RESOLUTION NO. 10 -32
RESOLUTION AUTHORIZING PREPARATION OF SIGNAL JUSTIFICATION
REPORTS FOR THE BIRCH ST/WARE ROAD INTERSECTION AND THE LAKE
DRIVE /MAIN STREET INTERSECTION
WHEREAS, the intersections of Lake Drive and Main Street; and Birch Street and Ware
Road are currently experiencing growing congestion and safety problems; and
WHEREAS, the City has previously received requests from residents to consider the
signalization of both intersections; and
WHEREAS, the city is proposing to prepare Signal Justification Reports to determine if
traffic signal improvements are warranted to improve safety and relieve congestion at
each intersection.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
LINO LAKES, MINNESOTA:
1. That preparation of Signal Justification Reports for the Lake Drive /Main Street
intersection and the Birch StreetNVare Road intersection is hereby authorized.
2. That the staff is hereby authorized to enter into a professional services
agreement with TKDA, the city e - , for tr= - •aration of said reports, in
the not to exceed amount of ', 1,000 total •oth reports.
ATTES
Juliann: Bartell, City Jerk
Jeff Rein- , rayor
Adopted by the Lino Lakes City Council this 12th day of April, 2010.
The motio for the adoption of the foregoing resolution was duly seconded by Council
Member `l a e se r- and upon vote being taken thereon, the following voted
in favor thereof:
I1 ,4r, 'Roe S r �fine-kt
The following voted against same:
11\10 Vt_e_ 010 s-e wt - 6' o✓i.vt e it , Ra *-V er "tY )
Whereupon said resolution was declared duly passed and adopted.
•
•
STAFF ORIGINATOR:
CITY COUNCIL
MEETING DATE:
TOPIC:
ACTION REQUIRED:
BACKGROUND
AGENDA ITEM 6G
Michael Grochala
April 12, 2010
Consider Resolution No. 10 -32, Authorizing
Preparation of Signal Justification Reports for the
Birch St./Ware Road & Lake Drive /Main Street
Intersections
3/5
The City has previously received requests from residents to consider the signalization of
the Lake Drive /Main Street intersection and the Birch StreetNVare Road intersection.
Both intersections are experiencing growing congestion and safety problems.
The preparation of a Signal Justification Report (SJR) is required when considering the
installation of a new signal system. The purpose of the report is to evaluate the existing
and proposed traffic conditions of the intersection and insure that the traffic signal will
improve the traffic flows and safety of the intersection.
TKDA, the city's consulting engineer, has estimated the cost of completing the two
reports at $6,800 to $10,000. The cost range reflects additional steps in the process
that may need to be undertaken based on the initial analysis.
No funding was programmed in the 2010 budget for the preparation of these reports.
Staff would recommend that the council appropriate funding for the studies from the
contingency fund at this time. If the projects proceed to construction and a permanent
funding source is determined the costs can then be reimbursed.
Once the SJR's are completed and a determination has been made on the whether the
signal systems should be installed, a separate feasibility study will need to be
commenced to determined the scope and costs of the improvement. Staff will
coordinate and work with Anoka County on the possible intersection improvements
throughout the process.
RECOMMENDATION
Staff is recommending approval of Resolution No. 10 -32
ATTACHMENTS
• 1. Resolution No. 10 -32