CITY OF LINO LAKES
RESOLUTION NO. 09-99
APPROVING PAYMENT REQUEST NO. 2R (FINAL) AND
COMPENSATING CHANGE ORDER NO. 1, 2009 OVERLAY PROJECT
WHEREAS, pursuant to the resolution of the Council adopted April 27, 2009, awarding
the contract for 2009 Overlay Project to T.A. Schifsky and Sons, Inc.;
WHEREAS, a complete breakdown is detailed in Payment No. 2R (Final) and
Compensating Change Order No. 1;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
Payment Request No. 2R (Final) and Compensating Change Order No. 1 is
approved for a final contract amount of $157,286.30.
Adopted by the Lino Lakes City Council this 23rd day of November, 2009.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member Roeser and upon vote being taken thereon, the following voted in favor
thereof:
O'Donnell, Roeser, Reinert, Gallup, Bergeson
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
•
AGENDA ITEM 6Ei
STAFF ORIGINATOR: James E. Studenski, City Engineer
COUNCIL MEETING DATE: November 23, 2009
TOPIC: Resolution No. 09 -99, Approving Payment Request
No. 2R (Final) and Compensating Change Order
No. 1, 2009 Overlay Project.
Vote Required: Simple Majority
BACKGROUND:
At the April 27, 2009 meeting, City Council awarded the 2009 Overlay Project contract to
T.A. Schifsky and Sons, Inc.
The contractor for the 2009 Overlay Project, T.A. Schifsky and Sons, Inc., is requesting
City approval of Payment Request No. 2R (Final) in the amount of $10,454.68. A copy
of the Final Payment is attached. The contractor has satisfactorily completed all work
and has provided all necessary documentation.
Also included with the request for Final Payment is Compensating Change Order
No. 1 in the deduct amount of $1,175.70. A copy of the Compensating Change Order is
attached. With this Change Order, the final project amount is $157,286.30, which is
below the contract amount of $158,462.00.
Approval of the Final Payment will begin the one -year warranty period.
RECOMMENDATION:
Staff recommends the approval of Resolution No. 09 -99, Approving Payment Request
No. 2R (Final) and Compensating Change Order No. 1, 2009 Overlay Project.
TKDA
AK ENGINEERING • ARCHITECTURE • PLANNING
The right time. The right people. The right compare
UW
444 Cedar Street, Suite 1500
Saint Paul, MN 55101 -2140
(651) 292-4400
(651) 292 -0083 Fax
www.tkda.com
Proj. No. 14292.003 Cert. No. 2R (FINAL) St. Paul, MN, October 23 2009
To City of Lino Lakes, Minnesota
This Certifies that T.A. Schifsky & Sons, Inc.
For 2009 Overlay Project
Owner
, Contractor
Is entitled to Ten Thousand Four Hundred Fifty -Four Dollars and 68/100 ($ 10,454.68 )
FINAL
being 2nd estimate for paft-ial payment on contract with you dated April 27, 2009
Received ent
of
()mow( 2,ro
bove Certificate.
T.
. Schifsky & Sons, Inc.
, 20
TKDA
es E. Studenski, P.E.
RECAPITULATION OF ACCOUNT
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
CONTRACT
PLUS EXTRAS
PAYMENTS
CREDITS
Contract price plus extras
$
158,462.00
All previous payments
$
146,831.62
All previous credits
Extra No.
Compensating Chage Order No. 1
$
(1,175.70)
,,
Credit No.
$
„ „
„
AMOUNT OF THIS CERTIFICATE
$
10,454.68
Totals
$
157,286.30
$
157,286.30
$ -
Credit Balance
$
-
There will remain unpaid on contract after
payment of this Certificate
$
-
$
157,286.30
$
157,286.30
( $ -
An Employee Owned Company Promoting Affirmative Action and Equal Opportunity
•
TKDA
Engineering- Architecture - Planning
PERIODICAL ESTIMATE FOR PARTIAL PAYMENTS
FINAL
Estimate No. 2R Period Ending September 24 , 2009 Page 1 of 1 Proj. No. 14292.003
Contractor T. A. Schifsky.& Sons Inc. Original Contract Amount $158,462.00
Project 2009 Overlay Project
Location City of Lino Lakes, Minnesota
Total Contract Work Completed
Total Approved Credits
Total Approved Extra Work Completed $
Approved Extra Orders Amount Completed $ 0.00
Total Amount Earned This Estimate $ 157,286.30
$ 157,286.30
$ 0.00
0.00
Less Approved Credits
Less 0 % Retained
Less Previous Payments
Total Deductions
Amount Due This Estimate
Contractor
Engineer
T.A. Schifsky
James E. Studenski, P.E.
0.00
0.00
146,831.62
146,831.62
$ 10,454.68
Date f 2 z'c /
1
Date
ESTIMATE NO. 2R (FINAL)
PERIOD ENDING: September 24, 2009
09 OVERLAY PROJECT
OF LINO LAKES, MINNESOTA
DA PROJECT NO. 14292.003
ITEM CONTRACT QUANTITY UNIT AMOUNT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE
1 MOBILIZATION LS 1 1 $ 10,000.00 $ 10,000.00
2 RECLAIM BITUMINOUS SY 11,350 11,115 $ 0.55 $ 6,113.25
3 HAUL OUT EXCESS MILLINGS (LV) CY 630 389 $ 4.65 $ 1,808.85
4 RESHAPE MILLINGS (3% CROWN) RS 37 35 $ 67.50 $ 2,362.50
5 BITUMINOUS BASE COURSE 2360 (LVNW 35030) TN 1,380 1,420 $ 52.00 $ 73,840.00
6 BITUMINOUS WEARING COURSE 2360 (LVWE 45030) TN 1,110 1,095 $ 52.00 $ 56,940.00
7 BITUMINOUS MATERIAL FOR TACK COAT GAL 610 600 $ 2.25 $ 1,350.00
8 BITUMINOUS CURBING LF 520 469 $ 4.50 $ 2,110.50
9 SAWCUT BITUMINOUS DRIVEWAYS LF 100 136 $ 1.25 $ 170.00
10 REMOVE BITIMINOUS DRIVEWAY MATERIAL SY 100 0 $ 1.80 $
11 BIT. WEARING COURSE 2360 (LVWE 45030) (FOR DRIVES) SY 100 96 $ 13.45 $ 1,291.20
12 REHABILITATE CATCH BASINS EA 6 4 $ 325.00 $ 1,300.00
TOTAL $ 157,286.30
TOTAL ESTIMATE NO. 2R (FINAL) $ 157,286.30
•
•
•
CHANGE ORDER
TKDA
Engineers- Architects - Planners
Compensating
Saint Paul, MN September 24 2009 Proj. No. 14292.003 Change Order No. 1R
To T.A. Schfisky and Sons, Inc.
for 2009 Overlay Project
for City of Lino Lakes, Minnesota
You are hereby directed to make the following change to your contract dated
April 27 , 20 "09 . The change and the work affected thereby is subject to all contract stipulations and
covenants. This Change Order will (increase) (decrease) (age) the contract sum by
One Thousand One Hundred Seventy -Five Dollars and 70/100 ($ 1,175.70).
COMPENSATING CHANGE ORDER
This change order shows the actual quantities installed at the unit price bid amounts (see attached itemization):
NET CHANGE =
(1,175.70)
Amount of Original Contract $ 158,462.00
Additions approved to date (Nos. ) $
Deductions approved to date (Nos. ) $
Contract amount to date $ 158,462.00
Amount of this Change Order (Add) (Deduct) (age) $ (1,175.70)
Revised Contract Amount $ 157,286.30
Approved City of Lino Lakes
Owner
TKDA
By By -•-• —
es E. Studenski, P.E.
T.A. Schfisky and Sons, Inc.
Contractor
White - Owner
Pink - Contractor
Blue - TKDA
COMPENSATING CHANGE ORDER NO. 1R
PERIOD ENDING: September 24, 2009
2009 OVERLAY PROJECT
iiikOF LINO LAKES, MINNESOTA
DA PROJECT NO. 14292.003
ITEM CONTRACT QUANTITY UNIT AMOUNT NET CONTRACT
NO. DESCRIPTION UNIT QUANTITY TO DATE PRICE TO DATE CHANGE AMOUNT
1 MOBILIZATION LS 1 1 $ 10,000.00 $ 10,000.00 $ $ 10,000.00
2 RECLAIM BITUMINOUS SY 11,350 11,115 $ 0.55 $ 6,113.25 $ (129.25) $ 6,242.50
3 HAUL OUT EXCESS MILLINGS (LV) CY 630 389 $ 4.65 $ 1,808.85 $ (1,120.65) $ 2,929.50
4 RESHAPE MILLINGS (3% CROWN) RS 37 35 $ 67.50 $ 2,362.50 $ (135.00) $ 2,497.50
5 BITUMINOUS BASE COURSE 2360 (LVNW 35030) TN 1,380 1,420 $ 52.00 $ 73,840.00 $ 2,080.00 $ 71,760.00
6 BITUMINOUS WEARING COURSE 2360 (LVWE 45030) TN 1,110 1,095 $ 52.00 $ 56,940.00 $ (780.00) $ 57,720.00
7 BITUMINOUS MATERIAL FOR TACK COAT GAL 610 600 $ 2.25 $ 1,350.00 $ (22.50) $ 1,372.50
8 BITUMINOUS CURBING LF 520 469 $ 4.50 $ 2,110.50 $ (229.50) $ 2,340.00
9 SAWCUT BITUMINOUS DRIVEWAYS LF 100 136 $ 1.25 $ 170.00 $ 45.00 $ 125.00
10 REMOVE BITIMINOUS DRIVEWAY MATERIAL SY 100 0 $ 1.80 $ - $ (180.00) $ 180.00
11 BIT. WEARING COURSE 2360 (LVWE 45030) (FOR DRIVES) SY 100 96 $ 13.45 $ 1,291.20 $ (53.80) $ 1,345.00
12 REHABILITATE CATCH BASINS EA 6 4 $ 325.00 $ 1,300.00 $ (650.00) $ 1,950.00
TOTAL COMPENSATING CHANGE ORDER NO. 1R $ 157,286.30 $ (1,175.70) $ 158,462.00