HomeMy WebLinkAbout2009-074 Council Resolution•
•
•
O'Donnell
Council Member introduced the following resolution and moved its adoption:
CITY OF LINO LAKES
RESOLUTION NO. 09 -74
RESOLUTION APPROVING CHANGE ORDER NO. 18
LAKE DRIVE /I35W IMPROVEMENT PROJECT
WHEREAS, pursuant to the resolution of the City Council adopted May 14, 2007, the
City awarded the construction contract for the Lake Drive /I -35W Improvement Project to
Lunda Construction Company, and
WHEREAS, final erosion control inspections found erosion failures adjacent to County
Ditch 10 -22 -32 along the south end of the project; and
WHEREAS, the project engineer has determined that repairs are necessary to correct
the erosion problem,
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
1. Change Order No.18, is hereby approved in the amount of $4,500.00
Julia ne Bartell,
ayC
I P. -ft •
•'n J. B''ges•n, Mayor
Adopted by the Lino Lakes City Council this 28th day of September, 2009.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member Gallup and upon vote being taken thereon, the following voted in favor
thereof:
O'Donnell, Gallup, Reinert, Bergeson
The following voted against same:
none (Absent - SToltz)
Whereupon said resolution was declared duly passed and adopted.
•
•
•
STAFF ORIGINATOR:
CITY COUNCIL
MEETING DATE:
TOPIC:
AGENDA ITEM 6E
Michael Grochala
September 28, 2009
Resolution No. 09 -74, Approving Change Order
No.18, Lake Drive /35W Improvement Project
VOTE REQUIRED: 3/5 Vote Required
BACKGROUND:
On May 14, 2007 the City Council awarded the Lake Drive /I -35W Improvement Project
to Lunda Construction Company in the amount of $7,531,701.71.
During the course of final inspections erosion failures were identified adjacent to County
Ditch 10 -22 -32 at the southern end of the project. Following review with the Rice Creek
Watershed District, Mn /DOT and project engineers a repair plan was designed to
remedy the situation.
Change Order No. 18 directs the contractor to furnish all equipment, materials and
labor necessary to repair the identified areas at an estimated cost of $4,500.
RECOMMENDATION:
Staff is recommending approval of Resolution No. 09 -74.
ATTACHMENTS
1. Resolution No. 09 -74
2. Change Order No. 18
Mn /DOT TP- 2460 - 0112 -92) -
SHEET 1 OF 2 SHEETS
State of Minnesota - Department of Transportation
CHANGE ORDER # 18
contractor: Lunda Construction Co.
Address: 15601 Clayton Avenue S.
Rosemount, MN 55068
State Project No.: 0280 -55
Contract No. Z07502
Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr.
In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions.
At approximately on the west side of C.S.A.H. 23 at station 22 +00 (Rice Creek Box Culvert) the adjacent
shoulder is showing erosion failure (20 ft X 4 ft) as well as the south Rip Rap ditch draining to the creek is
showing a depression due to erosion undermining the Rip Rap.
After review the Project Engineer has determined due to the sensitivity of the Marshan lake /wetlands this area
of repair shall be immediately repaired.
The C.S.A.H. 23 shoulder repair approximately (20 ft X 4 ft) shall be excavated approximately 14 inches and
than backfilled with a blended combination of crushed aggregate (1.5" minus) and compost material (two 6"
lifts compacted). Followed with shingled sod placed to a finish grade that is below the inplace bituminous
shoulder grade.
•he south Rip Rap ditch channel draining to Rice Creek as shown in the attached plan shall have pea rock cast
over the area to fill only the voids and not cover existing rip rap (approximately 2 cyds). After placement of pea
rock both the north and south rip rap channels draining to Rice Creek shall have an annual rye grass (10 lbs)
cast through the area.
This Change Order directs the Contractor to furnish all equipment, materials and labor necessary to repair the
above described areas of erosion.
All work will be performed in accordance with the pertinent portions of the Special Provisions, Mn/DOT
Standard Specifications, Mn/DOT Standard Plates and as directed by the Engineer.
Payment to the Contractor for this work will be at the Mn/DOT 1904 Force Account, as shown below in the Estimate of
Cost:
ESTIMATE OF COST
Force Account
Description Amount
Erosion Repair Areas $4,500.00
Mn /DOT TP- 2460 - 0112 -92)
SHEET 2 OF 2 SHEETS
State of Minnesota - Department of Transportation
CHANGE ORDER # 18
State Project No.: 0280 -55
Contract No. Z07502
°Contractor: Lunda Construction Co.
Address: 15601 Clayton Avenue S.
Rosemount, MN 55068
Location: In Lino Lakes on CSAH 23 (Lake Dr.) From 1000 ft. south of Town Center Parkway to Apollo Dr.
In accordance with the terms of this Contract, you are hereby authorized and instructed to perform the Work as altered by the following provisions.
Distribution: S.P. 0280 -55 Group 01 — 100%
CHANGE IN CONTRACT TIME
Due to this change the Contract Time:
a. Is increased ( ) by Working Days
Is decreased ( ) by Working Days
Is increased ( ) by Calendar Days
Is decreased ( ) by Calendar Days
b. Is not changed (X )
Issued By:
Project/Resident/Q3unty Engineer Date
Approved By:
City of Lino Lakes
Date
Approved By:
c. May be revised if the work affected Anoka County
the controlling operation ( )
Date
Accepted By: ?-1 ®°C>%
Contractor's Authorized Representative Date
Original to Project Engineer; copies to Contractor, City of Lino Lakes, Anoka County
This Change Order is for known and anticipated
costs only. Should this change impact a controlling
item, schedule or work sequence, creating a delay or
an acceleration of the work, or cause us to incur
additional or indirect costs which are now unknown
and not anticipated, we reserve the right to an
additional adjustment in the contract price and/or
contract time. • Lupo /N CC r4sT_ CC-,
64k-- *It\-lar