HomeMy WebLinkAbout2009-048 Council Resolution•
•
•
Council Member ' -b I z. introduced the following resolution and moved its
adoption:
CITY OF LINO LAKES
RESOLUTION NO. 09 -48
APPROVING THE 2009/2010 WORK SCHEDULE FOR FOXBOROUGH
CONSERVATION AREAS AND TO DISBURSE FOXBOROUGH CONSERVATION
MANAGEMENT STEWARDSHIP FUNDS FOR 2009
WHEREAS, Foxborough is a conservation development that set up a stewardship fund
for managing conservation easement areas set aside within the geographic limits of the
development; and
WHEREAS, The fund has an existing available balance of $12,690 for 2009; and
WHEREAS, The City received a proposed work plan describing work in 2009 and 2010;
and
WHEREAS, Proposed work plans are consistent with an approved Restoration and
Management Plan, and has been reviewed by the City of Lino Lakes Environmental
Board; and
WHEREAS, The cost of proposed work in the 2009 work plan totals $12,690; and
WHEREAS, The Lino Lakes Environmental Board reviewed the proposed costs and
work plan for Foxborough conservation areas on June 24, 2009 and recommended to
the City Council that all proposed tasks and costs be approved for 2009.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
The City Council approves the release to the Foxborough Homeowners Association an
amount of $12,690 from the stewardship fund for work completed in 2009 described as
Tasks 1 -6 in the work plan dated June 18, 2009 and
BE IT FURTHER RESOLVED THAT The City Council approves the proposed work for
2009 and 2010 as prepared by Jason Husveth, Critical Connections Ecological
Services, Inc. dated June 18, 2009, and that completed work in 2009 shall be reviewed
before the City approves the release of funds for those tasks.
•
Bartell, City Clerk
Adopted by the Lino Lakes City Council this 27th day of July 2009.
The motion for the adoption of the foregoing resolution was duly seconded by Council
Member Ball u&.p and upon vote being taken thereon, the following voted in favor
thereof:
Sio l +z, Ga.tla+ O' Donnell, Re s riert, 6e1esoo
The following voted against same:
no
Whereupon said resolution was declared duly passed and adopted.
•
•
Natural
Resource
Consulting
Landscape
Ecology
Botanical
Inventories
Critical Connections Ecological Services, Inc.
14760 Oakhill Road, Scandia, Minnesota 55073
Threatened &
Endangered
Species Surveys
Greenway &
Open Space
Planning
Natural
Community
Restoration
•ettand
Delineation &
Permitting
Wetland
Banking &
Monitoring
Minnesota
Land Cover
Classification
Geographic
Information
Systems
Global
Positioning
Systems
Database
Management &
Development
Environmental
Education
Mr. Marty Asleson
Natural Resources Specialist
City of Lino Lakes
600 Town Center Parkway
Lino Lakes, Minnesota 55014
June 18, 2009
Mr. Marcel Eibensteiner
Royal Oaks Realty
1000 County Road E, Suite 150
Shoreview, Minnesota 55126
Re: Foxborough Conservation Development, Lino Lakes, Minnesota
Restoration and Management Planning for the 2009 and 2010
Dear Mr. Asleson and Mr. Black:
At the request of the Foxborough Homeowner's Association and Royal Oaks Realty (ROR),
Critical Connections Ecological Services, Inc (CCES) prepared the following proposed scope of
work for ecological restoration and management of Foxborough conservation outlots in from
2009 and 2010. Proposed tasks and priorities were developed from CCES's past experience
implementing restoration and management tasks at Foxborough (2005- 2008), conversations
and site visits with City staff, and in accordance with the Foxborough Restoration and
Management Plan (CCES, August 2005). The proposed restoration and management tasks
will be implemented during from July 2009 through December 2010. The proposed scope of
work and prioritization of tasks are based on available funding within the Foxborough
Conservation Fund. The City of Lino Lakes has recently informed CCES that available funding
is as follows: $4.279f30 for 2009, and $6,700 far 2010; a total of $19,660 for July 2009 through
December 2010.4 12,1090
The following proposed tasks, timelines, costs, and priorities constitute the proposed scope
of work for 2009 and 2010 within Foxborough's conservation outlots.
2009 Proposed Restoration and Management Tasks:
Task 1: Management and Removal of Buckthorn
CCES restoration crews will manage and treat remaining areas of buckthorn infestation and
resprout. The primary areas to be treated include the northeast corner of the development,
along the trail corridor, and within the aspen woodlands of the southern portion of the site.
CCES restoration crews will cut and remove buckthorn brush, and chemically treat the cut
stumps with Glyphosate herbicide.
Phone: 651.433.4410 Fax: 651.433.4528
Email: info @ccesinc.com Web: www.ccesinc.com
Foxborough Conservation Development, Lino Lakes, Minnesota
Proposed Restoration and Management for 2009 and 2010
Scope of Work and Cost Estimate
Critical Connections Ecological Services, Inc.
Task 1 Timeline: July through December 2009
Task 1 Costs: $5,200 (Labor and Herbicide)
Page 2 of 3
Task 2: Management of Reed Canary Grass
CCES restoration crews will mow and herbicide reed canary grass within select areas of the Foxborough
conservation outlots. Reed canary grass will be treated within the northern wetland fringe and uplands
of the wetland mitigation area, in natural wetlands along the trail corridor, and within stormwater
basins that have been seeded with native species in past years. Reed canary grass will be treated with
Glyphosate herbicide when it occurs in monotypic stands, and Sethoxydim (grass specific) herbicide
when it occurs intermittently with other desirable native species.
Task 2 Timeline:
Task 2 Costs:
July through October 2009
$3,200 (Labor and Herbicide)
Task 3: Management of Invasive Cattails
Invasive cattails (Typha angustifolia and Typha X glauca) will be managed within stormwater basins of
within the Foxborough conservation outlots. Invasive cattails are becoming problematic within these
basins, and threaten to out - compete native species that were seeded into the basins in previous years.
Invasive cattails will be cut, and treated with Glyphosate herbicide.
Task 3 Timeline: July through October 2009
Task 3 Costs: $2,250 (Labor and Herbicide)
Task 4: Management of Other Invasive Species and Noxious Weeds
Other noxious weeds, such as Canada thistle, birds -foot trefoil, and yellow and white sweet clover, will
be chemically treated by CCES restoration crews within the Foxborough conservation outlots. These
species are particularly problematic along the trail corridor, where they are gaining a foothold from past
grading and trail construction. CCES restoration crews will chemically treat these other invasive species
with Glyphosate based herbicides (such as Roundup).
Task 4 Timeline: July 2009 through October 2010
Task 4 Costs: $1,800 (Labor and Herbicide)
Task 5: Removal of Non - Functioning Silt Fence
Damaged and non - functioning silt fence within the Foxborough conservation outlots will be removed by
CCES restoration crews. Functioning silt fences will be left in place, and reinforced if necessary.
Task 4 Timeline: July through October 2009
Task 4 Costs: $790 (Labor and Removal)
•
•
•
•
Foxborough Conservation Development, Lino Lakes, Minnesota
Proposed Restoration and Management for 2009 and 2010
Scope of Work and Cost Estimate
Critical Connections Ecological Services, Inc.
Page 3 of 3
Task 6: Project Management and Reporting
CCES will manage the implementation of proposed tasks for 2009. Jason Husveth (CCES's Principal
Ecologist) will report to and coordinate with City staff, the Lino Lakes Environmental Board, and the
Foxborough Homeowners Association to inform these constituents of work completed. CCES has
budgeted six (6) hours of Mr. Husveth's time to perform this task.
Task 6 Timeline: July 2009 through December 2010
Task 6 Costs: $720 (Consulting Hours)
2010 Proposed Restoration and Management Tasks:
Task 7: Prescribed Burn of Selected Habitats within Conservation Outlots
CCES will perform a spring prescribed burn within up to 10 acres of the Foxborough conservation
outlots. Prescribed burning will focus on habitats that were not burned in 2007 and /or have the
greatest ecological need for a prescribed burn. CCES will prepare a burning permit application, obtain
the permits, and prepare all burn units for prescribed burning (Le. create burn breaks and isolate burn
units). The burn will be implemented in April or May 2010. If the burn cannot be implement in the
spring of 2010 (due to weather constraints), CCES will implement the burn in October 2010.
Task 7 Timeline: July 2009 through December 2010
Task 7 Costs: $5,700 (Consulting, Labor, Materials, and Equipment)
Total Costs Tasks 1 through 7: $19,660.00
Thank you for reviewing this proposed scope of work for the Foxborough conservation development.
Please feel free to contact Jason Husveth (CCES Principal Ecologist) if you have any questions or require
additional information. We hope this proposal meets your approval, and that we can begin
implementation as soon as possible.
Respectfully submitted,
Critical Connections Ecological Services, Inc.
Ja - J. Husv
rincipal Ecologist
•
•
•
STAFF ORIGINATOR:
MEETING DATE:
TOPIC:
VOTE REQUIRED:
BACKGROUND
AGENDA ITEM 6C
Marty Asleson
July 27, 2009
Resolution No. 09 -48, Approving the 2009/2010
Management Plan for Conservation Areas in Foxborough
and the Disbursement of Foxborough Conservation
Management Stewardship Funds for work completed in 2009
3/5
The Foxborough Development was approved on August 22, 2005. Foxborough is a
conservation development that set up a stewardship fund for implementing the
management plan for conservation easement areas set aside within the geographic
limits of the development. Covenants and restrictions have been written subjecting all
those who purchase property in Foxborough to a Homeowners Association with
conservation easement use restrictions, yearly management work plan approvals by the
City, and annual fees for the maintenance of conservation areas.
The Conservation Fund for Foxborough consists of a $100,000 endowment established
by the developer, and annual fees of $100 per lot. Yearly Interest from the $100,000
endowment plus the annual $100 per lot Homeowners Association fee establishes the
amount of money available to manage conservation easement areas in Foxborough.
There are 57 lots within Foxborough. The annual contribution by the Homeowners
Association is $5,700 plus interest accrued. The Homeowners Association is
responsible for collecting the funds and the City maintains the collected funds in a
designated account. Until sufficient lots are sold within the development, the Developer
acts as the Homeowner's Association and has paid dues for 2009. The dues, together
with interest from the endowment fund, establish an available fund balance of $12,690
for 2009.
As part of Foxborough Development approvals, a Restoration and Management Plan
was required that laid out typical work schedules for the conservation areas. Each year,
the Homeowners Association must hire an ecologist to make recommendations
concerning the management of the Foxborough Conservation Areas relative to the plan
and monies available. Proposed work plans submitted to the City by the Homeowners
Association, which are the product of the ecologist's analysis, are reviewed by the
Environmental Board. The Environmental Board then makes a recommendation to the
City Council concerning the annual work plan. A similar process is followed to review
•
•
completed work for approving the transfer of money from the Foxborough Stewardship
fund to the Homeowners Association to pay for the completed work.
Attachment 1 is the report dated June 18, 2009 completed by Jason Husveth of Critical
Connections. Mr. Husveth is the ecologist hired by the Association (Royal Oaks Realty)
to make management recommendations. Recommendations are for the proposed work
plan for 2009 and 2010. The City of Lino Lakes Environmental Board reviewed the
report from Critical Connections and the Foxborough Homeowners Association
(presently Royal Oaks Realty) at the June 24, 2009 Environmental Board meeting. The
Environmental Board made a recommendation that the proposed work schedule for
2009 and 2010 be approved and stewardship funds released upon completion of
proposed tasks for 2009 only. Resolution No. 09 -48 approves the release of $12,690
for work completed in 2009. It also approves the work plan for 2010.
RECOMMENDATION
1. Approve adoption of Resolution No. 09 -48, approving the 2009/ 2010 work plan for
Foxborough conservation areas, and the release of $12,690 from the stewardship
fund for work done in 2009.
2. Refer back to the Environmental Board for further consideration.
ATTACHMENTS
1. Resolution No. 09 -48, Approving the 2009/2010 work plan for Foxborough
conservation areas in Foxborough and the Disbursement of Foxborough
Conservation Funds for Work Completed in 2009.
2. Critical Connections Proposed Work Plan for 2009 and 2010.