal local
circulation network providing access for the residential development areas.
The AUAR recognizes the importance of managing access to major transportation
infrastructure. Collector and arterial roads will not function well if new road
intersections and driveways are allowed without an overall plan. The AUAR follows
access management guidelines with %2 mile spacing between full intersections on 20th
Ave.
The development site does not abut Main St. The pictured collector road would
need to extend 1/4 mile south of the site to access Main St. The Centerville /Lino
Lakes border complicates the situation, as does the undetermined interchange design.
The location of the access to Main St. is still under consideration.
Main St. is challenging because of the I -35E interchange planning underway
among Lino Lakes, Anoka County, Centerville, and MnDOT. The current front
runner for the interchange design includes a typical diamond with one exception. In
the northwest quadrant of the interchange, the southbound exit ramp forms a new
intersection and continues onto a new local road south of Main St. (see attached
figure). This new local road would run between the existing 21st Ave. and I -35E.
The new signalized intersection on Main St. would be only about 600 feet from 21st
Ave. The latest plan is to convert the 21st Ave. intersection to limit turning
•
Comprehensive Plan Amendment
Village of Hardwood Creek
page 11
movements and allow westbound Main St. traffic to flow freely from the exit ramp to
20th Ave. The 20th Ave. intersection will be signalized.
All this means that the location of 21st Ave. north of Main St. is an important
consideration. The road design does not need finalization as part of the
comprehensive plan amendment approval. However, the road design must fulfill the
traffic needs.
A traffic study has resulted in a recommendation that running a new road from
Main St. north to the Hardwood Creek development on the west side of the existing
bank and would be an acceptable alternative. This road could provide full access to
the north with enough stacking distance and the level of service would be acceptable.
However, there are additional considerations such as access to properties within
Centerville, water and sanitary sewer trunk alignment to serve the project, and Anoka
County's view of access in the area, including spacing of signalized intersections.
The new road might end up being a right in/right out only, with primary access to the
site from 20th Ave. It could also end up aligning with the existing 21St Ave.
These questions will apply whether or not the comprehensive plan is amended and
no matter how the site is developed. The point is that there are alternatives for
creating accesses to the site. The details will have to be worked out at part of the
PUD review.
3) General Location and Extent of Public and Common Open Space.
The concept plan includes an extensive open space network. The open space is to
include stormwater management features, parkland, and trails combined into a large
greenway system.
Several branches of the county ditch system lay in tiles crossing the site.
However, many drain tiles that are not part of the ditch system were placed on the
site over the years to drain the land for agriculture. Much of the potential for
incorporating conservation development elements into the development lies with the
stormwater management design. Utilizing infiltration to the greatest extent possible
will be important, as will accommodating the flow currently carried by the numerous
drain tiles.
The Parks, Natural Open Space /Greenways and Trail System Plan includes trail
connections to be created on the site. The concept plan includes these and more to
facilitate walking and biking within the site and to connect to trails outside the site.
The greenway system would utilize the pipeline easement as part of the trail network.
4) General Location of Residential and Non - Residential Land Uses with Approximate
Type and Intensities of Development.
Single family and multi - family residential areas are shown on the concept plan.
Housing will cover approximately 150 to 170 acres. Commercial uses in the
southeast portion of the site will comprise 55 to 70 acres. The following table is
taken from the concept plan.
Comprehensive Plan Amendment
Village of Hardwood Creek
page 12
Total
363 acres
Commercial
500,000 to
600,000 sf
55 to 70 acres
Residential
Single family
400 to 420 units
Multi - family
800 to 830 units
1200 to 1250 units
150 to 170 acres
Open Space
80 to 95 acres
Public Right of Way
55 acres
5) A Staging and Time Schedule of Development.
The submittal includes a phasing plan. The site would develop from south to
north, with over half the commercial development and some residential in phase one.
Phase two would include the rest of the commercial area and a large amount of
residential. Phases three and four would continue the residential development. The
developer envisions full build out of the site over six years.
6) Other Special Criteria for Development.
The AUAR has not yet been completed. Much of the project design will depend
on the AUAR, particularly the mitigation plan.
In addition, several roadway issues must be resolved. These include the design of
the I -35E interchange and the final design for the intersection at 21St Ave. and Main
St.
Timing will be another important aspect of this development. Transportation
infrastructure is needed to support a development of this size. In addition,
improvements to the water and sanitary sewer infrastructure will be needed to support
full build out of the project. The extent and timing of site development will rely
heavily upon these issues. The City Engineer's memo is attached.
What can be seen in the concept plan is an extensive open space /greenway
network. This will provide for trail connections, stormwater treatment, buffering
from the freeway, and the potential for wildlife habitat.
Though we don't have design details, the developer is including many
conservation development elements in the site design. We'll see more with the PUD
application. We are encouraged and support the efforts so far.
ENVIRONMENTAL BOARD
The Environmental Board discussed the application on August 31. Because this is not an
actual plat application with specifics, the Board's recommendation is general: "The
•
•
Comprehensive Plan Amendment
Village of Hardwood Creek
page 13
Environmental Board supports the general environmental direction of the Village of
Hardwood Creek, realizing that there is a lot more to be done."
OPTIONS
1. Recommend approval of the comprehensive plan amendment.
2. Recommend denial of the comprehensive plan amendment.
3. Comment on PUD concept plan.
RECOMMENDATION
Options 1 and 3
The application fulfills the following criteria, which are listed both for exceeding the 147
annual units statement and the Mixed Use section:
a) provision of housing unit variety that contributes toward meeting housing goals, such
as medium density, high- density, and mixed -use developments in locations
designated for them in the comprehensive plan
There are two specific goals that relate to this application in the Policy Plan section of the
comprehensive plan:
1. Provide a healthy variety of housing types, styles and choices to meet the
changing life cycle needs of the Lino Lakes Population.
3. Promote multiple family housing alternatives as an attractive life cycle housing
option.
The application will amend the plan to designate the site for multi - family as well as
single family development.
b) provision of infrastructure that will provide benefits beyond the project site, in
accordance with City transportation, sewer, or water plans, that is not financially
feasible without the project
The AUAR lays out a transportation framework to guide future planning. This includes a local
roadway system within development areas to avoid relying entirely on CSAH 14 and CSAH 21
for traffic movement. The system framework provides access to areas within the application site
as well as to land north of the site. This roadway system is vital to good transportation planning
Comprehensive Plan Amendment
Village of Hardwood Creek
page 14
in the eastern part of Lino Lakes. The Village of Hardwood Creek development will construct
these streets and by doing so build a major part of the needed transportation system as part of one
project. Smaller developments would not be able to create the system. and the City will not be
able to construct these streets.
In addition, Anoka County has identified the need to improve CSAH 21 to handle projected
traffic volumes. This project will provide resources to make significant improvements to CSAH
21 because improvements will be needed in order for this project to proceed.
The utilities (water and sanitary sewer) that will be constructed with this project will include
trunk lines planned to serve other property. Like the road system, this will provide a large piece
of the utility systems needed in this part of the city.
It is important to note that approval of this comprehensive plan amendment does not
grant or imply any right to an approval of the PUD application that will follow. Design
specifics, including road alignments, will be part of a full PUD review.
•
•
•
•
Site Location
•
•
LAND USE PLAN (DETAIL)
LINO LAKES COMPREHENSIVE PLAN
w
• URAL
LOW
DENSITY
SEWERED
RESID:
ESID.
LOW DENSITY
1
UNSEWERED RES:ID;
LOW DENSITY
SEWERED
RESID. °
INDUSTRIAL
•
■ `.
■
■
■ -i
•
•
PROPOSED AMENDMENT TO LAND USE PLAN
(DETAIL)
LINO LAKES COMPREHENSIVE PLAN
URAL
LOW
DENSITY
SEWERED
LOW DENSIT-X r
UNSEWERED RESID:°
LOW DENSITY
SEWERED
%S. iT
RESID.
•
•
•
ZONING MAP DETAIL
1 4101
•
•
•
AUAR Figure 21 -1: Existing and Proposed
Transportation Network
roi II
C :aN 111
I41E
Erlitna and Proposed
innaportalltanarsisatamacienalme
St 1sla/a
.,.0•a, ,..a, .a..
o
itC
•
V
u.p..MmSC..Y
,SEE
SITE
Figure 21 -1.
Existing and Proposed Transportation Network
•
•
I- 5 E at Anoka CSAH 14
Interchange Concepts
Prepared by SRF April 29, 2CC'C5
Diamond plus