HomeMy WebLinkAbout2009-004 Council ResolutionCouncil Member introduced the following resolution and moved its adoption:
-btoltz
CITY OF LINO LAKES
RESOLUTION NO. 09 -04
RESOLUTION APPROVING CHANGE ORDER NO. 5
LEGACY AT WOODS EDGE PHASE 2 — STREETLIGHTING IMPROVEMENTS
WHEREAS, pursuant to the resolution of the Council adopted April 24, 2006, awarding
the construction contract for the Legacy at Woods Edge Phase 1 — Streetlighting
Improvements to W.H. Response, and
WHEREAS, W.H. Response was required to perform additional work required to
mobilize and install Tight poles on the Lake Drive bridge over 35W due to anchor bolt
pattern changes installed under Lake Drive contract by Lunda Construction Co.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA that:
1. Change Order No.5 in the amount of $2,625.31 is hereby approved.
•
Bartell, Cit C
John . Ber. won, / ayor
Adopted by the Lino Lakes City Council this 12th day of January, 2009.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member and upon vote being taken thereon, the following voted in favor
thereof:
Stoltz, Gallup, Bergeson (absent - O'Donnell, Reinert)
The following voted against same:
none
Whereupon said resolution was declared duly passed and adopted.
•
•
•
•
AGENDA ITEM 1 E
STAFF ORIGINATOR: Michael Grochala
CITY COUNCIL
MEETING DATE: January 12, 2009
TOPIC:
ACTION REQUIRED:
BACKGROUND
Resolution No. 09 -04, Approving Change Order No.
5, Legacy at Woods Edge Phase 2 — Streetlighting
Improvements
Simple Majority
On April 24, 2006 the City Council awarded the Legacy at Woods Edge Phase 2 —
Street lighting Improvements contract to W.H. Response.
Change Order No. 5 is to compensate W.H. Response for additional work required to
mobilize and install light poles on the Lake Drive bridge over 35W due to anchor bolt
pattern changes installed under Lake Drive contract by Lunda Construction Co.
RECOMMENDATION
Staff is recommending the adoption of Resolution No. 09 -04, Approving Change Order
No.5 in the amount of $2,625.31.
ATTACHMENTS
1. Resolution No. 09 -04
2. Change Order No. 5
J
• SEH CHANGE ORDER
City of Lino Lakes, Minnesota December 15, 2008
•
OWNER DATE
OWNER'S PROJECT NO
Legacy at Woods Edge - Phase 2
PROJECT DESCRIPTION
5
CHANGE ORDER NO.
A- LINOL0305.03
SEH FILE NO.
The following changes shall be made to the contract documents:
Description:
Additional Charges to Complete Lake Drive Lighting
• Additional mobilization $725.00
• Traffic control on 35W $822.00
• Traffic control on Lake Drive $517.86
• Modify bridge pole adapter plates $560.45
• Total for this work $2,625.31
Total Cost: $2,625.31
Purpose of Change Order:
Additional work required to mobilize and install light poles on the Lake Drive bridge over 35W due to
anchor bolt pattern changes installed under Lake Drive contract.
Basis of Cost: ® Actual ❑ Estimated
Attachments (list supporting documents)
Details of work completed for Change Order #4
Contract Status
Original Contract
Net Change Prior C. O. 's 1 to 4
Change this C.O.
Revised Contract
Time
N/A
Recommended for Approval: Short Elliott Hendrickson Inc. by
Agreed to by Contractor:
Cost
$483,135.84
$153,504.41
$2,625.31
$639,265.56
Susan Mason /Project Manager
Approved for Owner:
BY Signature Lighting Inc. BY City of Lino Lakes, Minnesota
TITLE TITLE
Distribution Contractor 2 Owner 1 Project Representative 1 SEH Office 1
s:\ko \I \linol\ 030503 \legacyph2 \constphase \co #5.doc 1/04