HomeMy WebLinkAbout2009-004 Council ResolutionCouncil Member introduced the following resolution and moved its adoption: -btoltz CITY OF LINO LAKES RESOLUTION NO. 09 -04 RESOLUTION APPROVING CHANGE ORDER NO. 5 LEGACY AT WOODS EDGE PHASE 2 — STREETLIGHTING IMPROVEMENTS WHEREAS, pursuant to the resolution of the Council adopted April 24, 2006, awarding the construction contract for the Legacy at Woods Edge Phase 1 — Streetlighting Improvements to W.H. Response, and WHEREAS, W.H. Response was required to perform additional work required to mobilize and install Tight poles on the Lake Drive bridge over 35W due to anchor bolt pattern changes installed under Lake Drive contract by Lunda Construction Co. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LINO LAKES, MINNESOTA that: 1. Change Order No.5 in the amount of $2,625.31 is hereby approved. • Bartell, Cit C John . Ber. won, / ayor Adopted by the Lino Lakes City Council this 12th day of January, 2009. The motion for the adoption of the foregoing resolution was duly seconded by Council Member and upon vote being taken thereon, the following voted in favor thereof: Stoltz, Gallup, Bergeson (absent - O'Donnell, Reinert) The following voted against same: none Whereupon said resolution was declared duly passed and adopted. • • • • AGENDA ITEM 1 E STAFF ORIGINATOR: Michael Grochala CITY COUNCIL MEETING DATE: January 12, 2009 TOPIC: ACTION REQUIRED: BACKGROUND Resolution No. 09 -04, Approving Change Order No. 5, Legacy at Woods Edge Phase 2 — Streetlighting Improvements Simple Majority On April 24, 2006 the City Council awarded the Legacy at Woods Edge Phase 2 — Street lighting Improvements contract to W.H. Response. Change Order No. 5 is to compensate W.H. Response for additional work required to mobilize and install light poles on the Lake Drive bridge over 35W due to anchor bolt pattern changes installed under Lake Drive contract by Lunda Construction Co. RECOMMENDATION Staff is recommending the adoption of Resolution No. 09 -04, Approving Change Order No.5 in the amount of $2,625.31. ATTACHMENTS 1. Resolution No. 09 -04 2. Change Order No. 5 J • SEH CHANGE ORDER City of Lino Lakes, Minnesota December 15, 2008 • OWNER DATE OWNER'S PROJECT NO Legacy at Woods Edge - Phase 2 PROJECT DESCRIPTION 5 CHANGE ORDER NO. A- LINOL0305.03 SEH FILE NO. The following changes shall be made to the contract documents: Description: Additional Charges to Complete Lake Drive Lighting • Additional mobilization $725.00 • Traffic control on 35W $822.00 • Traffic control on Lake Drive $517.86 • Modify bridge pole adapter plates $560.45 • Total for this work $2,625.31 Total Cost: $2,625.31 Purpose of Change Order: Additional work required to mobilize and install light poles on the Lake Drive bridge over 35W due to anchor bolt pattern changes installed under Lake Drive contract. Basis of Cost: ® Actual ❑ Estimated Attachments (list supporting documents) Details of work completed for Change Order #4 Contract Status Original Contract Net Change Prior C. O. 's 1 to 4 Change this C.O. Revised Contract Time N/A Recommended for Approval: Short Elliott Hendrickson Inc. by Agreed to by Contractor: Cost $483,135.84 $153,504.41 $2,625.31 $639,265.56 Susan Mason /Project Manager Approved for Owner: BY Signature Lighting Inc. BY City of Lino Lakes, Minnesota TITLE TITLE Distribution Contractor 2 Owner 1 Project Representative 1 SEH Office 1 s:\ko \I \linol\ 030503 \legacyph2 \constphase \co #5.doc 1/04 Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110 -5196 SEH is an equal opportunity employer 1 www.sehinc.com 1 651.490.2000 1 800.325.2055 1 651.490.2150 fax